Elderly Village Construction Project 1Elderly Village Construction ProjectConducted by:SARAHANA CONSTRUCTION COMPANYSRM750ASSIGNMENT 2TRIMESTER 1, 2018Student NameChekuri, Eswar VarmaGodavarthi, AdithyaKondreddy, Satya Sai LohithKundanamadugu, Sai ChandrasekharCourse Name and Code: Built Environment Professional Practice (SRM750)Date:
Built Environment Professional Practice (SRM750)_1

Elderly Village Construction Project 2Client: Antony Clifford 203 Munibung Rd, Cardiff NSW 2033, VICTORIADear Sir, PROGRESS REPORTPROPOSED ELDERLY VILLAGE CONSTRUCTION PROJECT OF PHASE 6 & 7NEAR ADAM STREETThis report is to give a progressive analysis on the various activities which the Sarahana Construction Company would proposed for stage, (6 & 7) in line with the proposed Elderly village constructions project. In essence, this report is submitted with reference to all previous sections which have been submitted on sections such as (1,2,3,4 &5) respectively. All the analysis in this reported are presented with respect to the documentation approval acts and the overall Architect instructions at this phase. Moreover, this report aims at establishing all the necessary approaches and consultations which need to be considered and reworked on in order toenable the commencement of proposed Elderly village construction project. Thus, this report willcover the following sections with reference to the overall documentation;Detailed cross-examination of the existing and current site conditionAll the parameters associated with the current as well as the proposed building All the required project legislation Tender documentationKindly note that the Sarahana Construction Company has worked and established all the documentations which are required to take this project from this level to the next stage. Any required as well as relevant information and documentations have been for perusal. Therefore, we are humbled to present this document and we are quite sure that it will give you an overview and in-depth understanding on how to start the proposed construction project. Kindly, do not hesitate to contact as on any inquiry and query.Yours Faithfully Sarahana Construction Company
Built Environment Professional Practice (SRM750)_2

Elderly Village Construction Project 3ContentsExecutive Summary.........................................................................................................................4Company Summary.........................................................................................................................5Company History.........................................................................................................................5Mission Statement.......................................................................................................................5Company Objectives and Goals...................................................................................................5Company Services.......................................................................................................................5Principal Activities......................................................................................................................6Directors......................................................................................................................................6Organization Structure.................................................................................................................6Project Brief.....................................................................................................................................8Site Details...................................................................................................................................8Site Location................................................................................................................................8Site Neighborhood.......................................................................................................................9Site Zoning...................................................................................................................................9Site Overlays................................................................................................................................9Procurement Strategies..................................................................................................................10Approvals, Licenses and Permits Requirements before Construction.......................................10Building Approval Certificate...............................................................................................10Licensed Building Surveyor......................................................................................................11Licensed Builder....................................................................................................................11Fee Payment...........................................................................................................................11Plumbing Approval................................................................................................................12Documentation for Supporting Drawings..................................................................................12Building Surveyor Roles in the Project.....................................................................................12
Built Environment Professional Practice (SRM750)_3

Elderly Village Construction Project 4Builder.......................................................................................................................................13Procurement Methods................................................................................................................13Traditional Method................................................................................................................13Non-Traditional Procurement Method..................................................................................14Appropriate Procurement Method.........................................................................................15Recommendation Reason......................................................................................................15Development Approval..................................................................................................................16Design Response........................................................................................................................17Accommodating Space and Unit...........................................................................................17Surrounding Outlook.............................................................................................................18Safety Considerations............................................................................................................18Common Objectives and Property.........................................................................................19Facilities and Onsite Amenities.............................................................................................19Environmental Criteria and Heritage Considerations................................................................19Heritage Criteria....................................................................................................................20State-based Strategic Plans........................................................................................................21Graphical Analysis.................................................................................................................21Site Coverage.........................................................................................................................22Construction Procurement.............................................................................................................23Construction Procurement Recommendation Form..................................................................23Lump Sum.................................................................................................................................24Construction Managers..........................................................................................................25Project Manager.....................................................................................................................25Architect................................................................................................................................26Contractor..............................................................................................................................26
Built Environment Professional Practice (SRM750)_4

Elderly Village Construction Project 5Client......................................................................................................................................26Building Surveyor..................................................................................................................27Risks to the Members................................................................................................................27Architect................................................................................................................................27Contractor..............................................................................................................................27Construction Manager...........................................................................................................28Client......................................................................................................................................28Project Manager.....................................................................................................................28Building Surveyor..................................................................................................................28References......................................................................................................................................29Appendices....................................................................................................................................33
Built Environment Professional Practice (SRM750)_5

Elderly Village Construction Project 6Executive SummaryThis report mainly outlines and appraises all the developmental stages which are required in the implementation of Elderly Village construction project proposal. The project is to be carried out near Adam Street, Victoria by Sarahana Construction Company. All the considerations which should taken into account; Appraising all the documentation steps taken when developing the approval Selecting a appropriate and viable procurement method to be used in the construction proposal Furthermore, the project construction stages such as the initiation, construction and completion phases can also be in evaluating the entire process from the documentation level to the overall detailed and design analysis. Moreover, this study also focuses on establishing all the legal considerations and implications as well as their applications which need to be considered and apply in this project. Subsequently, the stakeholders’ services and considerations in the pre-construction stage is also procured and evaluated in this report. The report mainly prepared with references to all the code and principles which regulates the construction processes in Victorian State alongside the building regulations.
Built Environment Professional Practice (SRM750)_6

Elderly Village Construction Project 7Company SummaryCompany HistoryThe Sarahana Construction Company developed in 2010, and this was under the partnership between the way blotch Construction Company and Shrine architects. There are specific factors which led to the formation of the company. For instance, the desire to raise the profit margin by providing construction and design services in a variety of packages being the primary activity and heritage. For many years the company has offered commercial infrastructure and residential services in many geographical regions such as Australia. The services that were provided by the company included the design and construction services, building and construction services and project management services and they achieved the provision of the above services using technical expertise and advanced skills. However, the firm currently deals with the design and constructs the system, and it also shares the different workloads among the partners. Mission StatementThe mission of the company is to offer different customers with high-value construction services through building a strong partnership in the course of the delivery process. It is the duty of the firm to services to the clients, and this will involve ensuring that the quality of work done and services delivery extends beyond their expectations daily.Company Objectives and GoalsThe primary objective of the company is to make a massive contribution to every aspect of infrastructure delivery and project in the modern construction. The other objectives include;To Supervise and monitor totally the whole construction processTo treat all the project feature using the same range of commitmentTo channel and allocate the company’s services effectivelyTo diversify the company’s expertiseCompany ServicesThe company offers services in design and construction, and this is in the form of;Construction
Built Environment Professional Practice (SRM750)_7

Elderly Village Construction Project 8Permits and zoning applicationsFeasibility studiesFinance and managementPreliminary design studiesPrincipal ActivitiesThe principal activity is a general construction that is design and construction, and it includes refurbishment and renovation works as shown in the table below. Licensed BuildersLicensing CodeGBSDescriptionGeneral Construction and FormworksDirectorsChekuri, Eswar VarmaGodavarthi, AdithyaKondreddy, Satya Sai LohithKundanamadugu, Sai ChandrasekharThe total number of staff as at January 2018 was about 100Organization StructureThe company has four departments and is headed by four principal partners with diverse professionalism and expertise since it is a partnership business. Every department has a team of employees who help in running the operations through finance, management, construction and design documentation. The various directors and their roles mainly summarized as shown in the below