This project management report discusses the planning, resource allocation, risk management and plan revision for Bike Share Australia. It includes a comparison of different project schedules, a memo to the project manager, and a WBS for the project.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head: PROJECT MANAGEMENT Project: Bike Share Australia Name of the Student Name of the University Author’s Note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1 PROJECT MANAGEMENT Table of Contents Part A- Question 2......................................................................................................................2 A) Resolving allocation issues...............................................................................................2 b) Comparison........................................................................................................................2 c) Causes for the differences..................................................................................................2 Part A-Question 3.......................................................................................................................2 Part A- Question 3......................................................................................................................3 Part A- Question 4......................................................................................................................4 a) Resource choice and explanation.......................................................................................4 b) Comparison........................................................................................................................4 c) Explanation........................................................................................................................4 Part A- Question 5......................................................................................................................4 a) Project risks........................................................................................................................4 B) Incorporating activates in WBS........................................................................................5 Part B: Plan revising...................................................................................................................5 Part B question 1....................................................................................................................5 Part B question 2........................................................................................................................5 Bibliography...............................................................................................................................7
2 PROJECT MANAGEMENT Part A- Question 2 A) Resolving allocation issues The problem of over allocation in the project schedule can be resolved by levelling the resource of the project but the tasks are not split and not adjusted individual assignment on a specific task. Due to levelling of resources the task, duration of the project enhances. After levelling, it is identified that the duration of the project enhances from 161 to 205 days. b) Comparison BSA_PartAQ1.mppBSA_PartAQ2.mpp Total durationTotal costTotal durationTotal cost 161 days$ 382,300.00205 days$ 382,300.00 c) Causes for the differences It is found that in PartAQ1.mpp, the estimated timeframe for the project is 161 days however in the PartAQ1.mpp the assumed time for the project is 205 days. The changes that is occurred within the duration is only due to levelling over-allocated resources. Additionally it is identified that though the duration of the project increases, the project cost remains constant. Part A-Question 3 Memo To:Mike Edwards From: <<Student name>>, Project Manager Date: 21/5/18 Sub: Providing information about the completion of the project planning stage
3 PROJECT MANAGEMENT Message The project “Bike share Australia” is planned successfully as per the scope as well as objectives of the project. It is found that as per the project planning stage; it is found that the project will get completed within 205 days by assuming the commencing date as 28thof May 2018. It is found that the entire project will get successfully finished within the expected date that is around 14-03-19. It is found that the entire schedule of the project includes activities that needs to be completed in order to successfully execute the project. The activities include development of software database, accounting management system, GPS tracking as well as mobile interface app. Additionally, the project schedule also have activities for travelling in different cities like Melbourne, Sydney as well as Brisbane. Moreover the completion of the project mainly includes different week offs and holidays. The estimated labour cost in the project is provided in the table below: Resource NameCost Transport analyst (TA)$ 95.00/hr. Business analyst (BA)$ 120.00/hr. Database analysis (DB)$ 110.00/hr. Software engineer (SE)$ 110.00/hr. Network engineer (NE)$ 110.00/hr. Mechanical engineer (ME)$ 100.00/hr. Technician (TN)$ 50.00/hr. Accommodation$ 100.00 Flight$ 200.00 Part A- Question 3 The project schedule is attached below:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
4 PROJECT MANAGEMENT Part A- Question 4 a) Resource choice and explanation It is found that Business analyst is selected for the project, as it is the resource that would have greatest impact on minimizing the project duration. b) Comparison BSA_PartAQ3.mppBSA_PartAQ4.mpp Total durationTotal costTotal durationTotal cost 189.67 days$ 385,820.00157.33 days$ 382,300.00 c) Explanation The difference that is identified in the BSA_PartAQ3.mpp and BSA_PartAQ3.mpp is due to the utilization of level options for overcoming over allocation of the resources automatically. Part A- Question 5 a) Project risks Risk NoDescriptionImpactLikelihoodDegree
5 PROJECT MANAGEMENT 1Incompatibility of system is one ofthemajor issueforthe entire project. Thisgenerally creates delay in theuser interface development LowHigh 2Data compatibilityis notviablefor the alignment of activities The chances of data loss is high duringtime processing MediumMedium B) Incorporating activates in WBS WBS numberTask NameDurationResource 2.7Undertaking testing for data capability and system design 5 daysSoftware Engineer Part B: Plan revising Part B question 1 The mpp. File is attached below: Part B question 2 ChangeImpact on ProjectExplanation
6 PROJECT MANAGEMENT duration Sprint 1 Changes the duration of the activity to 1.6 weeks This is mainly because as it generally starts as the same time when the data analysis of database started. Sprint 2Changesthedurationof the activity to 1.2 weeks This is due to the reason that it started after GPS tracking phase is completed. Sprint 3Changesthedurationof the activity to 2 weeks This is due to the fact that creation of circulation map completed. Sprint 4Changesthedurationof the activity to 0.8 weeks This is mainly because it mainly started after the deployment of the last bike. ChangeImpact on Project Cost Explanation Sprint 1 The cost of the activity changes to budget$ 31,040.00 This is because in the sprint resources including software engineer, database analyst, technician, transport analyst and business analyst are added. Sprint 2The cost of the activity changes to budget $23,280.00 As software engineer, database analyst, technician, transport analyst and business analyst, the cost of the activity enhances. Sprint 3Thecostofthe activitychangesto budget$ 38,800.00 This is due to the fact that in this sprint resources including software engineer, database analyst, technician, transport analyst and business analyst are
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
7 PROJECT MANAGEMENT added which leads to increment of project cost Sprint 4The cost of the activity changes to budget$ 15,520.00 As software engineer, database analyst, technician, transport analyst and business analyst, the cost of the activity increases.
8 PROJECT MANAGEMENT Bibliography Heldman, K., 2018.PMP: project management professional exam study guide. John Wiley & Sons. Hornstein, H.A., 2015. The integration of project management and organizational change managementisnowanecessity.InternationalJournalofProjectManagement,33(2), pp.291-298. Joslin, R. and Müller, R., 2015. Relationships between a project management methodology and project success in different project governance contexts.International Journal of Project Management,33(6), pp.1377-1392. Kerzner,H.,2017.Projectmanagementmetrics,KPIs,anddashboards:aguideto measuring and monitoring project performance. John Wiley & Sons. Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking projectmanagementperformanceandprojectsuccess.Internationaljournalofproject management,32(2), pp.202-217. Sánchez, M.A., 2015. Integrating sustainability issues into project management.Journal of Cleaner Production,96, pp.319-330. Svejvig, P. and Andersen, P., 2015. Rethinking project management: A structured literature reviewwitha criticallookatthebravenewworld.InternationalJournalofProject Management,33(2), pp.278-290. Todorović, M.L., Petrović, D.Č., Mihić, M.M., Obradović, V.L. and Bushuyev, S.D., 2015. Projectsuccessanalysisframework:Aknowledge-basedapproachinproject management.International Journal of Project Management,33(4), pp.772-783.