1 Project Management Critical Path Analysis Practice-Uploader TaskOptimisticRealisticPessimisticPERTPredecessors A35156.3None B37147.5None C34104.83None D69129A,B E4696.17B,C F7141513C G7121812.17D,F H59139G,F PERT is given the formula = Optimistic time + (4 * Realistic time) + Pessimistic time /6 1.What is the shortest possible duration for this project? The shortest possible time is the PERT weighted average time which is (6.3+7.5+4.83+9+6.17+13+12.17+9) = 67.97 days 2.What sequence of tasks form the critical path? ADBECFGH 3.How much free float (=slack) can be found in task F? One day 4.Once the project begins, it is assumed that task A takes 10 days instead of the estimated 6.3 days. Assuming all other tasks are completed on time, how long will the project take? The project will take (10+7.5+4.83+9+6.17+13+12.17+9) = 71.67 days
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
2 Discussion Question #4inital prompt Critical path is the longest path taken from the start of the project to the end.Any activity on the critical path cannot be moved to the next not until the predecessor activity has been accomplished. Therefore, in my view CPM does not assume infinite resources when creating the initial project network because one has to determine the longest path by involving all activities to identify the longest path (Kerzner, H., & Kerzner, H. R,2017). For real world project critical path is a smart assumption because CPM does not move to the next activity until the predecessor is completed, which means there is no single activity that will be delayed. Response prompt Response to Saruta Alvarez-Balseca I agree with you that critical path method is a step-by-step technique that has to be accomplished prior to the project completion. However, critical path is the longest path that the path that takes the longest time from the commencement of the project to completion. I also agree with your definition as the shortest path through a project. Once there is a delay in one or more activities on the critical path, then the entire project will be delayed. Indeed, the critical path method is a significant tool to project management because it effectively helps in managing different task by scheduling them accordingly and keeping track of all activities by displaying them in a network diagram. The network diagram uses arrows that link project activities which are represented as nodes. Response to MeChell Hays Indeed, critical path method (CPM) maps the critical steps in a project, it is not necessarily supposed to be a complex project but any project by illustrating the sequence of
3 activities. CPM takes the longest path starting from the first activity to the end, hence it can be used to determine the duration of the project. Any activity on the critical path cannot be moved to the next not until the predecessor activity has been accomplished. However, if the activity is delayed for a specified number of days say three days, the whole project will be delayed for those three days not unless the activity following the delayed one is completed three days earlier. The critical path is a significant tool in a project because it aids to manage any project type. Once CPM has been identified, it becomes clear to know where the efforts can be compromised.
4 Learning Journal # Summary During the fourth week of my course learning about essential of project management, I learned a number of significant information. To begin with, the information taught during this time is not only useful to my academic excellence in the course but also in my future endeavours as a project manager. During the project I learnt that project management is the ability for one to apply skills, knowledge, tools and techniques to different project activities so that to be in a position to realize and even exceed the needs and expectations of stakeholders from a project. Secondly, I learned that any successful project commences will planning. After planning as a project manager one then develops the project schedule with the aid of six critical process that is defining the project scope, conducting work breakdown, developing estimate for tasks, precedence programming, conducting critical path analysis and developing the schedule (Kerzner, H., & Kerzner H. R., 2017). The project plan is created by combining the project schedule together with other information. The work breakdown allow the project manager with the ability to arrange information in form of “spreadsheet-like” software tools, which allow the manager to include task dependencies, add durations and resources. Various project management software tools are used to split the task into small manageable activities such as Microsoft Project, Primavera Project and Zoho Project (Harrison, & Lock, 2017). The use of software tools in project management has both advantages and disadvantages. Some of the advantages of using software tools include It has helps in setting up and managing complicated projects It allow the project manager the opportunity to view and track the project periodically with the software performing complicated work. It integrates significant project management data from different sources.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
5 Offers resources management tools The disadvantages of using software tools include: It may be challenging to learn how to use these tools. When wrong information is fed into the software, it will automatically provide faulty information. Nonetheless, despite the software tools having some drawbacks it is highly recommended that all projects are run with the help of a software. The use of software tools allow the manager to work effectively on even the most complex projects particularly when it comes to computing budgets and critical paths. Application After learning and acquired several skills and information regarding project management it will apply these skills in my professional life in a number of ways. First, in my professional life as a project manager before starting any project that I will given responsibility to lead the first step will always be planning. Project planning helps the project manager to seek for relevant information on how to solve a problem. Planning will enable me to identify the problem to solved. After I have identified the problem to be resolved, the next step will be to explore the necessary resources, equipment and the duration needed to complete the project to resolve the problem. The next step after presenting the necessary project requirements is to breakdown the project into small manageable activities using a software tool such as Zoho Project or Microsoft Project. Once I will have divided the project tasks into small activities I will then develop time estimate taken to complete each task. In order to successfully schedule my project activities I will apply the critical path analysis knowledge. Critical path is a strategy that help in ensuring that the project meets the deadline. Critical path analysis entails several steps such as: Splitting the projects into tasks
6 Estimating tasks Creating a network diagram Draw an initial Gantt chart Conduct resource levelling Compress the schedule. The critical path is significant because through it I will be in a position to perform a program evaluation and review technique. PERT is a vital planning tool in project management because it helps the project manager to come up with the most realistic time that a project will take to be complete. This techniques is significant because it makes the work of the project manager to become easier in terms of scheduling and coordination of project teams. Challenges The major challenge that I experienced during this week’s material is planning the progress of the project. Planning involves a range of steps such as defining scope, conducting work breakdown, and estimating time that each task will take. Indeed, the planning process is a hard process because it determine all the follow up project activities, which is challenging because failure to plan well it will result in chaos as the project progress. I was able to resolve the problem of planning different task by using project management software tools like Microsoft project and Zoho Project. Microsoft project plays a significant role in project management because it helps the manager in the development of the project schedule, allocation of resources to every task, managing the budget, tracking the progress of the project and analysing workloads (Newcomer, Hatry, & Wholey, 2015). Determining the time taken to complete a project was another challenging part during this week’s material. In order to determine the duration that a project will take to be accomplished was not an easy task; I had to seek the help of Program Evaluation Review Technique (PERT). PERT is a project management estimation technique that illustrates the time taken by each task as well as the total time needed to complete the project. PERT works by splitting the project into activities and events and then lays down a sequence, connection and the time taken to form the network. The lines
7 that link all the project events are referred to as paths (Meredith, Mantel Jr, & Shafer, 2017). The longest path that results from all the events is known as critical path. To find the duration of the project the critical path is used. When there is any delay to the critical path, it leads to the whole project delaying. Therefore, I was able to understand how to calculate the time taken to complete a project with the help of PERT. Questions (2 bullet points) There are various type of project management software that we have discussed about in the course such as Zoho Project, Microsoft Project and primavera Project. Among the three software which is the best for use in complex projects? What is the difference between the three software management projects? Based on this week’s material PERT is regarded as the best technique for determining the duration taken by the project. What are some of the challenges that a project manager is likely to experience chaklenges when using PERT to estimate the duration of a project.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
8 Case Study Assignment D-Uploader Activity NameActivityPredecessors Project planning activitiesANone Project controlBA Measure current demandCA Predict future demandDC Understand type, levels, reasons EA Brainstorm metricsFC,E Construct modelsGD,F Develop post-tactical org model HG Develop 3-5 scenarios (model)IH Select best scenarios (Model)JI Develop org future stateKJ Needs analysisLG Build staff transaction plansMH,L Develop communication plansNM Develop communicationON
9 materials Develop training planPM Engage support areasQL Engage tech teamsRL Hire train and install staffSM,Q,R Launch communicationsTO Measure actual vs. metricsUS,T Adjust staffing as neededVU Project closure activitiesWA,B,V Critical path ACDGHIJLMNOTUVW References
10 Meredith, J. R., Mantel Jr, S. J., & Shafer, S. M. (2017).Project management: a managerial approach. New York: John Wiley & Sons. Newcomer, K. E., Hatry, H. P., & Wholey, J. S. (Eds.). (2015).Handbook of practical program evaluation. San Francisco, CA: Jossey-Bass & Pfeiffer Imprints, Wiley. Kerzner, H., & Kerzner, H. R. (2017).Project management: a systems approach to planning, scheduling, and controlling. New York: John Wiley & Sons. Harrison, F., & Lock, D. (2017).Advanced project management: a structured approach. London: Routledge.