Running head: PROJECT MANAGEMENT
Project management
Name of the Student
Name of the University
Author’s Note

PROJECT MANAGEMENT
1
Table of Contents
Answer to question number 1..........................................................................................................2
a) Identification of the critical path.............................................................................................2
b) Listing the total and free float for each activity......................................................................3
Answer to question number 2.........................................................................................................4
Answer to question number 3..........................................................................................................5
Answer to question number 4..........................................................................................................6
Answer to question number 5a........................................................................................................8
Answer to question number 5b........................................................................................................9
Answer to question number 6a......................................................................................................10
Answer to question number 6b......................................................................................................11
Answer to question number 7........................................................................................................11
Bibliography..................................................................................................................................14

PROJECT MANAGEMENT
2
Answer to question number 1
a) Identification of the critical path
The above activities can be showcased in the form of diagram that is provided below:
Figure 1: Activities reflecting dependencies
(Source: Created by Author)
For calculating the critical path, the different paths are
1st path- A>B>C>D>I -28 days

PROJECT MANAGEMENT
3
2nd path- A>E>F>H>I- (5+3+8+6+8)- 30 days
3rd path- A>G>H>I (5+6+6+8)-25 days
4th path- A>E>F>D>I (5+3+8+5+8) -29 days
As, the minimum time that is needed for the project is 30 days and therefore the critical path of
the project is A>E>F>H>I
b) Listing the total and free float for each activity
The figure that is provided below showcase the float for each of the activity.
Figure 2: Diagram reflecting float for each activity
(Source: Created by Author)
Total float- LF- EF (Late finish- Early finish)
Free float- ES of next activity- EF
The calculation for total float and free float is done in the below table
Activity Total float (LF- EF) Free float

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
PRMG-010 Project Planning and Control Teqniques
|14
|1545
|76

assessment
|3
|293
|76

Principles of Project Management
|11
|1185
|433

Research on Industrial Engineering
|10
|823
|16

Project Management
|8
|928
|284

Project Management: Prepare Network Diagram, Evaluate Options to Meet Deadline
|10
|1301
|268