24Make menu222 25Test foods and drinks231 26Development--4 27Hiring and training256 28Create an employee profile263 29Recruiting275 30Advertising2814 31Interviews295 32Hiring staff304 33Onboarding training staff31,8,1620 34Provide feedback--1 35Monitoring performance of staff334 36Marketing plan3414 37Define scope353 38Define target audience362 39Pricing strategy374 40Promotional plan38,67 41Marketing budget398 41Risk management610 42Competitive analysis4115 43SWOT analysis42,324 44VIP pre gang opening4311 45Make a guest list432 46Schedule443
47Setting the budget462 48Project Management4710 The critical path is from work activities #8 → 9 → 10 → 2 → 3 → 5 → 12 → 5 → 13 → 14 → 17 → 33 → 42 → 43 → 46 → 47 → 48. If any delays happen along this path, the entire project will be delayed as a result.