Project Practical: Bike Share Australia Name of the Student: Student ID: Name of the University: Author’s note:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Part A: Developing the Schedule AQ1: AQ2: a. It was required to maximize the resources to their maximum capacity, Levelling option for the project has been selected as shown below,
The following over allocation was faced, The tasks were sequentially arranged for the dealing with the over allocation b. BSA_PartAQ1.mppBSA_PartAQ2.mpp Total CostTotal DurationTotal CostTotal Duration $661,380.00237 days$661,380.00242 days
c. The modification in the project information was seen as the total duration for the activities of the project increased due to the addition of the predecessor in the project activities. However, since no change in duration of each of the activity or resources are done. There is no change in project cost. AQ3: Memo To:Mike Edwards From: <<name of the student>>, Project Manager Date: 19/5/18 Sub: Providing detail information about the project and informing about the project schedule Message The project plan has been developed using the iterative model of operations and aligning the development of the activities. The project is implied for easing the utilization of the planning process and forming the implication of the activities. The utilization of the operations has been deployed for forming the implication of the activities favouring the bike development and deployment between the 3 cities of Sydney, Melbourne, and Brisbane. The project would start from 28thMay, 2018 and would run for 242 days to complete on 6thMay, 2019. The project schedule has covered the addition of GPS tracking development, mobile application, assembly of bikes, and deporting it to the required location. The project can be shortened by allocating some more resources for the initial plan development.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Resource NameCost Transport Analyst$95,000.00 Business Analysts$132,480.00 Database Analysis$21,120.00 Software Engineers$193,600.00 Network Engineer$80,080.00 Mechanical Engineer$68,800.00 Technician$60,800.00 Flight$3,200.00 Accommodation$6,300.00 AQ4. a. The project duration can be shortened by the decreasing the timeline of critical activities. The addition of the resources would also be helpful for forming the list of the activities and allowing the successive development of the operations. b. BSA_PartAQ3.mppBSA_PartAQ4.mpp Total CostTotal DurationTotal CostTotal Duration $667,071.33205.68 days$667,071.33280.68 c.
It was required for levelling all the resources “out of slack time” for ensuring that the project is levelled and no resource allocation is faced. QA5. a. Risk No.Risk DescriptionImpactLikelihoodDegree 1Flight delay due to weather conditions and cloudy weather Delay in arriving at Brisbane/Melbourne for bike accumulation HighLow 2Errors in design of the mobile interface Mobile app would not work properly MediumHigh b. WBS numberTask NameDurationResource 2.2.5Prototyping the mobile interface 4Software Engineer
Part B: Revising the Plan BQ1: BQ2: ChangeImpact on Project durationExplanation Change 2.5.1 Sprint 1 35 days lessChange in predecessor Change 2.5.2 Sprint 2 35 days lessChange in predecessor Change 2.5.3 Sprint 3 No changeChange in predecessor Change 2.5.4 Sprint 4 1 day lessChange in predecessor ChangeImpact on Project CostExplanation Change 2.5.1 Sprint 1 Increased by $30240Extra resource allocation in the sprint Change 2.5.2 Sprint 2Increased by $14280 Extra resource allocation in the sprint Change 2.5.3 Sprint 3Increased by $63000 Extra resource allocation in the sprint Change 2.5.4 SprintIncreased by $30240Extra resource allocation in the sprint
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Bibliography Budayan, C., Dikmen, I., Birgonul, M.T. and Ghaziani, A., 2018. A computerized method for delay risk assessment based on fuzzy set theory using MS Project™.KSCE Journal of Civil Engineering, pp.1-12. Gharaibeh, H., 2014. Evaluating Project Management Software Packages Using a Scoring Model —A Comparison between MS Project and Primavera.Journal of Software Engineering and Applications,7(07), p.541.