Fuel Oil Tank Storage and Handling

   

Added on  2019-10-31

14 Pages3145 Words32 ViewsType: 32
Business Development
 | 
 | 
 | 
2017Assignment on
Project management
Assignment on
Project management
Fuel Oil Tank Storage and Handling_1

Contents
Introduction:.............................................................................................................. 2
Project objectives:....................................................................................................... 2
Implementation phase:.................................................................................................. 2
Inspection of the tanks:.............................................................................................. 2
Requirement:.......................................................................................................... 3
Roles and responsibilities:.......................................................................................... 3
Implementation plan:................................................................................................ 4
Organization chart:................................................................................................... 5
Portfolio management for the activities:............................................................................ 6
Work Breakdown structure:........................................................................................... 6
Cost management Plan................................................................................................. 7
Time management plan:................................................................................................ 7
Quality management plan:............................................................................................. 9
Methodologies used for project evaluation:......................................................................10
Gantt chart:............................................................................................................. 12
Project closure:......................................................................................................... 12
References.............................................................................................................. 13
1
Fuel Oil Tank Storage and Handling_2

Introduction:
The organization wants to develop a project plan for management of multi-storage tank
facilities for petroleum. The renewable schemes are needed to restrict the wastage of petrol.
The renovation is required in the infrastructure of the tank to handle storage. The purpose of
this project is to design an implementation plan which identifies the successful
implementation of the project requirement (Kvimis, 2016). The project also focuses on the
development of the management plan to make a study on the four major areas of the proposed
project which are classified as time, resources, cost, and quality (Hussain, 2013). The
evaluation of the tools and methods used helps in determining the performance of the project.
Project objectives:
The objectives of this project are to focus on the following:
Scheduling of activities to make a balance of storage
Identifying and developing mitigation plan for Environmental risks
Renovation of the tank 1, tank 2, and tank 3.
Automation in the required activities
Reducing the risks associated with the environment.
Minimize the efforts of labour and technical staff
Implementation phase:
From the research case study, we analysed there are three tanks of different storage capacity.
The tank 1 has the storage capacity of unleaded petrol of 1 million litres. The tank 2 has the
storage capacity of unleaded petrol of 3 million litres. The tank 3 has the storage capacity of
unleaded petrol of 7 million litres. The renovation of the tanks is required for leveraging the
supply valve which can handle inflammable fumes. The changes are required in the current
infrastructure of the tank scenario to resolves the issues related with environment and the
storage of the fuel oil.
Inspection of the tanks:
The inspection of the tanks gathers the following information related to the tanks:
Tank 1 Tank 2 Tank 3
The tank 1 has the storage The tank 2 has the storage The tank 3 has the storage
2
Fuel Oil Tank Storage and Handling_3

capacity of unleaded petrol
of 1 million litres.
capacity of unleaded petrol
of 3 million litres.
capacity of unleaded petrol
of 7 million litres.
There are four steel patches
of size 2 m.Sq.
There are 7 steel patches of
size 3 m.Sq.
There are Six steel patches of
size 1.5 m.Sq.
There are 4 steel anchors on
the roof of the tank
There are 4 steel anchors on
the roof of the tank
There are 4 steel anchors on
the roof of the tank
Painting and cleaning from
outside
Painting and cleaning from
outside
Painting and cleaning from
outside
Main supply valve of the
tank should be replaced
Requirement:
Painting and cleaning from outside
Main supply valve of the tank should be replaced
Testing of the leakages Strategically maintained the spill kits for the tank
Upgrading of the three tanks
Managing integration between the three tanks.
Closing of the bypass valves
Management of the environmental risks to reduce the extra expenditure.
Coordination between vendors and supplier
Roles and responsibilities:
The subcontractor department is responsible for identifying the ratio between demand and
supply of the material (Passenheim, 2011). The master agreement should be prepared for
facilitating the purchase on demand. The equipment and materials are associated with the
expedite delivery process. The face to face meetings should be organized between the
contractors and sub-contractors. The statement of work should be discussed between the
participating units. The quality of the past storage capacity should be analysed and reviewed
(Project service centre, 2015). The financial resources should be estimated and analysed to
associated the cost with every activity. The on-time delivery of the raw material helps in the
successful completion of handling fuel oil in the three tanks.
The responsibility of the quality control department is to deploy a quality control program for
analysing the project activities. The testing should be performed to check the quality of the
3
Fuel Oil Tank Storage and Handling_4

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Project Management Assignment Sample (Docs)
|10
|1729
|177

Project Management Report for Tank Farm
|14
|2688
|9

Project Management for Oil Tank Renovation in Australia
|13
|1884
|458

[PDF] Construction Project Management
|10
|1987
|114

Assignment on Project Management (pdf)
|15
|2685
|57

Project Management Project Management Project Management Name of the University Author
|8
|1734
|427