Running head: BUSINESS MODELLING TOOLS Business Modelling Tools (7BSP1174): Group Coursework A Case Study ofAirport Terminal Construction Project Student Name: University Name:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1BUSINESS MODELLING TOOLS Executive Summary This report is based on Airport Terminal Construction Project for UK airport by Hertfordshire Investment Corporation (HIC). The project planning officer has determined that the project will be carried out into four phases that is 1) Surface preparation and foundation phase, 2) Structure construction phase, 3) Interior building phase and 4) Certification phase. From the provided information on the activities that will be conducted in the different phases, a schedule has been prepared with the help of MS Project application. It is identified that the project will complete on Friday, 06 March 2020 assuming it starts on Monday, 07 January 2019 for which the schedule is attached in Appendix 1. In this report, a schedule has been prepared for high level structural construction part of the project to determine the possible timescale. The aim of this report is to provide a timeline for executing the project which has been developed using Ms Project application. The activities determined by the PPO (Project Planning Officer) has been presented in a sequential manner in Ms Project. From the developed schedule, it has been identified that high level structural construction part of the project could be completed on Friday, 06 March 2020 and the critical activities within the project could not be delayed. After implementation of the changes in the project schedule as per provided information, it is estimated that the project will be completed onTuesday, 17 March 2020. It is recommended that the changes should be managed efficiently to complete the project. The company should monitor progress of the project on a regular basis so that the project remains on track and could be completed within estimated time and budget.The major risks that has been identified in context to this construction project are inadequate budget, unavailability of resource and delay in project progress. The company should be prepared for the risks through
2BUSINESS MODELLING TOOLS proper risk planning and management procedures that could be followed in case there is emergence of risks. Table of Contents Project Formulation.........................................................................................................................3 Response to the questions............................................................................................................6 Question 1................................................................................................................................6 Question 2................................................................................................................................6 Question 3................................................................................................................................8 Discussion........................................................................................................................................8 Conclusion.......................................................................................................................................9 Bibliography..................................................................................................................................11 Appendices....................................................................................................................................12 1. Schedule for the project.........................................................................................................12 2. Changes in the project...........................................................................................................12
3BUSINESS MODELLING TOOLS Project Formulation Phase A: Surface preparation and foundation phase Activity CodeActivity NameDurationPrecedence A1Meeting to evaluate the surfacing and foundation work volume3 days A2Meeting to determine transportation requirements1 dayA1 A3Fencing of the construction site3 daysA2 A4Building of the project management temporary offices4 daysA2 A5Building of temporary road to construction site3 daysA4 A6Clearing of the site7 daysA5 A7Digging of the foundations on Site A15 daysA6 A8Digging of the foundations on Site B18 daysA6 A9Digging of the foundations on Site C25 daysA6 A10Evaluation meeting2 daysA9 A11Preparation of foundation steel structure8 daysA10 A12Laying the steel structure on the foundation14 daysA11 A13Technical requirements of the concrete2 daysA10 A14Preparation of the concrete5 daysA13 A15Pouring of the concrete6 daysA12,A14 A16Drying up of the concrete5 daysA15 A17Engineering verification of the foundations3 daysA16 A18Meeting to evaluate the phase work and preparation of the reports2 daysA17 Phase B: Structure construction phase Activity CodeActivity NameDurationPrecedence B1Construction of a Concrete Platform at Site A16 days- B2Construction of a Concrete Platform at Site B20 days- B3Construction of a Concrete Platform at Site C28 days- B4Erection of Concrete Column at Site A24 daysB1 B5Erection of Concrete Column at Site B20 daysB2 B6Erection of Concrete Column at Site C22 daysB3 B7Technical Evaluation4 daysB4,B5,B6
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4BUSINESS MODELLING TOOLS B8Construction of Ceiling on Site A12 daysB7 B9Construction of Ceiling on Site B10 daysB7 B10Construction of Ceiling on Site C15 daysB7 B11Completion of Terminal Ground Floor0 daysB8,B9,B10 B12First Floor: Erection of Concrete Column at Site A12 daysB11 B13First Floor: Erection of Concrete Column at Site B15 daysB11 B14First Floor: Erection of Concrete Column at Site C16 daysB11 B15First Floor: Construction of Ceiling at Site A14 daysB12 B16First Floor: Construction of Ceiling at Site B18 daysB13 B17First Floor: Construction of Ceiling at Site C16 daysB14 B18Construction of Bridge Linking Site A to B10 daysB15,B16 B19Construction of Bridge Linking Site A to C14 daysB15,B17 B20Construction of Bridge Linking Site B to C14 daysB16,B17 B21Phase evaluation and report writing meeting2 daysB18,B19,B20 Phase C: Interior building phase Activity CodeActivity NameDurationPrecedence C1Meeting with the sub-contractors2 daysB21 C2Ground Floor: Wall separation work on Site A18 daysC1 C3Ground Floor: Wall separation work on Site B15 daysC1 C4Ground Floor: Wall separation work on Site C12 daysC1 C5First Floor: Wall separation work on Site A16 daysC2 C6First Floor: Wall separation work on Site B14 daysC3 C7First Floor: Wall separation work on Site C15 daysC4 C8Ground Floor: Setup of electricity and computer networks on Site A20 daysC2 C9Ground Floor: Setup of electricity and computer networks on Site B20 daysC3 C10Ground Floor: Setup of electricity and computer networks on Site C20 daysC4 C11First Floor: Setup of electricity and computer networks on Site A24 daysC5 C12First Floor: Setup of electricity and computer networks on Site B24 daysC6 C13First Floor: Setup of electricity and computer networks on Site C24 daysC7
5BUSINESS MODELLING TOOLS C14Ground Floor: Laying of plumbing and heating network on Site A24 daysC2 C15Ground Floor: Laying of plumbing and heating network on Site B24 daysC3 C16Ground Floor: Laying of plumbing and heating network on Site C24 daysC4 C17First Floor: Laying of plumbing and heating network on Site A30 daysC5 C18First Floor: Laying of plumbing and heating network on Site B30 daysC6 C19First Floor: Laying of plumbing and heating network on Site C30 daysC7 C20Phase evaluation and report writing meeting4 daysC19 Phase D: Certification phase Activity CodeActivity NameDuration D1Meeting with the sub-contractors2 daysC20 D2Meeting with the construction certification body2 daysD1 D3Ground Floor: Certification of the structure on Site A6 daysD2 D4First Floor: Certification of the structure on Site A6 daysD3 D5Ground Floor: Certification of the structure on Site B5 daysD2 D6First Floor: Certification of the structure on Site B5 daysD5 D7Ground Floor: Certification of the structure on Site C7 daysD2 D8First Floor: Certification of the structure on Site C7 daysD7 D9Ground Floor: Certification of the electricity and computer networks on Site A7 daysD3 D10First Floor: Certification of the electricity and computer networks on Site A7 daysD4 D11Ground Floor: Certification of the electricity and computer networks on Site B8 daysD5 D12First Floor: Certification of the electricity and computer networks on Site B8 daysD6 D13Ground Floor: Certification of the electricity and computer networks on Site C10 daysD7
6BUSINESS MODELLING TOOLS D14First Floor: Certification of the electricity and computer networks on Site C10 daysD8 D15Ground Floor: Certification of the plumbing and heating networks on Site A9 daysD9 D16First Floor: Certification of the plumbing and heating networks on Site A9 daysD10 D17Ground Floor: Certification of the plumbing and heating networks on Site B12 daysD11 D18First Floor: Certification of the plumbing and heating networks on Site B12 daysD12 D19Ground Floor: Certification of the plumbing and heating networks on Site C10 daysD13 D20First Floor: Certification of the plumbing and heating networks on Site C10 daysD14 D21Formal certification meeting3 daysD20 Response to the questions Question 1 The completion date for every phase should be presented in a table as follows: Phase LabelPhase NameCompletion Date Asurface preparation and foundation phaseWed 01-05-19 Bstructure construction phaseMon 14-10-19 Cinterior building phaseTue 14-01-20 Dcertification phaseFri 06-03-20 Question 2 Phase A: Surface preparation and foundation phase Activity CodeActivity Name A1Meeting to evaluate the surfacing and foundation work volume A2Meeting to determine transportation requirements A4Building of the project management temporary offices A5Building of temporary road to construction site A6Clearing of the site A9Digging of the foundations on Site C A10Evaluation meeting
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7BUSINESS MODELLING TOOLS A11Preparation of foundation steel structure A12Laying the steel structure on the foundation A15Pouring of the concrete A16Drying up of the concrete A17Engineering verification of the foundations A18Meeting to evaluate the phase work and preparation of the reports Phase B: Structure construction phase Activity CodeActivity Name B3Construction of a Concrete Platform at Site C B6Erection of Concrete Column at Site C B7Technical Evaluation B10Construction of Ceiling on Site C B11Completion of Terminal Ground Floor B13First Floor: Erection of Concrete Column at Site B B16First Floor: Construction of Ceiling at Site B B20Construction of Bridge Linking Site B to C B21Phase evaluation and report writing meeting Phase C: Interior building phase Activity CodeActivity Name C1Meeting with the sub-contractors C4Ground Floor: Wall separation work on Site C C7First Floor: Wall separation work on Site C C19First Floor: Laying of plumbing and heating network on Site C C20Phase evaluation and report writing meeting Phase D: Certification phase Activity CodeActivity Name D1Meeting with the sub-contractors D2Meeting with the construction certification body D7Ground Floor: Certification of the structure on Site C D8First Floor: Certification of the structure on Site C D14First Floor: Certification of the electricity and computer networks on Site C
8BUSINESS MODELLING TOOLS D20First Floor: Certification of the plumbing and heating networks on Site C D21Formal certification meeting Question 3 Phase LabelPhase NameCompletion Date Asurface preparation and foundation phaseWed 01-05-19 Bstructure construction phaseThu 17-10-19 Cinterior building phaseThu 23-01-20 Dcertification phaseTue 17-03-20 Discussion The project schedule has been prepared with the help of MS Project application by sequencing the activities in an appropriate manner. The activities has been arranged in a sequential manner to demonstrate the flow of activities and the sequence which will be followed to conduct the project. The project schedule has been prepared by determining the suitable predecessor to demonstrate which activity will be executed after previous activity. From the scheduling of project, it has been identified that it will be completed on Friday, 06 March 2020 with a duration of 305 days. The project will begin on Monday, 07 January 2019 and it will be carried in four different phases. There are dependencies and simultaneous actives also in this project which has been demonstrated with the help of setting predecessors in MS Project application as shown in Appendix 1. The identification and analysis of risks is an essential element for successful delivery of projects. The risk management process that could be followed for the project is presented as below: RiskRiskImpactProbabilityMitigation Strategy
9BUSINESS MODELLING TOOLS ID 01Inadequate budgetHighHighBudgetingplanhavetobe preparedinplanningphaseand reserve budget should be kept. 02Unavailabilityof resource MediumHighTemporaryresourcehavetobe kept in reserve so that those can be implementedduringshortageor unavailability of resources. 03Poor quality of required materials MediumLowQuality management plan will be developedsuchthatqualityof materialsischeckedduring procurement. 04Lack of technicalskills and knowledge LowHighTheskillsandabilitiesofthe workers should be evaluated prior to allocation in the project. 05Projectprogressisnot according to schedule MediumMediumThe progress of the project should be evaluated and monitored on a regular basis. The resources that should be put in place by the company for smooth execution of the project are people, equipment, facilities and funding. Human resources should be identified and allocated properly so that the execution of the activities could be carried out within the estimated time. The required equipment should be determined during the planning phase of the project so
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10BUSINESS MODELLING TOOLS that procurement could be easily done at the time of performing the associated activity. The facilities for the project have to be ensured such that no issue or conflict does not arises during the project. Proper funding or budget plan will be prepared so that there is no issues of inadequate budget or funding during execution of the project. The process that should be adopted by the company to ensure smooth execution of the project are listed as below: ï‚·The activities should be performed according to requirement of the client so that the project objectives are met. ï‚·The quality of materials should be checked during procurement. ï‚·The project team and the required resources should be managed properly. ï‚·Project progress should checked on a regular basis so that there is no delay in project. ï‚·Risk management should be done efficiently with proper planning and controlling procedures. ï‚·Project communication channels should be established and managed effectively. Conclusion From the overall report, it can be concluded that the project duration increases by 7 days due to the changes in various activities of the structure construction, the interior building and the certification phases. The changes in the different activities has impact on major four phases of the project. The changes within the project should be managed efficiently so that the project could be completed within the estimated timeframe as per developed schedule. The change management within the project should be done with the help of proper strategies such that it
11BUSINESS MODELLING TOOLS could be completed within the estimated time. It is determined that managing the activities that are on critical path will help to complete the project successfully. MS Project application has been used for developing the project schedule through proper sequencing of activities in an effective manner. The activities has been arranged suitably such that the suitable flow of activities can be maintained. The project schedule has been prepared by determining the suitable predecessor to demonstrate which activity will be executed after previous activity. From the prepared schedule after incorporating the changes, it is determined that the project will require 312 days to complete that means additional 7 days are required. The actual schedule prepared from the activities identified by PPO, it is estimated that the project will require 305 days to complete. It means that changes have impact on the project so it is essential to implement proper change management strategies for success of the project.
12BUSINESS MODELLING TOOLS Bibliography Harrison, F. andLock,D., 2017.Advancedprojectmanagement:astructuredapproach. Routledge. Heagney, J., 2016.Fundamentals of project management. Amacom. Kerzner, H. and Kerzner, H.R., 2017.Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons. Walker, A., 2015.Project management in construction. John Wiley & Sons.