Advantage Energy Technology Data Center Migration

   

Added on  2021-04-20

14 Pages1946 Words307 Views
 | 
 | 
 | 
Running head: PROJCET MANAGEMENT REPORTProject Management Report: Advantage Energy Technology Data Center MigrationName of the Student:Student ID:Name of the University:Author’s note:
Advantage Energy Technology Data Center Migration_1

1PROJCET MANAGEMENT REPORTTable of Contents1. Importance of accurate estimates for project management.....................................................22. Difference between bottom up and top down estimation........................................................23. Major types of costs.................................................................................................................24. White elephant in project management...................................................................................35. Connection between WBS and project networks....................................................................36. Requirement of WBS construction..........................................................................................67. Importance of Slack in project.................................................................................................78. Difference between free and total slack...................................................................................79. Uses of Lags in project network..............................................................................................710. Hammock Activity.................................................................................................................7Section 2: Project Plan.....................................................................................................................81. Implementation Plan................................................................................................................82. Project Budget Estimation.....................................................................................................103. Project Matrix........................................................................................................................114. Network Diagram..................................................................................................................115. Estimated Techniques used....................................................................................................116. Project Timeline.....................................................................................................................12Bibliography..................................................................................................................................14
Advantage Energy Technology Data Center Migration_2

2PROJCET MANAGEMENT REPORT1. Importance of accurate estimates for project managementThe accurate estimates help in project management of Advantage Energy TechnologyData Center Migration would help in calculating and developing the project plan comprising ofactivities of the network development project. The accurate estimation would help in,a)Development of accurate project budget and schedule for the project b)Implementation of the changes in accordance of the project activitiesc)Estimating the working duration for each of the activities2. Difference between bottom up and top down estimationThe comparison for the bottom up and top down estimation for the project of AdvantageEnergy Technology Data Center Migration is based on their major functions. The bottom upapproach relies on the identification of the project team members involved in the project forcalculating the expense. On the other hand the top down approach works by defining the tasks ofthe project and forming clear insights of the operations. For example, for project of upgradationof hardware is a project that would be completed using top down approach and the new projectsinvolve the use of top down approach for settling the project activities. 3. Major types of costsThe major types of costs expended on the project of Advantage Energy Technology DataCenter Migration are labour costs, tools costs, construction costs, and material costs. The labourcosts is the major costs of the project as it involves the calculation of the overall work duration ofthe resource and multiply it with the standard rate of the resource.
Advantage Energy Technology Data Center Migration_3

3PROJCET MANAGEMENT REPORTLabour cost: The labour include all the costs and expenses of the project activities paidin terms of the salaries and wages of the people working on the project.Non-labour costs: The non labour costs comprise of tools costs, construction costs, andmaterial costs that are not entitled for any human resources utilization for the deployment of theproject activities.The project manager is in charge of managing the costs of labour with the help ofcontracts and agreements, procurement, and limitation of the resource utilization. 4. White elephant in project managementWhite elephant is a term that is used for representing a business that is more likely forgeneration of loss and unable to achieve the profits on its completion. The white elephant can beassigned to social projects lie clearing of the locality, provision of the street lights, and parkmowing are all a part of white elephant project. 5. Connection between WBS and project networksThe work breakdown structure or WBS is a major representation of the project plan in asequential diagram that can be helpful for the deployment of the project networks. The WBSrepresents the work packages of the project and the project networks are built for representationof the activities grouped into specific phases. The project networks are deployed by consideringa block diagram that would be helpful for listing the activities of the project in a more specificline. The deployment of the WBS diagram would ease in listing the final project networkdiagram development. Task NameProjeFacilOperTelecommuSysteContraVenCityCli
Advantage Energy Technology Data Center Migration_4

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Project Management Assignment
|13
|2922
|486

Project Management Assignment - Accurate Estimates, WBS, Gantt Chart
|11
|2342
|476

Project Portfolio Management : Assignment
|44
|2950
|305

Managing Projects and Technologies for Business Students
|9
|2550
|53

WBS and Cost Budget Estimation for Construction of a New Building
|8
|1428
|176

MGMT2102 Project Management - PDF
|18
|3523
|34