Communication Plan: Archives Australia Information System Project
VerifiedAdded on  2023/06/12
|22
|2950
|133
Report
AI Summary
This document presents a comprehensive communication plan for a project focused on developing an information system and upgrading the website for the National Archives of Australia. It outlines key communication objectives, including effective information transfer, ensuring the information system meets client requirements, and addressing project challenges. The plan identifies various stakeholder groups, such as project governance, project management, and project operations, detailing their communication needs and preferred methods. It also includes a communication matrix, outlining the purpose and target audiences for different communication themes, as well as procedures for managing communication, including KPI measurements and corrective actions. The document further describes the project information system, including steps for development, approval, and maintenance, and provides sample WIP reports and project issue logs. The key stakeholders and their roles are identified, emphasizing the importance of their engagement for successful project completion. Desklib offers additional resources like this to aid students in their studies.

PART 1
Communication Plan
ATM ID: NAA RFT 2017/1058
Agency: National Archives of Australia
Category: 81110000
Computer services
Template with guidelines
Prepared by: <name of the student>
Position: Project Manager
Date: 24/05/18
Version No: 4.0
Communication Plan
ATM ID: NAA RFT 2017/1058
Agency: National Archives of Australia
Category: 81110000
Computer services
Template with guidelines
Prepared by: <name of the student>
Position: Project Manager
Date: 24/05/18
Version No: 4.0
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Document Change Control
The following is the document control for the revisions of this document:
Version Number Date of Issue Author(s) Brief Description of Change
1.0 15/03/18
Progress Updated, Existing resource utilization, Change in communication plan,
effective utilization of communication medium
2.0 4/04/18
Progress Updated, Existing resource utilization, Change in communication plan,
effective utilization of communication medium
3.0 7/05/18
Progress Updated, Existing resource utilization, Change in communication plan,
effective utilization of communication medium
The following is the document control for the revisions of this document:
Version Number Date of Issue Author(s) Brief Description of Change
1.0 15/03/18
Progress Updated, Existing resource utilization, Change in communication plan,
effective utilization of communication medium
2.0 4/04/18
Progress Updated, Existing resource utilization, Change in communication plan,
effective utilization of communication medium
3.0 7/05/18
Progress Updated, Existing resource utilization, Change in communication plan,
effective utilization of communication medium

Definition
The following are definitions of terms, abbreviations and acronyms used in this document.
Term Definition
Key Performance
Indicator (KPI)
These are the factors that can provide the success for the deployment of the information system development for
Archives
Work In Progress (WIP) Work In progress is term referred to the aspect of showing the project progress and the alignment of the improved
operation development
Validation The validation is the process of forming the confirmation of the output by checking the system for any downfall or pit
OOB Action The actions that would not be considered as a part for the project activities and OOB stands for out of bounds
Administrative Sign Off Administrative officials would review and sign off the documents for approving the project communication plan
Agile / Scrum Methodology for developing the complete project plan and it is iterative in nature
The following are definitions of terms, abbreviations and acronyms used in this document.
Term Definition
Key Performance
Indicator (KPI)
These are the factors that can provide the success for the deployment of the information system development for
Archives
Work In Progress (WIP) Work In progress is term referred to the aspect of showing the project progress and the alignment of the improved
operation development
Validation The validation is the process of forming the confirmation of the output by checking the system for any downfall or pit
OOB Action The actions that would not be considered as a part for the project activities and OOB stands for out of bounds
Administrative Sign Off Administrative officials would review and sign off the documents for approving the project communication plan
Agile / Scrum Methodology for developing the complete project plan and it is iterative in nature
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Table of Contents
1. Introduction 3
2. Communication objectives 4
3. Communication Purpose and Target Audiences 5
4. Communication Message and Delivery 5
5. Communication Message Contents 5
1. Introduction 3
2. Communication objectives 4
3. Communication Purpose and Target Audiences 5
4. Communication Message and Delivery 5
5. Communication Message Contents 5
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1. Introduction
Project Communication plan holds an integral role for the installation of the information system update for the
upgrade of the website for Archives Australia. The communication plan would allow the ease of information
transfer and it would provide opportunity for improving the activities of the project. The communication
requirements for the project would be analysed for developing effective updates of the website. The
implication of the effective communication process would be helpful for ensuring that implication would be
helpful for achieving the required standards of final project deliverable. The alignment of the improved
activities would allow the utilization of the effective communication medium.
1.1. Project Components / Stakeholder Groups
The project of developing information system and upgrading the website information for Archives Australia
would consider a number of human resources. The stakeholders of the project are classified based on their
role in project. The stakeholder’s group for the project are Project governance, project management, and
project operation. The three levels of project stakeholders have diverse roles and responsibilities. Moreover,
the alignment of the improved communication would help in forming the major transfer of information to the
required stakeholder.
Project Communication plan holds an integral role for the installation of the information system update for the
upgrade of the website for Archives Australia. The communication plan would allow the ease of information
transfer and it would provide opportunity for improving the activities of the project. The communication
requirements for the project would be analysed for developing effective updates of the website. The
implication of the effective communication process would be helpful for ensuring that implication would be
helpful for achieving the required standards of final project deliverable. The alignment of the improved
activities would allow the utilization of the effective communication medium.
1.1. Project Components / Stakeholder Groups
The project of developing information system and upgrading the website information for Archives Australia
would consider a number of human resources. The stakeholders of the project are classified based on their
role in project. The stakeholder’s group for the project are Project governance, project management, and
project operation. The three levels of project stakeholders have diverse roles and responsibilities. Moreover,
the alignment of the improved communication would help in forming the major transfer of information to the
required stakeholder.

2. Communication Objectives
The key communication objectives for the project are:
1
Transfer of information is the primary objective for communication in the project of developing information system and upgrading the website
information for Archives Australia
2
Ensuring that the information system developed meets the client’s requirement checklist by providing the developers with the proper
information
3
Transferring the problems faced while executing the project so that appropriate solutions can be developed for the project
4
Aligning the implication of the successful project execution development for the project for overcoming the probable issues
The key communication objectives for the project are:
1
Transfer of information is the primary objective for communication in the project of developing information system and upgrading the website
information for Archives Australia
2
Ensuring that the information system developed meets the client’s requirement checklist by providing the developers with the proper
information
3
Transferring the problems faced while executing the project so that appropriate solutions can be developed for the project
4
Aligning the implication of the successful project execution development for the project for overcoming the probable issues
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3. Communication Matrix - Purpose and Target Audiences
This section identifies the audiences targeted in this Communication Plan, and the purpose of communicating with each audience.
Stakeholder Group Stakeholder Communication (theme content) Format Frequency
Governance group Client To inform about the progress of the project Report,
Board
Meetings
Monthly
Governance group Investors To inform about the investment usages for the
project
Report,
Board
Meetings
Monthly
Governance group Steering Committee To take the key decisions for the project Report,
Board
Meetings
Monthly
Managerial group Project Manager To manage all activities in the project Reports,
Face to Face
Conversation
Weekly
Managerial group HR Manager To manage human resources for the project Reports,
Face to Face
Conversation
Weekly
Managerial group Contractor To provide external work support to the project Call Weekly
Operation group Supplier To provide required materials for the project Call Once
Operation group End User To provide feedback on the system developed Online
Survey
Once
Operation group Project Team To execute the activities of project Face to Face
Conversation
Daily
Operation group Workers To work the constructional activities of project Face to Face
Conversation
Daily
This section identifies the audiences targeted in this Communication Plan, and the purpose of communicating with each audience.
Stakeholder Group Stakeholder Communication (theme content) Format Frequency
Governance group Client To inform about the progress of the project Report,
Board
Meetings
Monthly
Governance group Investors To inform about the investment usages for the
project
Report,
Board
Meetings
Monthly
Governance group Steering Committee To take the key decisions for the project Report,
Board
Meetings
Monthly
Managerial group Project Manager To manage all activities in the project Reports,
Face to Face
Conversation
Weekly
Managerial group HR Manager To manage human resources for the project Reports,
Face to Face
Conversation
Weekly
Managerial group Contractor To provide external work support to the project Call Weekly
Operation group Supplier To provide required materials for the project Call Once
Operation group End User To provide feedback on the system developed Online
Survey
Once
Operation group Project Team To execute the activities of project Face to Face
Conversation
Daily
Operation group Workers To work the constructional activities of project Face to Face
Conversation
Daily
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4. Communication Management Procedures
The following outlines the Stakeholder Group, KPI measurement, Threshold or limit for regular range of performance, Corrective Action for Out of
Range performance, Work In Progress frequency.
Stakeholder
Group
KPI Threshold Corrective action WIP Frequency
Governance group
Stakeholder
Engagement rates
Unable to reach
benchmark Engagement Survey should be used
Twice in a month
Open rates for
communication
Unawareness of activities
Digital tools for communication
Half yearly
Adoption range Lack of Back tracking
Promoting the communication method
Monthly
Responses and
feedbacks
Requirement for
information pushing 2 way communication should be used
Weekly
The following outlines the Stakeholder Group, KPI measurement, Threshold or limit for regular range of performance, Corrective Action for Out of
Range performance, Work In Progress frequency.
Stakeholder
Group
KPI Threshold Corrective action WIP Frequency
Governance group
Stakeholder
Engagement rates
Unable to reach
benchmark Engagement Survey should be used
Twice in a month
Open rates for
communication
Unawareness of activities
Digital tools for communication
Half yearly
Adoption range Lack of Back tracking
Promoting the communication method
Monthly
Responses and
feedbacks
Requirement for
information pushing 2 way communication should be used
Weekly

Contribution to
organization goal
Limited to internal
communication Keeping an eye on the project target
Once
organization goal
Limited to internal
communication Keeping an eye on the project target
Once
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

5. Stakeholder Communication (Network links)
This section outlines the links in the project for the key information and communications channels.
To inform about the progress of the project
To inform about the investment usages for the
project
To take the key decisions for the project
To manage all activities in the project
To manage human resources for the project
To provide external work support to the project
To provide required materials for the project
To provide feedback on the system developed
To execute the activities of project
To work the constructional activities of project
Client
Report
Board Meetings
Face to Face Conversation
Call
Online Survey
Project Team
This section outlines the links in the project for the key information and communications channels.
To inform about the progress of the project
To inform about the investment usages for the
project
To take the key decisions for the project
To manage all activities in the project
To manage human resources for the project
To provide external work support to the project
To provide required materials for the project
To provide feedback on the system developed
To execute the activities of project
To work the constructional activities of project
Client
Report
Board Meetings
Face to Face Conversation
Call
Online Survey
Project Team
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

6. Project Information System
This section explains the way that information is documented, accessed, recorded and archived for the project.
Include (WIP Final, Admin Sign Off, Lessons Learned/Archiving/KMS)
The project of developing information system and upgrading the website information for Archives Australia is developed for listing the effective
communication network and it would allow the utilization of the effective development model. The process of information system includes,
Step 1: Development of effective plan
Step 2: Designing the information system
Step 3: Developing integrated database and migrating all information in the database
Step 4: Implication of authorization for access
Step 5: Completion of System Development (User interface for access, modify, login, and record data)
Step 6: Approval of the system (WIP final, Admin Sign off)
Step 7: Maintenance and Monitoring (Incorporating lesson learnt)
This section explains the way that information is documented, accessed, recorded and archived for the project.
Include (WIP Final, Admin Sign Off, Lessons Learned/Archiving/KMS)
The project of developing information system and upgrading the website information for Archives Australia is developed for listing the effective
communication network and it would allow the utilization of the effective development model. The process of information system includes,
Step 1: Development of effective plan
Step 2: Designing the information system
Step 3: Developing integrated database and migrating all information in the database
Step 4: Implication of authorization for access
Step 5: Completion of System Development (User interface for access, modify, login, and record data)
Step 6: Approval of the system (WIP final, Admin Sign off)
Step 7: Maintenance and Monitoring (Incorporating lesson learnt)

6. Project Information System
This section explains the way that information is documented, accessed, recorded and archived for the project.
Include (WIP Final, Admin Sign Off, Lessons Learned/Archiving/KMS)
The project of developing information system and upgrading the website information for Archives Australia is developed for listing the effective
communication network and it would allow the utilization of the effective development model. The process of information system includes,
Step 1: Development of effective plan
Step 2: Designing the information system
Step 3: Developing integrated database and migrating all information in the database
Step 4: Implication of authorization for access
Step 5: Completion of System Development (User interface for access, modify, login, and record data)
Step 6: Approval of the system (WIP final, Admin Sign off)
Step 7: Maintenance and Monitoring (Incorporating lesson learnt)
This section explains the way that information is documented, accessed, recorded and archived for the project.
Include (WIP Final, Admin Sign Off, Lessons Learned/Archiving/KMS)
The project of developing information system and upgrading the website information for Archives Australia is developed for listing the effective
communication network and it would allow the utilization of the effective development model. The process of information system includes,
Step 1: Development of effective plan
Step 2: Designing the information system
Step 3: Developing integrated database and migrating all information in the database
Step 4: Implication of authorization for access
Step 5: Completion of System Development (User interface for access, modify, login, and record data)
Step 6: Approval of the system (WIP final, Admin Sign off)
Step 7: Maintenance and Monitoring (Incorporating lesson learnt)
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 22
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.