Activity #. Description. Predecessor(s). Duration(days)

Develop a project management plan for the relocation of Burnaby Hospital, including upgrading roadways, sidewalks, and helipad with new advanced technology.

8 Pages326 Words49 Views
   

Added on  2022-11-28

Activity #. Description. Predecessor(s). Duration(days)

Develop a project management plan for the relocation of Burnaby Hospital, including upgrading roadways, sidewalks, and helipad with new advanced technology.

   Added on 2022-11-28

ShareRelated Documents
Activity
#
Description Predecessor(s) Duration(days)
1 Store renovation -- 2
2 Proper approval of permissions 1 1
3 Pour foundation 11,2 7
4 Financial plan 3 8
5 Color schemes 4 2
6 Finalize 13 2
7 Furniture placement 6 1
8 Window treatment 7,14 3
9 Lightning -- 1
10 Installation of equipment 9 1
11 Find suppliers 10 4
12 Look for equipment 11 6
13 Negotiate 12,5 2
14 Purchase equipment 6 5
15 Test equipment 14 3
16 Install equipment 15 5
17 Development -- 3
18 Expert judgement 17 7
20 Determine market needs 18 14
21 Identify economic factors 19 7
22 Consumer research 20 6
23 Identify and prioritize the food
platform
21 3
Activity #. Description. Predecessor(s). Duration(days)_1
24 Make menu 22 2
25 Test foods and drinks 23 1
26 Development -- 4
27 Hiring and training 25 6
28 Create an employee profile 26 3
29 Recruiting 27 5
30 Advertising 28 14
31 Interviews 29 5
32 Hiring staff 30 4
33 Onboarding training staff 31,8,16 20
34 Provide feedback -- 1
35 Monitoring performance of staff 33 4
36 Marketing plan 34 14
37 Define scope 35 3
38 Define target audience 36 2
39 Pricing strategy 37 4
40 Promotional plan 38,6 7
41 Marketing budget 39 8
41 Risk management 6 10
42 Competitive analysis 41 15
43 SWOT analysis 42,32 4
44 VIP pre gang opening 43 11
45 Make a guest list 43 2
46 Schedule 44 3
Activity #. Description. Predecessor(s). Duration(days)_2
47 Setting the budget 46 2
48 Project Management 47 10
The critical path is from work activities #8 → 9 → 10 → 2 → 3 → 5 → 12 → 5 →
13 → 14 → 17 → 33 → 42 → 43 → 46 → 47 → 48.
If any delays happen along this path, the entire project will be delayed as a
result.
Activity #. Description. Predecessor(s). Duration(days)_3

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
A Catalogue of Bicycles (A 47)
|2
|156
|360

Design and FEA Analysis of Connecting Rod for Engine
|50
|4240
|265

DATE, FLOAT AND CRITICAL PATH CALCULATION.
|2
|235
|39

European History : Assignment
|160
|34211
|69

Statistics - Variable List, Histogram, Descriptive Statistics, Pivot Table and Bar Chart
|8
|1287
|69

Business Law Case: Unison Finance Group Pty Ltd v Electric Life Pty
|77
|12861
|65