This assessment guide provides information on BSBPMG514 Manage Project Cost, including the purpose of assessment, competencies being assessed, assessment requirements, and technical tools for completing the assessment.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
photocopying, recording or otherwise without the prior written permission of Australian College of Business Intelligence. Disclaimer: The Australian College of Business Intelligence does not invite reliance upon, nor accept responsibility for, the information it provides. The Australian College of Business Intelligence makes every effort to provide a high-quality service. However, neither the Australian College of Business Intelligence, nor the providers of data, gives any guarantees, undertakings or warranties concerning the accuracy, completeness or up-to-date nature of the information provided. Users should confirm information from another source if it is of sufficient importance for them to do so. Content s 1. Assessment Information......................................................................................................4 A. Purpose of assessment........................................................................................................................4 B. Competencies being assessed.............................................................................................................4 C. What you are required to do...............................................................................................................5 D. Adjustment and Support.....................................................................................................................7 E. Assessment submission.......................................................................................................................7
F. Assessment results and feedback........................................................................................................8 G. Technical tools for completing this assessment..................................................................................9 2. Assessment Coversheet.....................................................................................................10 3. Assessment Requirements.................................................................................................11 A. Overview...........................................................................................................................................11 B. Task 1 – Questioningi. Instructions for students............................................................................12 4. Marking Guide...................................................................................................................28 A. Marking Guide for Tasks 1 & 2 & 3....................................................................................................28
1. Assessment Information A. Purpose of assessment This assessment will develop your skills and knowledge skills and knowledge required to identify, analyse and refine project costs to produce a budget, and to use this budget as the principal mechanism to control project cost. The assessment is designed to help you gather evidence of your competence against the requirements of the unit of competency, as outlined below. Your evidence may take a variety of forms and must be: Authentic – your own work Valid – related to the competency Sufficient – appropriate quantity and quality Current – recent proof of your skills and knowledge B. Competencies being assessed Elements To achieve competency in this unit students must demonstrate their ability to: 1.Determine project cost 2.Monitor and control project cost 3.Complete cost-management processes Performance Evidence Evidence of the ability to: Work closely with others to determine resources against budgetary frameworks Prepare a budget and cost-management plan for a project Monitor costs across a project's life cycle including solving cost variations and analysing possible alternatives Record expenditure, create accurate financial reports and review cost-management processes Knowledge Evidence To complete the unit requirements safely and effectively, you must: Explain appropriate budgeting processes, tools and techniques
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Describe methods and tools for costing and cost analysis Explain strategies for managing costs and their application in different situations Outline processes for reviewing costs against outcomes Summarise key organisational policies and procedures applicable to this role For further information on the competencies of this unit, please refer to: https://training.gov.au/Training/Details/BSBPMG514 C. What you are required to do This assessment requires you toanswer all questions within each Assessment Task and be assessed as “Satisfactory” in each to gain competency inBSBPMG514 Manage Project Cost. Task 1 For Task 1, you are required to analyse different models and tools utilised in managing a project’s cost. You will also demonstrate understanding of the various components needed in developing and implementing a project. Task 2 For Task 2, you are a Project Manager with OzMarket Consulting. You have been employed to project manage a new garden for a local park. You are required to write a financial report listing the costings of the project and to revise financial projections due to changes that occur during the implementation phase. Task 3 Task 3 requires you to report on the financial outcomes of the project and to summarise the financial issues that arose in order to take into account for future projects. For further details, please refer to the “Assessment Requirements” section of this document. Assessment resources To enable you to complete this assessment, the following documents have been provided in the unit course page on Moodleunit on Moodle:BSBPMG514 Manage Project Cost Learner Guide BSBPMG514 Manage Project Cost PowerPoint slides PMBOK 5th edition – refer to Chapter 7, “Project Cost Management” on pages 193 - 226
BSBPMG514 Marking Guide Sample Project management plan A note on plagiarism and referencing Plagiarism is a form of theft where the work, ideas, inventions etc. of other people are presented as your own. When quoting or paraphrasing from a source such as the Internet, the source must be recognised. If you are quoting a source, make sure to acknowledge this by including “quotation marks” around the relevant words/sentences or ideas. Note the source at the point at which it is included within your assessment, such as by using a citation. Then list the full details of the source in a ‘references’ section at the end of your assessment. All sources used for your assessment should be detailed in the ‘references’ section. It is advisable to never copy another person’s work. D. Adjustment and Support i. Reasonable adjustment ACBI supports individual differences in the learning environment and provides ‘reasonable adjustment’ in training and assessment activities to support every learner. If you have any special needs that make it difficult for you to complete your learning or assessments, you should discuss this with your assessor. ACBI will endeavour to provide you with reasonable alternatives to assist you to complete the required tasks such as completing tests verbally or using an interpreter. NOTE: If you have any special needs, you should discuss this with your assessor before starting your assessment. ii. Support While ACBI may not be able to assist you with language training or specific Language, Literacy and Numeracy (LLN) training, our assessors will work with you to ensure that you are supported throughout your qualification. If you require individual tutoring this may attract an additional fee (please refer to the ACBI Student Handbook available from https://www.acbi.edu.au). Support may be offered by your assessor, or for more specialist support you may need to contact the RTO administration. E. Assessment submission Always submit assessments on time by the due date. You can find the due date in the unit course page on Moodle.
i. Assessment Coversheet Once you have completed all the tasks of the assessment, you must complete the Assessment Cover Sheet, including signing the declaration. ii. File naming conventions When submitting assessments electronically follow the following standard for naming document files and subject line. You must insert the following information: Unit of Competency code (ie. BSBPMG514) ‘A’ for word assessment then followed by the assessment number and a dash Your first name and initial of last name. Capitalise only the first letter of names. Then insert a hashtag, followed by submission attempt. Hence as an example of incorporating the four points above your file name or subject line should appear this way:BSBPMG514A1 – JessieA #1 iii. Submission via Moodle Please refer to the “Instructions for Submitting Your Assessment” on the unit course page in Moodle. NOTE: Please take care to follow all instructions listed. Assessments uploaded with a draft status on Moodle may not be graded. F. Assessment results and feedback i. Assessment results Once you have submitted this assessment online via Moodle, your assessor will grade it and provide you with feedback. For each task of the assessment, you will receive a grade of ‘Satisfactory’ or ‘Not Satisfactory’. You will also receive a grade for the entire assessment of ‘Competent’ or ‘Not Competent’. Each task of the assessment must be ‘Satisfactory’ in order to receive a grade of ‘Competent’. ii. Resubmission If your assessment is graded ‘Not Competent’, you receive instructions via the feedback form on components to be amended. Your assessor is committed to providing you with detailed feedback on the outcomes of the assessment and will provide guidance on areas for improvement. In most instances, you should need only complete the sections of the assessment that were deemed ‘Not Satisfactory’. However, it is important to remember that depending on the task, it may be necessary to repeat the whole task (for example presentations or the delivery of a training session).
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
If resubmission is required, you will need to amend or update your assessment as a different version by the required term cut-off date, as detailed on Moodle. NOTE: For further information on late assessment, please refer to the ‘Assessment Policy’ available on Moodle. iii. What happens if you do not agree with the assessment result If you do not think the assessment process is valid, or disagree with the decision once it is made, or believe that you have been treated unfairly, you can appeal. The first step is to discuss the matter with your trainer. If you still do not agree with the assessment, you are able to request a re-assessment. It is possible to have your evidence assessed by a different trainer. If you remain dissatisfied after the re-assessment, you should contact the Director of Studies. Full details of the Appeals process are contained in your Student Handbook. G. Technical tools for completing this assessment To complete this assessment, you need access to: A computer with internet Word processing and other relevant programs to develop appropriate documentation and reports as required
2.AssessmentCoversheet Unit of Competency:BSMPMG514 Manage project cost Assessment Tasks: ☐Task 1. Questioning ☐Task 2. Project ☐Task 3. Written Questions Due Date:Date Submitted: Declaration:I have read and understood the following information at the beginning of this assessment guide (please tick): ☐Assessment information ☐Submitting assessments ☐Plagiarism and referencing I declare this assessment is my own work and where the work is of others, I have fully referenced that material. Name (please print): Student signature: Date: 3. Assessment Requirements
A.Task 1 – Questioning i. Instructions for students Task 1 of this assessment requires you to analyse different models and tools utilised in managing a project’s cost and gain an understanding of the various components needed in developing and implementing a project. Answer the questions below using the space provided: Answer all parts of each question Use your own words and give examples wherever possible The quality of your answer is more important than how long it is Enter your answers in this document You may use various sources of information to inform your answers, including your resources provided by ACBI, books, and online sources. You must acknowledge and cite your sources. ii. Task 1 Questions 1A.Describe two (2) methods and two (2) tools that can be used for costing a project and conducting a cost analysis. Answer in 40 to 80 words. There are different types of methods and tools for costing and project such as: Expert judgement method- Under it, experts provide past years’ financial information to project managers which is used for further cost analysis (Matsuo and Schmidt, 2019). Parametric estimating method- This method is used for estimating overall cost of project. In this, statistical connection between historical data and variables is used to predict the cost. Tools: Bottom up estimation- In this tool cost is estimated from lower level in accordance of task break under work break down structure. Three-pointestimation-Thistoolofcost analysisisbasedon PERT(Program evaluation and review technique). It focuses on three points that are most likely,
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
optimistic and pessimistic. 1B. Answer the following: a)Describe two (2) different strategies that can be used to manage project costs. b)Outline the most appropriate strategy for responding to budgetary problems before they arise and after they arise. Answer in 80 to 160 words. (a) Budgeting- In this future time period’s cost is estimated by help of previous years’ financial information. Cost tracking- It is also an important strategy which is used in order to track cost of different kinds of activities and operations separately. (b) Most appropriate strategy. Fromabovementionedtwostrategies,costtrackingseemaneffectivewayto overcome budgetary issues which they arise. It becomes possible because under this technique cost of each variable is tracked and compared to actual cost. Due to this, it
becomes easier for project managers to manage their overall financial issues. 1C. Answer the following: a)Explain why costs should be reviewed against the project outcomes b)Outline one process that could be used to review costs against outcomes Answer in 80 to 160 words. (a) This is essential for project managers to review cost with outcome of project. It is so because by help of this comparison, this becomes easier for managers to assess efficiency of project. As well as success of project is also determined by help of review of actual cost with actual cost of operation at the end of project (Rowe, 2020). (b) One of the effective process in order to review cost against outcomes is variance analysis. It is so because under this actual cost of overall project is compared to estimated cost after finishing the project.
1D. Answer the following: a)Outline why it is important for each member of the organisation to adhere to organisational policies and procedures b)Describe the purpose of policies and procedures as they relate to project management roles Answer in 80 to 160 words. (a) The organizational policies and procedures are too crucial for each member of a company. It is so because in accordance of policies and strategies employees develop themselves. As well as a project’s goals are determined as per the organizational structure. (b) The main purpose of policies and procedure of an organization is that these are interrelated to goal of a project (Pellerin and Perrier, 2019). It is so because in a project, different types of roles and responsibilities are assigned to members in accordance of organizational structure that can be matrix, functional etc.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
B. Task 2 – Questioning i. Instructions for students Read the scenarios of OzMarket Consulting provided below, then answer the following questions. Answer the questions below using the space provided: Answer all parts of each question Use your own words and give examples wherever possible The quality of your answer is more important than how long it is Enter your answers in this document You may use various sources of information to inform your answers, including your resources provided by ACBI, books, and online sources. You must acknowledge and cite your sources. ii. Task 2 Scenario Scenario: OzMarket Consulting has been employed to project manage the design and development of a garden for the local park. You have been engaged as the Project Accounts Manager to oversee all project costs. Total costs MUST not exceed$10,000.00. The park is to be constructed on undeveloped land next to a river. Tests were conducted and results report the soil quality is quite poor and is predominantly clay. The area to be developed is ten (10) metres by ten (10) metres. Undertake the following tasks to complete this assessment activity. Use the following figures when appropriate. PositionHourly Rate Project Manager$60.00 Project Account Manager$50.00 Project Department Heads$50.00 Labourer$25.00 Plant operators$30.00 (wet hire)
Landscape designer$100.00 PlantsPrice per variety Flowers$1.00 Shrubs$2.00 Trees$10.00 MaterialPrice per tonne Soil$30.00 Stone$20.00 Sand$20.00 MiscellaneousPrice per linear metre Turf$5.00 Drainage (AG Pipe)$2.00 Fencing$10.00 Watering Equipment$3.00 If you determine other material is required you are to provide a list of the items and their relative costs (if used). iii. Task 2 Questions 2A. NOTE: This is a multipart question. Ensure you complete each part of the question. i.Determine what resources may be required for the landscaping project and estimate the
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
costs of the resources. ii.Create aWork Breakdown Structure (WBS)for the landscaping task. iii.Once you have created the WBS, consult with others involved in the project, as role played by other students in your student. Use the consultation to determine if you have missed any tasks. This consultation can be done verbally or in a written format. After your consultation, record notes of what was discussed. iv.Identify any tolerances necessary. v.Estimate the costs of the project based on the resources identified in the WBS. State all figures used and show all working. Answer below using the tables provided. Answer in 100-250 words. i. Determine what resources may be required for the landscaping project and estimate the costs of the resources For landscape project of developing garden for local park different types of resources will be needed that are as follows: Type of resourcesEstimated cost (In $) Labour charges7000 Plants500 Basic material500 Other1500 Total9500
ii. Work Breakdown Structure (WBS) for the landscaping task This is defined as a form of structure which breaks overall tasks of a project in sub activities which makes work easier. ActivityStart dateEnd date Foundation: Measurement of area1/03/20202/03/2020 Cleaning of area3/03/202005/03/2020 Preparing area for gardening06/03/202008/03/2020 Construction: Boundary construction (Fencing)09/03/202015/03/2020 Footpath construction16/03/202020/03/2020 Entrance and exit gate construction21/03/202026/03/2020 Preparing proper water drainage system27/03/202031/03/2020 Gardening: Growing of plans and flowers01/04/202003/04/2020 Growing grass on the area04/04/202005/04/2020 Designing: Water foundation preparation06/04/202010/04/2020 Exercise equipment installation11/04/202012/04/2020
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
iii. Notes from consultation with others In accordance of prepared WBS, a discussion has been date whose outcome is as follows: Managing quality of project is essential. Designing of landscape garden must be attractive. iv. Identified necessary tolerances For above landscape project, the key tolerances are as follows:
All activities need to be performed under given time period. Cost of project must under estimated cost of project. v. Estimated costs of the project based on the resources identified in the WBS. NOTE: Ensure you state all figures used and show all working. ParticularsUnit cost ($)Amount ($) Raw material cost:1090 Flowers1100 Shrubs240 Trees10100 Soil3090 Stone2060 Sand2080 Gate150300 Pipes100200 Water foundation120120 Salary and wages of professionals:8410 Project manager2880 Account manager2300 Designer750 Plant operator300 Labour cost of measuring and cleaning the surface for garden 1500
Contractor charges680 Total cost9500 2B. Using the figures, WBS and cost estimates you developed during the previous question (Task 2, Question 2B), create a cost management plan which includes a project budget. Ensure the cost management plan clarifies any details which may impact the ongoing management of project finances. Your plan must be presented in an industry appropriate format. Use the template called “BSBPMG514 Cost management plan template” provided on Moodle to create your plan. Save your plan as “BSBPMG514 Cost management plan – Your Name”, replacing “Your Name” with your first and last names. Ensure you submit your plan as part of your assessment. Cost management plan for 12 months- Covered in excel sheet. Introduction-The main objective of cost plan is to getting an idea about how much fund will
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
be needed in order to complete different kinds of activities and operations of above project. Cost management approach-Each cost management plan is prepared in accordance of various kinds of approaches. It depends on companies’ that which approach they are going to use. In the aspect of above mentioned cost management approach, variances are computed in order to gather information about activities which are underperforming. Measuring project cost-In the context of above project’s cost, it can be estimated that there will an expense of $10648while the actual cost is of $9500. As well as variance is of $1148 that is a favourable variance. Reporting format- The format which is used in above cost management plan is for 12 months in which each month’s estimated cost is mentioned. Cost variance response process- In relation to above cost management plan, overall total cost variance is favourable. Though, there is an activity whose variance is negative and that is of purchasing of tree. In this context company needs that they should purchase tress from a supplier whose rates are lower and it can be done by comparative analysis of rates of different suppliers. Cost change control process- The variance of total cost of project is favourable. Thus, company does not need to make any changes in their cost management plan. Project budget- The total estimated material cost for project is of $1118 while actual cost is of $1090 that is a positive aspect. Charges of contractor are of $900 but in actual contractor was paid only $680. 2C. NOTE: This question has multiple parts. Make sure you complete each part. i.Create a financial management plan which will allow you to monitor actual against the budgeted expenditure. Use the template called “BSBPMG514 Budget Analyser Template” provided on Moodle to create your plan. Save your plan as “BSBPMG514 Financial management plan – Your Name”, replacing “Your Name” with your first and last names. Ensure you submit your plan as part of your assessment. ii.Create an implementation plan for monitoring of expenditure. Ensure you include how these plans will be communicated with the stakeholders. Save your plan as “BSBPMG514 Implementation plan – Your Name”, replacing “Your Name”
with your first and last names. Ensure you submit your plan as part of your assessment. iii.The project has been running for three (3) weeks and during a recent monitoring activity you realised that there is a discrepancy between the estimated costs and the actual costs due to an increase in the number of hours it is taking to complete each task. In the table below, create an outline of three or more options for controlling the costs. (i)Financial management plan: ParticularsBudgeted cost ($)Actual cost ($) Raw material cost: Flowers120100 Shrubs6040 Trees38100 Soil10090 Stone8060 Sand9080 Gate300300 Pipes210200 Water foundation120120 Salaryandwagesof professionals: Project manager30002880 Account manager25002300 Designer1000750 Plant operator330300 Labourcostofmeasuring and cleaning the surface for garden 18001500 Contractor charges900680 (ii)Implementation plan for monitoring of expenditure.
In order to control different kinds of expenses, companies should apply an effective monitoring plan. The variance analysis can be useful in order to monitor the expenses. Underthistechniqueactualnumberof expensesarecomparedto estimated expenses. By help of this variances are computed which can be adverse and favorable (Nachbagauer and Schirl-Boeck, 2019). iii. Option for controlling costs The cost can be controlled by eliminating those activities which are higher expensive and their output is negative. As well as raw material needs to be purchased from those suppliers who offer materials at lower cost. 2D. THE SCENARIO:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
The Project Manager has read your report on controlling the costs and would like further information on budgeting processes. You are to explain budgeting processes, tools and techniques and explain how these could be used to achieve financial objectives of the project and how they could be used to monitor actions taken to control costs on a project that is currently running over budget. Decisions will need to be made on how to control the costs. Set up a meeting with: You, role playing being the Project Accounts Manager Your Trainer & Assessor, role playing being the Project Manager NOTE: This meeting will be observed by your Trainer & Assessor. During this meeting, your Trainer & Assessor will complete the observation checklist found in the “BSBPMG514 Marking Guide”. WHAT YOU NEED TO DO BEFORE YOUR MEETING: Prepare for your meeting by determining the most appropriate tools, techniques and processes for budgeting on a small project such as this landscaping project. WHAT YOU NEED TO DO DURING YOUR MEETING: You are to explain budgeting processes, tools and techniques. This includes how these could be used to achieve financial objectives of the project and how they could be used to monitor actions taken to control costs on a project that is currently running over budget. Decisions will need to be made on how to control the costs. WHAT YOU NEED TO DO AFTER YOUR MEETING: Record note of what was discussed during your meeting, including any feedback received. Answer in 40-80 words.
Meeting notes Meeting- The meeting was organized about making discussion on budgeting tools and techniques so that cost can be controlled. Notes after meeting: The overall conclusion of meeting was to assure that there should be implementation of effective budgeting approach which can be flexible or fixed budgeting method. The reason for applying these methods is that by help of it project managers can focus on each individual activity in an effective manner. 2E. Read the scenario below, then answer the following question. Scenario: You recently met with the Project Manager. This resulted in the decision to halve the number of shrubs being planted, to cut back by 50% the number of watering points and reduce the hours of the staff by 25%. Undertake a cost-analysis to identify if these variations will help bring the budget back into alignment. Then consider the cost analysis you undertook andanswer the points below: Explain why you used the method and tools you selected Outline if the cost analysis identifies any alternative viable actions Describe why should costs be monitored across the project lifecycle Answer in 80 to 160 words.
Reason for applying above mentioned method was to reduce overall cost of different kinds of activities and operations. By doing so cost will be lower than estimation. The cost should be monitored during entire lifecycle of project because it is a key aspect. Any ignorance in this may lead to failure of project. Therefore, each activity’s cost need to be identified during five phases of project life cycle. 2F. Using the data from Task 2, create a monthly financial report for the project. Ensure all variations are incorporated. Answer in 80 to 160 words. Analysis of variances: Pro ject Bu dge t - Bu dge t An alys esJanuaryFebruaryMarchAprilMayJune Det ails of WB B u d g A c t u V a r i W e e k W e e k W e e k W e e k W e e k W e e k W e e k W e e k W e e k W e e k W e e k W e e k W e e k W e e k W e e k W e e k W e e k W e e k W e e k W e e k W e e k W e e k W e e k W e e k
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
S et e d A m o u nt a l A m o u n t a n c e123412 3 41234123412341234 Stu den ts to ent er det ails of the WB S whi ch sho uld sho w the cor res pon din g allo cat ed am ou nt in the bud get ed col um S t u d e n ts to e n te r t h e a m o u n t a s p e r t h e 1 st c ol u m n o A c t u a l a m o u n t is a u t o m a ti c a ll y c a l c u l a t e d a s t V a r i a n c e a u t o m a ti c a ll y c a l c u l a t e d w h i c h i s t
nf W B S h e a m o u n t is e x p e n s e d o f d u ri n g t h e p r o j e c t h e d i f f e r e n c e b e t w e e n t h e a c t u a l a n d b u d g e t e d a m o u n t
Ra w mat eria l cost : Flo wer s 1 2 0 1 0 0 2 0 2 0 2 5 2 5 1 0 1 0 1 0 Shr ubs 6 0 4 0 2 0 1 0523 1 0 1 0 Tre es3 8 1 0 0 - 6 2828578 Soil 1 0 0 9 0 1 0552855 1 0 1 0 1 0 1 0 1 0 1 0 Sto ne 8 0 6 0 2 0285555 1 055 1 0 San d 9 0 8 0 1 0 1 0 1 05 1 05 1 0 2 055 Gat e 3 0 0 3 0 00 1 5 0 1 0 0 5 0 Pip es 2 1 0 2 0 0 1 00000000000 1 5 0 5 0 Wat er fou nda tion 1 2 0 1 2 00 1 0 0 2 0 Sal ary and wa ges of pro fess ion als:0 Proj ect 3 0 2 8 1 2 0004 8 0004 8 0004 8 0004 8 0004 8 0004 8
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
ma nag er 0 0 8 00000000 Acc oun t ma nag er 2 5 0 0 2 3 0 0 2 0 0000 3 8 4 3 8 4 3 8 4 3 8 4 3 8 4 3 8 4 Des ign er 1 0 0 0 7 5 0 2 5 0000 1 2 5 1 2 5 1 2 5 1 2 5 1 2 5 1 2 5 Pla nt ope rato r 3 3 0 3 0 0 3 0 5 0 5 0 5 0 5 0 5 0 5 0 Lab or cost of mea suri ng and clea nin g the surf ace for gar den 1 8 0 0 1 5 0 0 3 0 0 2 5 0 2 5 0 2 5 0 2 5 0 2 5 0 2 5 0 Con trac tor cha rges 9 0 0 6 8 0 2 2 0 1 1 3 1 1 3 1 1 3 1 1 3 1 1 3 1 1 3
C. Task 3 – Written Questions i. Instructions for students Read the scenarios of OzMarket Consulting provided below, then answer the following questions. Answer the questions below using the space provided: Answer all parts of each question Use your own words and give examples wherever possible The quality of your answer is more important than how long it is Enter your answers in this document You may use various sources of information to inform your answers, including your resources provided by ACBI, books, and online sources. You must acknowledge and cite your sources. ii. Task 3 Scenario Scenario: The landscaping project has been successfully completed. The client is satisfied. The Project Manager is happy. Everyone is starting to consider the next project. Before you can start your next project, you need to finalise the landscaping project. iii. Task 3 Questions
3A. Create a checklist of all the activities done to signify financial completion of the project. Answer in 40 to 80 words. There are less number of activities which are significantly completed. This is so because majority of activities’ cost is higher than expected cost. There is some cost of material whose cost is lower than estimation such as purchasing of shrubs, trees etc. 3B. Using the Financial Management Plan you created as part of Task 2, Question 2C, completea final costing of the project for forwarding to OzMarket Consulting. Ensure the actual cost for the project has been captured this updated plan. Save your plan as “BSBPMG514 Final Costing – Your Name”, replacing “Your Name” with your first and last names. Ensure you submit your plan as part of your assessment. 3 B Actual cost of landscape project: ParticularsActual cost (In $) Raw material cost: Flowers100 Shrubs40 Trees100 Soil90
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Stone60 Sand80 Gate300 Pipes200 Water foundation120 Salaryandwagesof professionals: Project manager2880 Account manager2300 Designer750 Plant operator300 Labor cost of measuring and cleaningthesurfacefor garden 1500 Contractor charges680 3C.Develop a project outcome review which answers the following questions: a)Was the project cost effective? b)Did the processes used to manage the costs on the project prove to be efficient? c)How could you improve the processes used to ensure a better outcome on the next project? d)What are two or more improvements you can recommend? Document your project outcome review below.
Answer in 80 to 160 words. (a)No, project was not cost effective because majority of activities were producing negative variance. Only some activities’ cost was lower than estimation. (b)The processes used for cost management did not help in successful management of cost. This is so because cost of various operations was not under budgeted cost. (c)For next project,theprojectmanagershould use some othercost management strategies which can be helpful. They can use activity based costing approach which may control overall cost of different operations. (d)Two recommendations: Hiring employees on contract base so that cost of labor can be controlled. Purchasing of materials from lower costly supplier. REFERENCES Books and journal: Matsuo, T. and Schmidt, T.S., 2019. Managing tradeoffs in green industrial policies: The role of renewable energy policy design.World Development,122, pp.11-26. Rowe, S.F., 2020.Project management for small projects. Berrett-Koehler Publishers. Pellerin, R. and Perrier, N., 2019. A review of methods, techniques and tools for project planning and control.International Journal of Production Research,57(7), pp.2160-2178. Nachbagauer, A.G. and Schirl-Boeck, I., 2019. Managing the unexpected in megaprojects: riding the waves of resilience.International Journal of Managing Projects in Business.