This article is a case study on AT&T Project and focuses on project management methodologies, budget estimates, project deliverables, project scope, and organizational chart. The article also provides insights on roles and responsibilities of different stakeholders involved in the project.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head: PROJECT MANAGEMENT Case Study: AT&T Project Name of the Student Name of the University Author’s Note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
2 PROJECT MANAGEMENT 1. Project Overview 1.1 Project charter 1.1.1 Purpose The project mainly focusses on the organization AT& T that mainly establishes project management centre of Excellence for fostering project management culture as well as for improving organizational competencies. However, during the establishment of PMCOE, the organization faces a number of challenges. In order to combat those challenges, PMCOE applied various methodologies of project management during the development of the center. The priority from PMCOE was to ensure that merging of project management practices between different legacies companies so that it can run smoothly. PMCOE utilizes five-step procedures that are established by PMI for achieving success within the project. 1.1.2 Duration It is identified that around 110 days are required for completing AT&T project. The time that is needed for executing each of the project activities are listed in the table below: Task NameDurationStartFinish AT&T Project110 daysMon 16-04-18Fri 14-09-18 Initiation phase13 daysMon 16-04-18Wed 02-05-18 Analyzing challenges1 dayMon 16-04-18Mon 16-04-18 Identification of solutions1 dayTue 17-04-18Tue 17-04-18 Getting approval from senior management1 dayWed 18-04-18Wed 18-04-18 Development of proposal2 daysThu 19-04-18Fri 20-04-18 Identifying needs of the project2 daysMon 23-04-18Tue 24-04-18 Forecasting resources2 daysWed 25-04-18Thu 26-04-18
3 PROJECT MANAGEMENT Identifying financial benefits1 dayFri 27-04-18Fri 27-04-18 Re-evaluation of plan3 daysMon 30-04-18Wed 02-05-18 Milestone 1:Completion of initiation phase0 daysWed 02-05-18Wed 02-05-18 Planning phase9 daysThu 03-05-18Tue 15-05-18 Determination of products and services that will be added within the project management community 3 daysThu 03-05-18Mon 07-05-18 Completion of need assessment2 daysTue 08-05-18Wed 09-05-18 Identification of critical project management products and services identified 4 daysThu 10-05-18Tue 15-05-18 Milestone 2:Completion of planning phase0 daysTue 15-05-18Tue 15-05-18 Execution phase88 daysWed 16-05-18Fri 14-09-18 Execution of the outlined plan10 daysWed 16-05-18Tue 29-05-18 Delivery of project on time and budget10 daysWed 30-05-18Tue 12-06-18 Maintaining project quality10 daysWed 13-06-18Tue 26-06-18 Integration of two legacy teams10 daysWed 27-06-18Tue 10-07-18 Gaining traction with the merged PM community 10 daysWed 11-07-18Tue 24-07-18 Milestone 3:Completion of execution phase 0 daysTue 24-07-18Tue 24-07-18 Monitoring and Controlling process31 daysWed 25-07-18Wed 05-09-18 Reporting business plan to senior management 5 daysWed 25-07-18Tue 31-07-18 An annual client satisfaction Survey was5 daysWed 01-08-18Tue 07-08-18
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4 PROJECT MANAGEMENT distributed Additional surveys was distributed to the participants 5 daysWed 08-08-18Tue 14-08-18 Analysis of feedback10 daysWed 15-08-18Tue 28-08-18 Key findings that was incorporated for improving the PMCOE 6 daysWed 29-08-18Wed 05-09-18 Milestone 4:Completuion of controlling and monitoring phase 0 daysWed 05-09-18Wed 05-09-18 Closure phase of the project7 daysThu 06-09-18Fri 14-09-18 Integration of legacy completion2 daysThu 06-09-18Fri 07-09-18 Repetition of planning, executing and controlling 3 daysMon 10-09-18Wed 12-09-18 Identification of lessons learnt2 daysThu 13-09-18Fri 14-09-18 Milestone 5:Completion of closure phase0 daysFri 14-09-18Fri 14-09-18 1.1.3Budget estimate The entire project will be completed with the budget $2,100,000. It is identified that the budget that is needed for completing each of the project activities are reflected in the table below: Task NameDurationResource NamesCost AT&T Project110 days$2,100,000.00 Initiation phase13 days$130,000.00 Analyzing challenges1 dayPMP-K$10,000.00 Identification of solutions1 dayPMP-K$10,000.00
5 PROJECT MANAGEMENT Getting approval from senior management 1 dayPMP-I$10,000.00 Development of proposal2 daysPMP-B$20,000.00 Identifying needs of the project2 daysPMP-H$20,000.00 Forecasting resources2 daysPMP-A$20,000.00 Identifying financial benefits1 dayPMP-K$10,000.00 Re-evaluation of plan3 daysPMP-B$30,000.00 Planning phase9 days$90,000.00 Determination of products and services that will be added within the project management community 3 daysPMP-I$30,000.00 Completion of need assessment2 daysPMP-K$20,000.00 Identification of critical project management products and services identified 4 daysPMP-A$40,000.00 Execution phase88 days$1,880,000.00 Execution of the outlined plan10 daysPMP-C$100,000.00 Delivery of project on time and budget 10 daysPMP-D$100,000.00 Maintaining project quality10 daysPMP-E$100,000.00 Integration of two legacy teams10 days PMP-F, Cost of equipment (Hardware/Software)[1] $600,000.00 Gaining traction with the10 daysPMP-G, Cost of$600,000.00
6 PROJECT MANAGEMENT merged PM community equipment (Hardware/Software)[1] Monitoring and Controlling process 31 days$310,000.00 Reporting business plan to senior management 5 daysPMP-K$50,000.00 An annual client satisfaction Survey was distributed 5 daysPMP-B$50,000.00 Additional surveys was distributed to the participants 5 daysPMP-H$50,000.00 Analysis of feedback10 daysPMP-J$100,000.00 Key findings that was incorporated for improving the PMCOE 6 daysPMP-I$60,000.00 Closure phase of the project7 days$70,000.00 Integration of legacy completion 2 daysPMP-A$20,000.00 Repetition of planning, executing and controlling 3 daysPMP-H$30,000.00 Identification of lessons learnt2 daysPMP-A$20,000.00
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7 PROJECT MANAGEMENT 1.1.4 Assumptions and Constraints Assumptions:The assumptions that are made within the project are as follows: The project will be completed by utilizing budget of around $2,100,000.00 It is assumed that the project will take 110 days to complete The project will follow the scope properly for making the project successful. Constraints:Project constraints are elaborated below: Budget:The AT & T should be completed within the budget $2,100,000.00. If the project is not executed within the assumed budget, then the organization will face financial challenges. Scope:The scope of the project should be followed while progressing with the project. If the scope of the project is not met, then it will be quite difficult to execute the project successfully within the assumed time and budget. Time:The entire project must be completed within 110 days. If the entire project is not completed within 10 days, then the budget of the project will also increase which generally can create financial pressure on the organization. 1.1.5 Project Deliverable The deliverables of the project include: legacy teams integration Gaining traction with the merged PM community Reporting business plan to the senior management of the organization Survey related to an annual client satisfaction was distributed Additional surveys were distributed to the participants Analysis of feedback
8 PROJECT MANAGEMENT Key findings that was incorporated for improving the PMCOE 1.2 Scope management plan 1.2.1 Project scope The project scope is provided below: Combating and avoiding challenges that occur during the development of the centre with the application of project management methodology To make sure that the merging of variousPM practices between various legacy organizations can run smoothly Establishment of consultants for supporting different business units To understand which services are important for AT&T community 1.2.2 WBS AT&T Project Initiation phase Analyzing challenges Identification of solutions Getting approval from senior management Development of proposal Identifying needs of the project Forecasting resources Identyfying finanacial benefits Re-evaluation of plan Milestone 1:Completion of initiation phase Planning phase Determination of products and services that will be added within the project management community Completion of need assesment Identification of critical project management productsa nd services identified Milestone 2:Completion of planning phase Execution phase Execution of the outlined plan Delivery of project on time and budget Maintaining project quality Integration of two legacy teams Gaining traction with the merged PM community Milestone 3:Completion of execution phase Monitoring and Controlling process Reporting business plan to senior amnagement An annual client satisfaction Survey was distributed Additional surveys was distributed to the participants Analysis of feedback Key findings that was incorported for improving the PMCOE Milestone 4:Completuion of controlling and monitoring phase Closure phase of the project Integration of legacy completion Repeatation of planning, executing and controlling Identification of lessons learnt Milestone 5:Completion of closure phase Figure 1: Work Breakdown Structure (Source: Created by Author)
VP (Sponsor) Project managers Program managersSupervisorsPMPS Chief executive officer 9 PROJECT MANAGEMENT 2. Project organization 2.1Organizational chart Figure 2: Project organizational chart (Source: Created by Author) 2.2Roles and responsibilities RolesResponsibilities SponsorThe sponsor is an individual who takes the entireprojectaccountability.Theyare generally concerned with ensuring that the entire project will be able to deliver proper benefits as per the organizational goals and objectives. They also act as an arbitrator for making proper decisions that are beyond the
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10 PROJECT MANAGEMENT project manager authority. Project managerThe project managers involve in the project ofAT&Tforrecognizingthemission internally in context to project management mentoring, consulting, processes, training as well as tools and techniques. Program managerThePMCOEtargetedtheprogram managers of different projects so that they canbeabletodriveAT&Tculturefor supportingaswellassustainingthe professional project. SupervisorPMCOE targeted the supervisors of the organizationforassessingaswellas improvingAT&Tprofessionalproject management competency at different levels includingindividual,teamaswellas organizational. Project management professionalThe project management professional is the individualswhoareresponsiblefor planning, executing, initiating,monitoring aswellasclosingtheentireproject successfully within the estimated time and budgetsothatthechallengesthat organizationAT&Tarefacingcanbe resolved quite easily.
12 PROJECT MANAGEMENT (Source: Created by Author) 3.2 Cost management plan It is identified that bottom-up approach is utilized for estimating the budget of the project. It is identified that with the help of bottom-up approach, the entire project of AT&T will be completed within the budget of around $2,100,000.00. The cost that is required for finishing each of the activities of the project is provided in the table below: Task NameDurationStartFinishPredecessorsResource NamesCost AT&T Project110 days Mon 16- 04- 18 Fri 14-09- 18 $2,100,000.00 Initiation phase 13 days Mon 16- 04- 18 Wed 02-05- 18 $130,000.00 Analyzing challenges 1 day Mon 16- 04- 18 Mon 16-04- 18 PMP-K$10,000.00 Identification of solutions 1 day Tue 17- 04- 18 Tue 17-04- 18 3PMP-K$10,000.00 Getting1 dayWedWed4PMP-I$10,000.00
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
13 PROJECT MANAGEMENT approval from senior management 18- 04- 18 18-04- 18 Development of proposal 2 days Thu 19- 04- 18 Fri 20- 04-18 5PMP-B$20,000.00 Identifying needs of the project 2 days Mon 23- 04- 18 Tue 24-04- 18 6PMP-H$20,000.00 Forecasting resources 2 days Wed 25- 04- 18 Thu 26-04- 18 7PMP-A$20,000.00 Identifying financial benefits 1 day Fri 27- 04- 18 Fri 27- 04-18 8PMP-K$10,000.00 Re- evaluation of plan 3 days Mon 30- 04- 18 Wed 02-05- 18 9PMP-B$30,000.00 Milestone 1:Completion 0 daysWed 02- Wed 02-05- 10$0.00
14 PROJECT MANAGEMENT of initiation phase 05- 18 18 Planning phase 9 days Thu 03- 05- 18 Tue 15-05- 18 $90,000.00 Determination of products and services that will be added within the project management community 3 days Thu 03- 05- 18 Mon 07-05- 18 10PMP-I$30,000.00 Completion of need assessment 2 days Tue 08- 05- 18 Wed 09-05- 18 13PMP-K$20,000.00 Identification of critical project management products and services 4 daysThu 10- 05- 18 Tue 15-05- 18 14PMP-A$40,000.00
15 PROJECT MANAGEMENT identified Milestone 2:Completion of planning phase 0 days Tue 15- 05- 18 Tue 15-05- 18 15$0.00 Execution phase 88 days Wed 16- 05- 18 Fri 14-09- 18 $1,880,000.00 Execution of the outlined plan 10 days Wed 16- 05- 18 Tue 29-05- 18 16PMP-C$100,000.00 Delivery of project on time and budget 10 days Wed 30- 05- 18 Tue 12-06- 18 18PMP-D$100,000.00 Maintaining project quality 10 days Wed 13- 06- 18 Tue 26-06- 18 19PMP-E$100,000.00 Integration of two legacy teams 10 daysWed 27- 06- Tue 10-07- 18 20PMP-F, Cost of equipment (Hardware/Software) $600,000.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
16 PROJECT MANAGEMENT 18[1] Gaining traction with the merged PM community 10 days Wed 11- 07- 18 Tue 24-07- 18 21 PMP-G, Cost of equipment (Hardware/Software) [1] $600,000.00 Milestone 3:Completion of execution phase 0 days Tue 24- 07- 18 Tue 24-07- 18 22$0.00 Monitoring and Controlling process 31 days Wed 25- 07- 18 Wed 05-09- 18 $310,000.00 Reporting business plan to senior management 5 days Wed 25- 07- 18 Tue 31-07- 18 22PMP-K$50,000.00 An annual client satisfaction Survey was distributed 5 days Wed 01- 08- 18 Tue 07-08- 18 25PMP-B$50,000.00 Additional surveys was distributed to 5 daysWed 08- 08- Tue 14-08- 26PMP-H$50,000.00
17 PROJECT MANAGEMENT the participants1818 Analysis of feedback 10 days Wed 15- 08- 18 Tue 28-08- 18 27PMP-J$100,000.00 Key findings that was incorporated for improving the PMCOE 6 days Wed 29- 08- 18 Wed 05-09- 18 28PMP-I$60,000.00 Milestone 4:Completuion of controlling and monitoring phase 0 days Wed 05- 09- 18 Wed 05-09- 18 29$0.00 Closure phase of the project 7 days Thu 06- 09- 18 Fri 14-09- 18 $70,000.00 Integration of legacy completion 2 days Thu 06- 09- 18 Fri 07- 09-18 29PMP-A$20,000.00 3 daysMonWed32PMP-H$30,000.00
18 PROJECT MANAGEMENT Repetition of planning, executing and controlling 10- 09- 18 12-09- 18 Identification of lessons learnt 2 days Thu 13- 09- 18 Fri 14- 09-18 33PMP-A$20,000.00 Milestone 5:Completion of closure phase 0 days Fri 14- 09- 18 Fri 14- 09-18 34$0.00 Resource NameType Materi al Label Initia ls Grou p Max . Unit s Std. RateOvt. Rate Cost/ Use Accru e At Base Calend ar PMP-AWork100 % $10,000.00/ day $0.00/ hr.$0.00Prorat ed Standa rd PMP-BWorkP100 % $10,000.00/ day $0.00/ hr.$0.00Prorat ed Standa rd PMP-CWorkP100 % $10,000.00/ day $0.00/ hr.$0.00Prorat ed Standa rd PMP-DWorkP100 % $10,000.00/ day $0.00/ hr.$0.00Prorat ed Standa rd PMP-EWorkP100 % $10,000.00/ day $0.00/ hr.$0.00Prorat ed Standa rd PMP-FWorkP100 % $10,000.00/ day $0.00/ hr.$0.00Prorat ed Standa rd PMP-GWorkP100 % $10,000.00/ day $0.00/ hr.$0.00Prorat ed Standa rd PMP-HWorkP100 % $10,000.00/ day $0.00/ hr.$0.00Prorat ed Standa rd PMP-IWorkP100 % $10,000.00/ day $0.00/ hr.$0.00Prorat ed Standa rd
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
19 PROJECT MANAGEMENT PMP-JWorkP100 % $10,000.00/ day $0.00/ hr.$0.00Prorat ed Standa rd PMP-KWorkP100 % $10,000.00/ day $0.00/ hr.$0.00Prorat ed Standa rd Cost of equipment (Hardware/Softw are) Materi al$500,000.00$0.00Prorat ed Cost of materialMateri alC$419,000.00$0.00Prorat ed 3.3 Risk management plan RiskDescriptionImpactConsequencesRisk mitigation Improper budget estimation Ifthebudget for the project is notestimated properly,then theproject manager faces a lot of difficulty incompleting the project. HighHighProperearned valueanalysis mustbe undertakenin ordertomake sure that proper theentire projectwillbe accomplished withinthe estimated budget. Schedule slippage Iftheproject management professionalis not able to track HighHighIt is very much essentialto trackthe schedule of the
20 PROJECT MANAGEMENT the schedule of theproject properly,then thechancesof schedule slippageare high, and due to slippageof schedule,itis quite challengingto completethe projectwithin theexpected budgetand time. project properly onaweekly basis so that the wholeproject will be finished withinthe predictable budgetand time. Improper management Ifproject management professionalis notableto managethe project successfullyon time, then it is quite MediumMediumItisquite necessaryto utilizeproject management strategies within theprojectso thattheentire project must be successfully
21 PROJECT MANAGEMENT challengingto finish the entire project effectively withinthe probable budget and time. managed by the project management professionalso thattheentire project must be completed successfully withinthe estimatedtime and budget. Inexperienced project management professional Iftheproject management professionalis not experienced, thentheycan facedifficulty in executing the project successfully withinthe estimated budgetand time. HighMediumIt is very much necessaryto hire experienced project management professionals withinthe projectsothat they are capable of finishing the projectwithin theexpected deadline.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
22 PROJECT MANAGEMENT 3.4 Communication management plan Deliverable info DescriptionRecipientDelivery Method ScheduleWhois responsible Project information Information aboutthe projectis requiredto bedelivered totheteam membersso that they can bework properlyfor achieving the objectives as well as goals ofthe project. Project team SharePoint Team meetings Conference calls As required Project management professional
23 PROJECT MANAGEMENT Project StatusPMP-B must provide aproper update about the status of the project to theproject sotheycan makesure thatthe entire project befinished withinthe probable budgetand time PMP- BEmailBy1pm on Monday Project management professional Agenda/minute s Monthly basis meetings are arrangedin orderto discuss aboutthe progressof the project. Project team MeetingsMonthlyProject management professional
24 PROJECT MANAGEMENT Project updateThe update aboutthe projectis providedto thesteering committee so thatthey canmake sure that the entire project ofAT$Tis on track. Steering committee Email Team meetings As required Project management professional Project risksTherisks thatare associated withthe projectare illustrated by PMP-Ato theother project management professional sothatthe risks, as well PMP-AEmail Conference calls As required Project management professional
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
25 PROJECT MANAGEMENT as challenges, can be easily resolved. Timeline update The update aboutthe project timelineis providedto theproject management professional sothatthe projectgets executed withinthe expected deadline Project team Risk document Meeting minutes As required Project management professional 3.5 Resource Histograms Theresourcehistogramthatisprovidedbelowreflectsthattheentireproject management professional works for 80 hrs within the project in order to finish the project within the expected time and budget.
26 PROJECT MANAGEMENT PMP-APMP-BPMP-CPMP-DPMP-EPMP-FPMP-GPMP-HPMP-IPMP-JPMP-K 0 hrs 10 hrs 20 hrs 30 hrs 40 hrs 50 hrs 60 hrs 70 hrs 80 hrs 90 hrs Actual WorkRemaining WorkBaseline Work Figure 4: Resource Histogram (Source: Created by Author) 4. Technical process plans 4.1Method of training The method of training that is used by the organization AT&T within the organization are elaborated below: Online training classes:The organization AT&T provides online training facility to the project management professionals so that they can be able to utilize the online classes in order to update their knowledge on the project so that they can be able to work properly within the project. It is identified that online classes are mainly arranged for the project management professionals who have problems in attending classroom training. The team members for keeping themselves update as well as skilled so that they can be able to execute the project within expected budget and time can utilize online training. Classroom training:Classroom training is provided to the project management professionals in order to enhance their skill as well as knowledge in the project so that they can work properly within the project for finishing the project activities within the estimated budget and time. Supporting the team with proper training facility is like leading the project
27 PROJECT MANAGEMENT towards success. The training will help the team members to manage the project work effectively by completing the tasks that are assigned to them within the due date. Symposium:The leaders of the project arrange meetings on a weekly basis so that the team members of the project can discuss about the project properly. The team members can discuss about the project related risks as well as challenges that they are facing during the progress of the project so that the leaders can discuss properly and provide a proper solution totheteammembersforresolvingtheissuesaswellaschallengesoftheproject appropriately. 4.2Process improvement plan The process improvement plans that are utilized in the project are as follows: Estimating budget properly:The budget of the project must be estimated by engaging in market analysis in order to know about the costs of materials as well as resources that are required for completing the project successfully. After getting proper information, the budget of the project can be estimated properly so that the entire project can be successfully finished within the assumed budget. In order to minimize the issues of the budget shortfall, it also necessary for the project management professionals to engage in earned value analysis in order to make sure that the entire project gets completed within the assumed budget. Proper schedule tracking:As the problem of schedule slippage occurs, it is very much necessary for the project management professionals to manage the schedule of the project so that the chances of schedule slippage can be avoided. For mitigating the problem of schedule slippage, it is necessary to utilize weekly basis tracking for ensuring that the entire project is on track and it will be successful gets completed within the time that is assumed during the initiation phase of the project
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
28 PROJECT MANAGEMENT Improving quality:It is identified that improper quality of the project can create number of quality issues and therefore proper steps must be utilized for finishing the project so that the project can be executed successfully within the expected time budget without compromising the quality of the project. Proper quality-based outcome not only helps in resolving quality related issues but also helps in developing the center effectively in the absence of any problem. Reducing lead time:The project lead time must be reduced for improving the project performance so that theentire project can be easily get finished within the expected budget as well as time.
29 PROJECT MANAGEMENT Bibliography Badewi, A. (2016). The impact of project management (PM) and benefits management (BM) practices on project success: Towards developing a project benefits governance framework.International Journal of Project Management,34(4), 761-778. Bentahar, O., & Cameron, R. (2015). Design and Implementation of a Mixed Method Research Study in Project Management.Electronic Journal of Business Research Methods,13(1). Cagliano, A. C., Grimaldi, S., & Rafele, C. (2015). Choosing project risk management techniques. A theoretical framework.Journal of Risk Research,18(2), 232-248. Correa, A. (2016).Project management in architectural practices: project success factors in building design processes(Doctoral dissertation, Dublin Business School). Costantino, F., Di Gravio, G., & Nonino, F. (2015). Project selection in project portfolio management:Anartificialneuralnetworkmodelbasedoncriticalsuccess factors.International Journal of Project Management,33(8), 1744-1754. Fernandes,G.,Ward,S.,&Araújo,M.(2015).Improvingandembeddingproject management practice in organisations—A qualitative study.International Journal of Project Management,33(5), 1052-1067. Heldman, K. (2018).PMP: a project management professional exam study guide. John Wiley & Sons. Hornstein, H. A. (2015). The integration of project management and organizational change management is now a necessity.International Journal of Project Management,33(2), 291-298.
30 PROJECT MANAGEMENT Joslin, R., & Müller, R. (2015). Relationships between a project management methodology and project success in different project governance contexts.International Journal of Project Management,33(6), 1377-1392. Kerzner,H.(2017).Projectmanagementmetrics,KPIs,anddashboards:aguideto measuring and monitoring project performance. John Wiley & Sons. Lock, D. (2017).The essentials of project management. Routledge. Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A. M. E., & Villanueva, P. (2014). Projectriskmanagementmethodologyfor smallfirms.Internationaljournal of project management,32(2), 327-340. Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success.International journal of project management,32(2), 202-217. Papke-Shields, K. E., & Boyer-Wright, K. M. (2017). Strategic planning characteristics applied to project management.International Journal of Project Management,35(2), 169-179. Sánchez, M. A. (2015). Integrating sustainability issues into project management.Journal of Cleaner Production,96, 319-330. Špundak, M. (2014). Mixed agile/traditional project management methodology–reality or illusion?.Procedia-Social and Behavioral Sciences,119, 939-948. Svejvig, P., & Andersen, P. (2015). Rethinking project management: A structured literature review with a critical look at the brave new world.International Journal of Project Management,33(2), 278-290.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
31 PROJECT MANAGEMENT Todorović, M. L., Petrović, D. Č., Mihić, M. M., Obradović, V. L., & Bushuyev, S. D. (2015). Project success analysis framework: A knowledge-based approach in project management.International Journal of Project Management,33(4), 772-783. Verzuh, E. (2015).The fast forward MBA in project management. John Wiley & Sons. Zwikael, O. (2016). International journal of project management special issue on “project benefit management”.