The report aims in preparation of a project plan related to the development of a Fitness App by the company App world Ink. The company is known to create all types of smartphone application to satisfy the needs of the customers. The current project that is undertaken by App world Ink, is based on development of a Fitness application. The application aims to provide all the necessary fitness tips and will incorporate in app purchases for the fitness products as well. The details of the schedule, budget and the risks are discussed in the plan that is developed.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
![Document Page](https://desklib.com/media/document/docfile/pages/bisy2004-bisy2004-fitness-app-name-of-bxqy/2024/09/11/a62cc958-96a6-44bb-b940-c2fd33ab0938-page-1.webp)
Running head: BISY2004
Bisy2004: Fitness APP
Name of Student
Name of University
Author Note
Bisy2004: Fitness APP
Name of Student
Name of University
Author Note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
![Document Page](https://desklib.com/media/document/docfile/pages/bisy2004-bisy2004-fitness-app-name-of-bxqy/2024/09/11/69e0b7ad-9b68-4d74-a716-60913cea151b-page-2.webp)
1
BISY2004
Executive Summary
The report aims in preparation of a project plan related to the development of a Fitness App by
the company App world Ink. The company is known to create all types of smartphone
application to satisfy the needs of the customers. The current project that is undertaken by App
world Ink, is based on development of a Fitness application. The application aims to provide all
the necessary fitness tips and will incorporate in app purchases for the fitness products as well.
The details of the schedule, budget and the risks are discussed in the plan that is developed.
BISY2004
Executive Summary
The report aims in preparation of a project plan related to the development of a Fitness App by
the company App world Ink. The company is known to create all types of smartphone
application to satisfy the needs of the customers. The current project that is undertaken by App
world Ink, is based on development of a Fitness application. The application aims to provide all
the necessary fitness tips and will incorporate in app purchases for the fitness products as well.
The details of the schedule, budget and the risks are discussed in the plan that is developed.
![Document Page](https://desklib.com/media/document/docfile/pages/bisy2004-bisy2004-fitness-app-name-of-bxqy/2024/09/11/c1c43936-d224-44fe-b8b6-22892c23823d-page-3.webp)
2
BISY2004
Table of Contents
Introduction..........................................................................................................................3
Background and Rationale...............................................................................................3
Project Charter.................................................................................................................3
1. Gantt chart.......................................................................................................................4
2. Network Diagram............................................................................................................5
3. Milestone.........................................................................................................................9
4. Resources Table.............................................................................................................11
5. Project Budget...............................................................................................................12
6. RACI Table....................................................................................................................16
7. Potential Risks...............................................................................................................18
8. Probability Impact Matrix..............................................................................................21
Conclusion.........................................................................................................................21
BISY2004
Table of Contents
Introduction..........................................................................................................................3
Background and Rationale...............................................................................................3
Project Charter.................................................................................................................3
1. Gantt chart.......................................................................................................................4
2. Network Diagram............................................................................................................5
3. Milestone.........................................................................................................................9
4. Resources Table.............................................................................................................11
5. Project Budget...............................................................................................................12
6. RACI Table....................................................................................................................16
7. Potential Risks...............................................................................................................18
8. Probability Impact Matrix..............................................................................................21
Conclusion.........................................................................................................................21
![Document Page](https://desklib.com/media/document/docfile/pages/bisy2004-bisy2004-fitness-app-name-of-bxqy/2024/09/11/9e1ac35c-eb78-4593-b3fe-a359cbc2b75e-page-4.webp)
3
BISY2004
Introduction
Background and Rationale
The project plan aims in providing the readers with a detailed information regarding the
scheduling needs of development of a Fitness application. The report provide the details of the
network diagram, milestone and the resources assigned. It is quite crucial to understand
requirement of the project to set up the budget of the project in an accurate manner. The major
milestone of the project. The potential project risks and significant issues are discussed in an
effective manner. Development of the project plan aims in overseeing of all the critical tasks and
the milestone of this project. The plan provides the detail of the time estimated for finishing the
project, along with the effort needed to execute the project in a set time. The project plan further
provides an idea of the Gantt chart and the network diagram prepared for project. The probability
impact matric that is prepared as a part of the project plan provides a description of the risks that
are required to be addressed in the project.
Project Charter
Project Title: Fitness App
Date of Approval: 26th December 2018
Starting Date: 26th December 2018
Completion Date: 26th April 2019
Key Schedule Milestone: Completion of Plan by 15th January 2019, Completion of model
development by 26th February, Finalization of Model Design by 14th March and Completion of
the Project by 26th April.
BISY2004
Introduction
Background and Rationale
The project plan aims in providing the readers with a detailed information regarding the
scheduling needs of development of a Fitness application. The report provide the details of the
network diagram, milestone and the resources assigned. It is quite crucial to understand
requirement of the project to set up the budget of the project in an accurate manner. The major
milestone of the project. The potential project risks and significant issues are discussed in an
effective manner. Development of the project plan aims in overseeing of all the critical tasks and
the milestone of this project. The plan provides the detail of the time estimated for finishing the
project, along with the effort needed to execute the project in a set time. The project plan further
provides an idea of the Gantt chart and the network diagram prepared for project. The probability
impact matric that is prepared as a part of the project plan provides a description of the risks that
are required to be addressed in the project.
Project Charter
Project Title: Fitness App
Date of Approval: 26th December 2018
Starting Date: 26th December 2018
Completion Date: 26th April 2019
Key Schedule Milestone: Completion of Plan by 15th January 2019, Completion of model
development by 26th February, Finalization of Model Design by 14th March and Completion of
the Project by 26th April.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
![Document Page](https://desklib.com/media/document/docfile/pages/bisy2004-bisy2004-fitness-app-name-of-bxqy/2024/09/11/2d68162c-c5bd-4a0f-bdad-0c251fb571ba-page-5.webp)
4
BISY2004
Total Budget: $358,120.00, with $2, 50,000 for Marketing
Project Manager: Ramandeep Kaur Kaul
1. Gantt chart
The figure 1 depicts the Gantt chart of the undertaken project. The figure provides the
detailed work breakdown structure as well. The column named “WBS” indicate the work
breakdown structure and the “Task Name” indicate the task to be executed for completion of the
project on a scheduled time (Kerzner and Kerzner 2017). The Gantt chart corresponding to the
development of a fitness application are as follows-
Figure 1: The Gantt chart corresponding to development of a Fitness Application
BISY2004
Total Budget: $358,120.00, with $2, 50,000 for Marketing
Project Manager: Ramandeep Kaur Kaul
1. Gantt chart
The figure 1 depicts the Gantt chart of the undertaken project. The figure provides the
detailed work breakdown structure as well. The column named “WBS” indicate the work
breakdown structure and the “Task Name” indicate the task to be executed for completion of the
project on a scheduled time (Kerzner and Kerzner 2017). The Gantt chart corresponding to the
development of a fitness application are as follows-
Figure 1: The Gantt chart corresponding to development of a Fitness Application
![Document Page](https://desklib.com/media/document/docfile/pages/bisy2004-bisy2004-fitness-app-name-of-bxqy/2024/09/11/b32e49b0-7818-491f-9936-a91d4903d0a0-page-6.webp)
5
BISY2004
The tasks which are to be executed as a part of the project is indicated in the Gantt chart.
It is observed that the entire project of development of the fitness application will take four
months. Figure 1 indicates that there are 7 major phases that are needed to be completed for
successful execution of the project. It is observed that a maximum time is allocated for the
development phase. The project will be successfully completed only if all the tasks are
completed within the scheduled deadline. The column “milestone” indicate whether a particular
activity is a milestone or not (Meredith et al., 2017). The Gantt chart indicate that the project has
7 major milestone including the last milestone, which is the “Project End”. The critical tasks of
the project are indicated in red. All the tasks marked in red indicate the project’s critical task.
2. Network Diagram
The figure 2, indicates the network diagram of the fitness application development
project. The network diagram is prepared, provide a critical view of the tasks which are to be
executed as a part of project execution phase. The network diagram of the Fitness app
development project, is depicted as follows-
BISY2004
The tasks which are to be executed as a part of the project is indicated in the Gantt chart.
It is observed that the entire project of development of the fitness application will take four
months. Figure 1 indicates that there are 7 major phases that are needed to be completed for
successful execution of the project. It is observed that a maximum time is allocated for the
development phase. The project will be successfully completed only if all the tasks are
completed within the scheduled deadline. The column “milestone” indicate whether a particular
activity is a milestone or not (Meredith et al., 2017). The Gantt chart indicate that the project has
7 major milestone including the last milestone, which is the “Project End”. The critical tasks of
the project are indicated in red. All the tasks marked in red indicate the project’s critical task.
2. Network Diagram
The figure 2, indicates the network diagram of the fitness application development
project. The network diagram is prepared, provide a critical view of the tasks which are to be
executed as a part of project execution phase. The network diagram of the Fitness app
development project, is depicted as follows-
![Document Page](https://desklib.com/media/document/docfile/pages/bisy2004-bisy2004-fitness-app-name-of-bxqy/2024/09/11/53e8f0bc-f056-4126-8f89-4205dd8b3827-page-7.webp)
6
BISY2004
BISY2004
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
![Document Page](https://desklib.com/media/document/docfile/pages/bisy2004-bisy2004-fitness-app-name-of-bxqy/2024/09/11/703a4936-9123-416f-bd66-dce9599e7ef9-page-8.webp)
7
BISY2004
BISY2004
![Document Page](https://desklib.com/media/document/docfile/pages/bisy2004-bisy2004-fitness-app-name-of-bxqy/2024/09/11/58a86fbf-5ec1-4f3a-b23b-74f642068eda-page-9.webp)
8
BISY2004
BISY2004
![Document Page](https://desklib.com/media/document/docfile/pages/bisy2004-bisy2004-fitness-app-name-of-bxqy/2024/09/11/aff8da74-a580-4b83-a4ea-aecaacc7b365-page-10.webp)
9
BISY2004
Figure 2: Representing the Network Diagram
3. Milestone
Milestone of a project generally signifies the critical tasks that are to be executed as a part
of project implementation. The milestone for this fitness development project is identifies on
basis of SMART criteria. With the help of the SMART criteria, the key events of the
development of the fitness app project is identified on basis of the criteria, which include,
specific, measurable, attainable and relevant to the project (Fleming and Koppelman 2016). The
milestone that are indicated in the table below are specific to the project undertaken, it is
attainable, measurable and is definitely relevant to the project undertaken. The project milestone
are shown as follows-
BISY2004
Figure 2: Representing the Network Diagram
3. Milestone
Milestone of a project generally signifies the critical tasks that are to be executed as a part
of project implementation. The milestone for this fitness development project is identifies on
basis of SMART criteria. With the help of the SMART criteria, the key events of the
development of the fitness app project is identified on basis of the criteria, which include,
specific, measurable, attainable and relevant to the project (Fleming and Koppelman 2016). The
milestone that are indicated in the table below are specific to the project undertaken, it is
attainable, measurable and is definitely relevant to the project undertaken. The project milestone
are shown as follows-
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
![Document Page](https://desklib.com/media/document/docfile/pages/bisy2004-bisy2004-fitness-app-name-of-bxqy/2024/09/11/3b4a93c0-5ddc-4c07-911a-8c96f3163eab-page-11.webp)
10
BISY2004
Milestone Date Status Responsible Comment
M1: Approval of
Project Plan
Tue 15-01-19 Completed Project Manager The Plan was
approved
M2: Sending the
model product
for Approval
Mon 25-02-19 Completed Application
Designer
The Model was
ready within the
expected time
M3: Finalization
of Model Design
and
Specification
Thu 14-03-19 Completed Application
Designer
All Good
M4: The Fitness
App is Ready to
Launch
Tue 09-04-19 Completed Application
Designer
The application
launch was one
schedule
M5: Application
Launch
Thu 11-04-19 Completed Project Manager All Good
M6: Completion
of Training
Tue 23-04-19 Completed Trainer The training was
needed
BISY2004
Milestone Date Status Responsible Comment
M1: Approval of
Project Plan
Tue 15-01-19 Completed Project Manager The Plan was
approved
M2: Sending the
model product
for Approval
Mon 25-02-19 Completed Application
Designer
The Model was
ready within the
expected time
M3: Finalization
of Model Design
and
Specification
Thu 14-03-19 Completed Application
Designer
All Good
M4: The Fitness
App is Ready to
Launch
Tue 09-04-19 Completed Application
Designer
The application
launch was one
schedule
M5: Application
Launch
Thu 11-04-19 Completed Project Manager All Good
M6: Completion
of Training
Tue 23-04-19 Completed Trainer The training was
needed
![Document Page](https://desklib.com/media/document/docfile/pages/bisy2004-bisy2004-fitness-app-name-of-bxqy/2024/09/11/72519a3d-e186-40e4-84a3-e35d4645cf90-page-12.webp)
11
BISY2004
M7: The Project
Ends
Fri 26-04-19 Completed Project Manager All good
The table above indicates the most significant milestone of the project considered. Since
the project has been already completed, it is observed that all the milestone are achieved within
the set date. The above indicated seven milestone was quite critical to ascertain that the Fitness
app development project has been finished in a successful manner. The table further indicates the
date of achievement of the milestone and the person who was responsible for achieving the
milestone.
4. Resources Table
Appropriate estimate and calculation of the resources needed for the project was
necessary in order to ensure that the fitness app development project is executed accordingly. For
ensuring that the fitness application is developed in effective way, the most essential resources
needed for the project is estimated and is allocated to each of the task (Heagney 2016). The
project cost is analyzed on basis of the resources and the cost of each resources. The resources
considered for this firness development project are indicated in the table below-
Resource
Name Type Materia
l Label Initials Grou
p
Max.
Units Std. Rate Ovt.
Rate Cost/Use Accrue
At
Base
Calendar Overallocated
Project
Manager Work P 100% $90.00/hr $0.00/
hr $0.00 Prorated Standard No
Business
Analyst Work B 100% $50.00/hr $0.00/
hr $0.00 Prorated Standard No
Resource
Manager Work R 100% $60.00/hr $0.00/
hr $0.00 Prorated Standard No
Marketing
Manager Work M 100% $75.00/hr $0.00/
hr $0.00 Prorated Standard No
BISY2004
M7: The Project
Ends
Fri 26-04-19 Completed Project Manager All good
The table above indicates the most significant milestone of the project considered. Since
the project has been already completed, it is observed that all the milestone are achieved within
the set date. The above indicated seven milestone was quite critical to ascertain that the Fitness
app development project has been finished in a successful manner. The table further indicates the
date of achievement of the milestone and the person who was responsible for achieving the
milestone.
4. Resources Table
Appropriate estimate and calculation of the resources needed for the project was
necessary in order to ensure that the fitness app development project is executed accordingly. For
ensuring that the fitness application is developed in effective way, the most essential resources
needed for the project is estimated and is allocated to each of the task (Heagney 2016). The
project cost is analyzed on basis of the resources and the cost of each resources. The resources
considered for this firness development project are indicated in the table below-
Resource
Name Type Materia
l Label Initials Grou
p
Max.
Units Std. Rate Ovt.
Rate Cost/Use Accrue
At
Base
Calendar Overallocated
Project
Manager Work P 100% $90.00/hr $0.00/
hr $0.00 Prorated Standard No
Business
Analyst Work B 100% $50.00/hr $0.00/
hr $0.00 Prorated Standard No
Resource
Manager Work R 100% $60.00/hr $0.00/
hr $0.00 Prorated Standard No
Marketing
Manager Work M 100% $75.00/hr $0.00/
hr $0.00 Prorated Standard No
![Document Page](https://desklib.com/media/document/docfile/pages/bisy2004-bisy2004-fitness-app-name-of-bxqy/2024/09/11/dcec4675-18dd-43a9-9cc1-a6005e74184c-page-13.webp)
12
BISY2004
Advertising
Head Work A 100% $80.00/hr $0.00/
hr $0.00 Prorated Standard No
Database
Administrato
r
Work D 100% $60.00/hr $0.00/
hr $0.00 Prorated Standard No
Programmers Work P 500% $60.00/hr $0.00/
hr $0.00 Prorated Standard No
Software
Testers Work S 100% $55.00/hr $0.00/
hr $0.00 Prorated Standard No
Software
Engineers Work S 100% $60.00/hr $0.00/
hr $0.00 Prorated Standard No
Trainers Work T 200% $35.00/hr $0.00/
hr $0.00 Prorated Standard No
Software Material S $0.00 $20,000.00 Prorated No
Hardware Material H $0.00 $15,000.00 Prorated No
Advertising
and
Marketing
Material A $0.00 $250,000.00 Prorated No
Training Material T $0.00 $2,000.00 Prorated No
The above table provides an idea of the human resources and the materials required for
the project. The table indicates that there are no over allocation of the resources. The budget of
the project is set on basis of the cost of the resources. The table indicates all the resources that
have been considered for this particular project including their cost.
5. Project Budget
It is necessary to estimate the project’s budget to check if the implementation of the
project would be an economically feasible idea. The budget of this particular project is estimated
on basis of the resource requirements and the duration for the completion of the tasks. The cost
of execution of this particular project is shown in the table below-
Task Name Duration Cost
Development of Fitness APP 88 days $358,120.00
Phase 1 Planning 15 days $12,480.00
Finding out the requirements 2 days $1,440.00
Estimating cost 3 days $2,640.00
Creating team 2 days $1,440.00
BISY2004
Advertising
Head Work A 100% $80.00/hr $0.00/
hr $0.00 Prorated Standard No
Database
Administrato
r
Work D 100% $60.00/hr $0.00/
hr $0.00 Prorated Standard No
Programmers Work P 500% $60.00/hr $0.00/
hr $0.00 Prorated Standard No
Software
Testers Work S 100% $55.00/hr $0.00/
hr $0.00 Prorated Standard No
Software
Engineers Work S 100% $60.00/hr $0.00/
hr $0.00 Prorated Standard No
Trainers Work T 200% $35.00/hr $0.00/
hr $0.00 Prorated Standard No
Software Material S $0.00 $20,000.00 Prorated No
Hardware Material H $0.00 $15,000.00 Prorated No
Advertising
and
Marketing
Material A $0.00 $250,000.00 Prorated No
Training Material T $0.00 $2,000.00 Prorated No
The above table provides an idea of the human resources and the materials required for
the project. The table indicates that there are no over allocation of the resources. The budget of
the project is set on basis of the cost of the resources. The table indicates all the resources that
have been considered for this particular project including their cost.
5. Project Budget
It is necessary to estimate the project’s budget to check if the implementation of the
project would be an economically feasible idea. The budget of this particular project is estimated
on basis of the resource requirements and the duration for the completion of the tasks. The cost
of execution of this particular project is shown in the table below-
Task Name Duration Cost
Development of Fitness APP 88 days $358,120.00
Phase 1 Planning 15 days $12,480.00
Finding out the requirements 2 days $1,440.00
Estimating cost 3 days $2,640.00
Creating team 2 days $1,440.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
![Document Page](https://desklib.com/media/document/docfile/pages/bisy2004-bisy2004-fitness-app-name-of-bxqy/2024/09/11/1c62d023-88c1-422a-9adc-b0397a529350-page-14.webp)
13
BISY2004
dividing roles 1 day $480.00
setting positions 1 day $720.00
Design the plan and time duration
for the task 7 days $5,040.00
Development of Project Plan 1 day $720.00
M1: Approval of Project Plan 0 days $0.00
Phase 2 Development 29 days $19,200.00
Start of the work as per plan 1 day $960.00
Development of Prototype Design 10 days $9,600.00
Development of the model product 18 days $8,640.00
M2: Sending the model product for
Approval 0 days $0.00
Phase 3 Finalizing 13 days $7,840.00
The Model is reviewed by the top
Management 3 days $0.00
Testing of the model Application 5 days $4,600.00
Mistakes and Bugs are Identified 3 days $1,320.00
The Bugs are Fixed 2 days $1,920.00
M3: Finalization of Model Design
and Specification 0 days $0.00
Phase 4: Final Application
Development 18 days $53,640.00
Coding is completed as per
specifications 13 days $47,480.00
Database Coding 7 days $3,360.00
The Database is linked with the
application 2 days $960.00
System Testing 2 days $880.00
Bug Fixing 1 day $960.00
M4: The Fitness App is Ready to
Launch 0 days $0.00
Phase 5: Launch 2 days $254,240.00
Preparation of Launch 1 day $251,240.00
Sending out invites 1 day $600.00
Development of Training Modules 2 days $2,400.00
M5: Application Launch 0 days $0.00
Phase 6: Training 8 days $8,080.00
Training Preparations 1 day $720.00
Training the staffs about operation
of the application 7 days $3,960.00
Training on Safety Maintenance 5 days $3,400.00
M6: Completion of Training 0 days $0.00
BISY2004
dividing roles 1 day $480.00
setting positions 1 day $720.00
Design the plan and time duration
for the task 7 days $5,040.00
Development of Project Plan 1 day $720.00
M1: Approval of Project Plan 0 days $0.00
Phase 2 Development 29 days $19,200.00
Start of the work as per plan 1 day $960.00
Development of Prototype Design 10 days $9,600.00
Development of the model product 18 days $8,640.00
M2: Sending the model product for
Approval 0 days $0.00
Phase 3 Finalizing 13 days $7,840.00
The Model is reviewed by the top
Management 3 days $0.00
Testing of the model Application 5 days $4,600.00
Mistakes and Bugs are Identified 3 days $1,320.00
The Bugs are Fixed 2 days $1,920.00
M3: Finalization of Model Design
and Specification 0 days $0.00
Phase 4: Final Application
Development 18 days $53,640.00
Coding is completed as per
specifications 13 days $47,480.00
Database Coding 7 days $3,360.00
The Database is linked with the
application 2 days $960.00
System Testing 2 days $880.00
Bug Fixing 1 day $960.00
M4: The Fitness App is Ready to
Launch 0 days $0.00
Phase 5: Launch 2 days $254,240.00
Preparation of Launch 1 day $251,240.00
Sending out invites 1 day $600.00
Development of Training Modules 2 days $2,400.00
M5: Application Launch 0 days $0.00
Phase 6: Training 8 days $8,080.00
Training Preparations 1 day $720.00
Training the staffs about operation
of the application 7 days $3,960.00
Training on Safety Maintenance 5 days $3,400.00
M6: Completion of Training 0 days $0.00
![Document Page](https://desklib.com/media/document/docfile/pages/bisy2004-bisy2004-fitness-app-name-of-bxqy/2024/09/11/a4c595a2-51af-4718-8d9a-8b892300abca-page-15.webp)
14
BISY2004
Phase 7: Evaluation and Closure 3 days $2,640.00
Completion of verification and
Validation Activities 2 days $1,440.00
Payment Completion 1 day $720.00
Resource Release 1 day $480.00
M7: The Project Ends 0 days $0.00
The above table represents the cost that is needed to be considered for execution of the
project on time. The cost table view of the estimated budget of the fitness app development
project is indicated as follows-
Task Name Fixed
Cost
Fixed Cost
Accrual Total Cost Baseline Variance Actual Remaining
Development of
Fitness APP $0.00 Prorated $358,120.00 $0.00 $358,120.00 $0.00 $358,120.00
Phase 1
Planning $0.00 Prorated $12,480.00 $0.00 $12,480.00 $0.00 $12,480.00
Finding out
the requirements $0.00 Prorated $1,440.00 $0.00 $1,440.00 $0.00 $1,440.00
Estimating
cost $0.00 Prorated $2,640.00 $0.00 $2,640.00 $0.00 $2,640.00
Creating team $0.00 Prorated $1,440.00 $0.00 $1,440.00 $0.00 $1,440.00
dividing roles $0.00 Prorated $480.00 $0.00 $480.00 $0.00 $480.00
setting
positions $0.00 Prorated $720.00 $0.00 $720.00 $0.00 $720.00
Design the
plan and time
duration for the
task
$0.00 Prorated $5,040.00 $0.00 $5,040.00 $0.00 $5,040.00
Development
of Project Plan $0.00 Prorated $720.00 $0.00 $720.00 $0.00 $720.00
M1: Approval
of Project Plan $0.00 Prorated $0.00 $0.00 $0.00 $0.00 $0.00
Phase 2
Development $0.00 Prorated $19,200.00 $0.00 $19,200.00 $0.00 $19,200.00
Start of the
work as per plan $0.00 Prorated $960.00 $0.00 $960.00 $0.00 $960.00
Development
of Prototype
Design
$0.00 Prorated $9,600.00 $0.00 $9,600.00 $0.00 $9,600.00
BISY2004
Phase 7: Evaluation and Closure 3 days $2,640.00
Completion of verification and
Validation Activities 2 days $1,440.00
Payment Completion 1 day $720.00
Resource Release 1 day $480.00
M7: The Project Ends 0 days $0.00
The above table represents the cost that is needed to be considered for execution of the
project on time. The cost table view of the estimated budget of the fitness app development
project is indicated as follows-
Task Name Fixed
Cost
Fixed Cost
Accrual Total Cost Baseline Variance Actual Remaining
Development of
Fitness APP $0.00 Prorated $358,120.00 $0.00 $358,120.00 $0.00 $358,120.00
Phase 1
Planning $0.00 Prorated $12,480.00 $0.00 $12,480.00 $0.00 $12,480.00
Finding out
the requirements $0.00 Prorated $1,440.00 $0.00 $1,440.00 $0.00 $1,440.00
Estimating
cost $0.00 Prorated $2,640.00 $0.00 $2,640.00 $0.00 $2,640.00
Creating team $0.00 Prorated $1,440.00 $0.00 $1,440.00 $0.00 $1,440.00
dividing roles $0.00 Prorated $480.00 $0.00 $480.00 $0.00 $480.00
setting
positions $0.00 Prorated $720.00 $0.00 $720.00 $0.00 $720.00
Design the
plan and time
duration for the
task
$0.00 Prorated $5,040.00 $0.00 $5,040.00 $0.00 $5,040.00
Development
of Project Plan $0.00 Prorated $720.00 $0.00 $720.00 $0.00 $720.00
M1: Approval
of Project Plan $0.00 Prorated $0.00 $0.00 $0.00 $0.00 $0.00
Phase 2
Development $0.00 Prorated $19,200.00 $0.00 $19,200.00 $0.00 $19,200.00
Start of the
work as per plan $0.00 Prorated $960.00 $0.00 $960.00 $0.00 $960.00
Development
of Prototype
Design
$0.00 Prorated $9,600.00 $0.00 $9,600.00 $0.00 $9,600.00
![Document Page](https://desklib.com/media/document/docfile/pages/bisy2004-bisy2004-fitness-app-name-of-bxqy/2024/09/11/0d4c2643-ab98-4a65-a63a-2a12beed1c67-page-16.webp)
15
BISY2004
Development
of the model
product
$0.00 Prorated $8,640.00 $0.00 $8,640.00 $0.00 $8,640.00
M2: Sending
the model product
for Approval
$0.00 Prorated $0.00 $0.00 $0.00 $0.00 $0.00
Phase 3
Finalizing $0.00 Prorated $7,840.00 $0.00 $7,840.00 $0.00 $7,840.00
The Model is
reviewed by the
top Management
$0.00 Prorated $0.00 $0.00 $0.00 $0.00 $0.00
Testing of the
model
Application
$0.00 Prorated $4,600.00 $0.00 $4,600.00 $0.00 $4,600.00
Mistakes and
Bugs are
Identified
$0.00 Prorated $1,320.00 $0.00 $1,320.00 $0.00 $1,320.00
The Bugs are
Fixed $0.00 Prorated $1,920.00 $0.00 $1,920.00 $0.00 $1,920.00
M3:
Finalization of
Model Design and
Specification
$0.00 Prorated $0.00 $0.00 $0.00 $0.00 $0.00
Phase 4: Final
Application
Development
$0.00 Prorated $53,640.00 $0.00 $53,640.00 $0.00 $53,640.00
Coding is
completed as per
specifications
$0.00 Prorated $47,480.00 $0.00 $47,480.00 $0.00 $47,480.00
Database
Coding $0.00 Prorated $3,360.00 $0.00 $3,360.00 $0.00 $3,360.00
The Database
is linked with the
application
$0.00 Prorated $960.00 $0.00 $960.00 $0.00 $960.00
System
Testing $0.00 Prorated $880.00 $0.00 $880.00 $0.00 $880.00
Bug Fixing $0.00 Prorated $960.00 $0.00 $960.00 $0.00 $960.00
M4: The
Fitness App is
Ready to Launch
$0.00 Prorated $0.00 $0.00 $0.00 $0.00 $0.00
Phase 5:
Launch $0.00 Prorated $254,240.00 $0.00 $254,240.00 $0.00 $254,240.00
Preparation of
Launch $0.00 Prorated $251,240.00 $0.00 $251,240.00 $0.00 $251,240.00
BISY2004
Development
of the model
product
$0.00 Prorated $8,640.00 $0.00 $8,640.00 $0.00 $8,640.00
M2: Sending
the model product
for Approval
$0.00 Prorated $0.00 $0.00 $0.00 $0.00 $0.00
Phase 3
Finalizing $0.00 Prorated $7,840.00 $0.00 $7,840.00 $0.00 $7,840.00
The Model is
reviewed by the
top Management
$0.00 Prorated $0.00 $0.00 $0.00 $0.00 $0.00
Testing of the
model
Application
$0.00 Prorated $4,600.00 $0.00 $4,600.00 $0.00 $4,600.00
Mistakes and
Bugs are
Identified
$0.00 Prorated $1,320.00 $0.00 $1,320.00 $0.00 $1,320.00
The Bugs are
Fixed $0.00 Prorated $1,920.00 $0.00 $1,920.00 $0.00 $1,920.00
M3:
Finalization of
Model Design and
Specification
$0.00 Prorated $0.00 $0.00 $0.00 $0.00 $0.00
Phase 4: Final
Application
Development
$0.00 Prorated $53,640.00 $0.00 $53,640.00 $0.00 $53,640.00
Coding is
completed as per
specifications
$0.00 Prorated $47,480.00 $0.00 $47,480.00 $0.00 $47,480.00
Database
Coding $0.00 Prorated $3,360.00 $0.00 $3,360.00 $0.00 $3,360.00
The Database
is linked with the
application
$0.00 Prorated $960.00 $0.00 $960.00 $0.00 $960.00
System
Testing $0.00 Prorated $880.00 $0.00 $880.00 $0.00 $880.00
Bug Fixing $0.00 Prorated $960.00 $0.00 $960.00 $0.00 $960.00
M4: The
Fitness App is
Ready to Launch
$0.00 Prorated $0.00 $0.00 $0.00 $0.00 $0.00
Phase 5:
Launch $0.00 Prorated $254,240.00 $0.00 $254,240.00 $0.00 $254,240.00
Preparation of
Launch $0.00 Prorated $251,240.00 $0.00 $251,240.00 $0.00 $251,240.00
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
![Document Page](https://desklib.com/media/document/docfile/pages/bisy2004-bisy2004-fitness-app-name-of-bxqy/2024/09/11/9cf6c35a-8d28-4bb3-a60d-37f9712b8b6a-page-17.webp)
16
BISY2004
Sending out
invites $0.00 Prorated $600.00 $0.00 $600.00 $0.00 $600.00
Development
of Training
Modules
$0.00 Prorated $2,400.00 $0.00 $2,400.00 $0.00 $2,400.00
M5:
Application
Launch
$0.00 Prorated $0.00 $0.00 $0.00 $0.00 $0.00
Phase 6:
Training $0.00 Prorated $8,080.00 $0.00 $8,080.00 $0.00 $8,080.00
Training
Preparations $0.00 Prorated $720.00 $0.00 $720.00 $0.00 $720.00
Training the
staffs about
operation of the
application
$0.00 Prorated $3,960.00 $0.00 $3,960.00 $0.00 $3,960.00
Training on
Safety
Maintenance
$0.00 Prorated $3,400.00 $0.00 $3,400.00 $0.00 $3,400.00
M6:
Completion of
Training
$0.00 Prorated $0.00 $0.00 $0.00 $0.00 $0.00
Phase 7:
Evaluation and
Closure
$0.00 Prorated $2,640.00 $0.00 $2,640.00 $0.00 $2,640.00
Completion of
verification and
Validation
Activities
$0.00 Prorated $1,440.00 $0.00 $1,440.00 $0.00 $1,440.00
Payment
Completion $0.00 Prorated $720.00 $0.00 $720.00 $0.00 $720.00
Resource
Release $0.00 Prorated $480.00 $0.00 $480.00 $0.00 $480.00
M7: The
Project Ends $0.00 Prorated $0.00 $0.00 $0.00 $0.00 $0.00
6. RACI Table
BISY2004
Sending out
invites $0.00 Prorated $600.00 $0.00 $600.00 $0.00 $600.00
Development
of Training
Modules
$0.00 Prorated $2,400.00 $0.00 $2,400.00 $0.00 $2,400.00
M5:
Application
Launch
$0.00 Prorated $0.00 $0.00 $0.00 $0.00 $0.00
Phase 6:
Training $0.00 Prorated $8,080.00 $0.00 $8,080.00 $0.00 $8,080.00
Training
Preparations $0.00 Prorated $720.00 $0.00 $720.00 $0.00 $720.00
Training the
staffs about
operation of the
application
$0.00 Prorated $3,960.00 $0.00 $3,960.00 $0.00 $3,960.00
Training on
Safety
Maintenance
$0.00 Prorated $3,400.00 $0.00 $3,400.00 $0.00 $3,400.00
M6:
Completion of
Training
$0.00 Prorated $0.00 $0.00 $0.00 $0.00 $0.00
Phase 7:
Evaluation and
Closure
$0.00 Prorated $2,640.00 $0.00 $2,640.00 $0.00 $2,640.00
Completion of
verification and
Validation
Activities
$0.00 Prorated $1,440.00 $0.00 $1,440.00 $0.00 $1,440.00
Payment
Completion $0.00 Prorated $720.00 $0.00 $720.00 $0.00 $720.00
Resource
Release $0.00 Prorated $480.00 $0.00 $480.00 $0.00 $480.00
M7: The
Project Ends $0.00 Prorated $0.00 $0.00 $0.00 $0.00 $0.00
6. RACI Table
![Document Page](https://desklib.com/media/document/docfile/pages/bisy2004-bisy2004-fitness-app-name-of-bxqy/2024/09/11/8fd6b6a6-b8e0-4874-af1d-ebbc9f078c69-page-18.webp)
17
BISY2004
The RACI table provides an idea of the team members who are Responsible (R),
Accountable (A), was Consulted (C), or Informed (I) about a particular task (Mir and Pinnington
2014.). This table helps in assigning responsibilities to the team
Project
Manager
Resource
Manager
Marketing
and
Advertising
Head
Business
Analyst
Software
Engineers
Initiation
Document
R A I C I
Project
Charter
R A I C I
Project Plan R A I C I
Scope A R I I I
Stakeholder
Matric
A R C C I
WBS and
Gantt Chart
R A I I C
Milestone R A I I C
Resources A R A C I
Budget A R A C I
BISY2004
The RACI table provides an idea of the team members who are Responsible (R),
Accountable (A), was Consulted (C), or Informed (I) about a particular task (Mir and Pinnington
2014.). This table helps in assigning responsibilities to the team
Project
Manager
Resource
Manager
Marketing
and
Advertising
Head
Business
Analyst
Software
Engineers
Initiation
Document
R A I C I
Project
Charter
R A I C I
Project Plan R A I C I
Scope A R I I I
Stakeholder
Matric
A R C C I
WBS and
Gantt Chart
R A I I C
Milestone R A I I C
Resources A R A C I
Budget A R A C I
![Document Page](https://desklib.com/media/document/docfile/pages/bisy2004-bisy2004-fitness-app-name-of-bxqy/2024/09/11/1113f5ba-be2c-4d66-bc68-9dd3332645b9-page-19.webp)
18
BISY2004
The RACI table above provides a knowledge of the responsibilities of the most
prominent resources in the development of the fitness application project (Kerzner 2018). The
RACI table provides the details of the responsibility of each member of the team.
7. Potential Risks
Identification of the risks and uncertainties are critical for executing the project in an
effective manner (Marchewka 2014). The major risks to which this project is exposed to in
indicated
BISY2004
The RACI table above provides a knowledge of the responsibilities of the most
prominent resources in the development of the fitness application project (Kerzner 2018). The
RACI table provides the details of the responsibility of each member of the team.
7. Potential Risks
Identification of the risks and uncertainties are critical for executing the project in an
effective manner (Marchewka 2014). The major risks to which this project is exposed to in
indicated
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
![Document Page](https://desklib.com/media/document/docfile/pages/bisy2004-bisy2004-fitness-app-name-of-bxqy/2024/09/11/c1c078f6-d371-451e-a7ac-a902f8f9f258-page-20.webp)
19
BISY2004
No. Ro1 RO2 RO3 RO4 RO5 RO6
Rank 1 2 3 4 5 6
Risk Schedule issues Budgeting
Issues
Technical Fault Resource
Shortage
Operational Scope of
Improvement
Detected
Description Delays in
project
execution is
seen
The cost
estimated for the
project is
insufficient
Issues in linking
with the server
is detected
Unavailability of
the estimated
resources
Operational
Failure is seen
Project
developed has
scope of
Improvement
Category Schedule Risk Financial Risk Technical Risk Resource Risk Operational Risk Scope Creep
Root Cause Improper
estimate
Improper
estimate
Ineffective
supervision
Improper
estimate
Improper bug
fixing
Improper
estimate
Triggers Overtask Delays Ineffective
supervision
Overtask Inexperienced
team
Improvement in
project is needed
Potential
Response
Modify Avoid Accept Avoid Accept Share
Risk Owner Project Manager Project Manager Technical Resource Technical Project Manager
BISY2004
No. Ro1 RO2 RO3 RO4 RO5 RO6
Rank 1 2 3 4 5 6
Risk Schedule issues Budgeting
Issues
Technical Fault Resource
Shortage
Operational Scope of
Improvement
Detected
Description Delays in
project
execution is
seen
The cost
estimated for the
project is
insufficient
Issues in linking
with the server
is detected
Unavailability of
the estimated
resources
Operational
Failure is seen
Project
developed has
scope of
Improvement
Category Schedule Risk Financial Risk Technical Risk Resource Risk Operational Risk Scope Creep
Root Cause Improper
estimate
Improper
estimate
Ineffective
supervision
Improper
estimate
Improper bug
fixing
Improper
estimate
Triggers Overtask Delays Ineffective
supervision
Overtask Inexperienced
team
Improvement in
project is needed
Potential
Response
Modify Avoid Accept Avoid Accept Share
Risk Owner Project Manager Project Manager Technical Resource Technical Project Manager
![Document Page](https://desklib.com/media/document/docfile/pages/bisy2004-bisy2004-fitness-app-name-of-bxqy/2024/09/11/f6b09671-041e-4e55-89a7-797f2c5543be-page-21.webp)
20
BISY2004
Expert Manager Expert
Probability 60% 50% 45% 35% 25% 20%
Impact High High Medium Medium Low Low
Status Stand by Stand by Stand by Stand by Stand by Stand by
The Table above identifies the major risks and the root cause of each risk. These risks were addressed to complete the project
on time.
BISY2004
Expert Manager Expert
Probability 60% 50% 45% 35% 25% 20%
Impact High High Medium Medium Low Low
Status Stand by Stand by Stand by Stand by Stand by Stand by
The Table above identifies the major risks and the root cause of each risk. These risks were addressed to complete the project
on time.
![Document Page](https://desklib.com/media/document/docfile/pages/bisy2004-bisy2004-fitness-app-name-of-bxqy/2024/09/11/b056d822-74c6-4330-8365-ded08bedbe14-page-22.webp)
21
BISY2004
8. Probability Impact Matrix
The probability impact matrix indicates the actual impact of the identified risk (Too and
Weaver 2014).
Probability
High R01
Medium R03, R04 R02
Low R05,R06
Low Medium High
Impact
Conclusion
The enveloped project plan gives an idea of the tasks, required to be completed, to
complete the project successfully. The project plan indicate that it is possible to complete the
project in the identified schedule and the budget. The plan identifies the significant risk and the
issues, management of which indicated that there is no direct effect of those risks on the project.
The probability impact matrix that is developed provide an idea of the impact of the risks.
BISY2004
8. Probability Impact Matrix
The probability impact matrix indicates the actual impact of the identified risk (Too and
Weaver 2014).
Probability
High R01
Medium R03, R04 R02
Low R05,R06
Low Medium High
Impact
Conclusion
The enveloped project plan gives an idea of the tasks, required to be completed, to
complete the project successfully. The project plan indicate that it is possible to complete the
project in the identified schedule and the budget. The plan identifies the significant risk and the
issues, management of which indicated that there is no direct effect of those risks on the project.
The probability impact matrix that is developed provide an idea of the impact of the risks.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
![Document Page](https://desklib.com/media/document/docfile/pages/bisy2004-bisy2004-fitness-app-name-of-bxqy/2024/09/11/90b34708-4d43-4b5a-a509-ca5ac0da83d9-page-23.webp)
22
BISY2004
References
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management.
Project Management Institute.
Heagney, J., 2016. Fundamentals of project management. Amacom.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Kerzner, H., 2018. Project management best practices: Achieving global excellence. John Wiley
& Sons.
Marchewka, J.T., 2014. Information technology project management. John Wiley & Sons.
Meredith, J.R., Mantel Jr, S.J. and Shafer, S.M., 2017. Project management: a managerial
approach. John Wiley & Sons.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking
project management performance and project success. International journal of project
management, 32(2), pp.202-217.
Too, E.G. and Weaver, P., 2014. The management of project management: A conceptual
framework for project governance. International Journal of Project Management, 32(8),
pp.1382-1394.
BISY2004
References
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management.
Project Management Institute.
Heagney, J., 2016. Fundamentals of project management. Amacom.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Kerzner, H., 2018. Project management best practices: Achieving global excellence. John Wiley
& Sons.
Marchewka, J.T., 2014. Information technology project management. John Wiley & Sons.
Meredith, J.R., Mantel Jr, S.J. and Shafer, S.M., 2017. Project management: a managerial
approach. John Wiley & Sons.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking
project management performance and project success. International journal of project
management, 32(2), pp.202-217.
Too, E.G. and Weaver, P., 2014. The management of project management: A conceptual
framework for project governance. International Journal of Project Management, 32(8),
pp.1382-1394.
1 out of 23
Related Documents
![[object Object]](/_next/image/?url=%2F_next%2Fstatic%2Fmedia%2Flogo.6d15ce61.png&w=640&q=75)
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.