Case Study On Substation Project Assignment

Added on - 21 Feb 2021

  • 25

    Pages

  • 5225

    Words

  • 5

    Views

  • 0

    Downloads

Trusted by +2 million users,
assist thousands of students everyday
Showing pages 1 to 6 of 25 pages
CERTIFIED COST PROFESSIONAL (CCP) TECHNICAL PAPERHOW TO GET EXTENSION OF TIME & COST CLAIMS – CASE STUDY ON SUBSTATION PROJECT INSAUDI ARABIA.HOW TO GET EXTENSION OF TIME & COST CLAIMS-CASE STUDY ON SUBSTATION PROJECT IN SAUDI ARABIA1
CERTIFIED COST PROFESSIONAL (CCP) TECHNICAL PAPERHOW TO GET EXTENSION OF TIME & COST CLAIMS – CASE STUDY ON SUBSTATION PROJECT INSAUDI ARABIA.AbstractDisputes and claims in construction contracts will be consistently be involved in numerousissues that are complex and numerous unique cases where the interpretation of the contract orlegal case precedents will not provide immediate solution. Nevertheless, strategies entailinganalysing time extension claims have developed and evolved in the recent years with acombination of recommendations, practice guidelines, protocol, and surfeit of methodologytogether with publications that has been prepared by experts. This paper emphasizes onimportant principles and common problems concerning time extension claims within a casestudy. The case study was carried out through the presently ongoing project, and the projectname is ‘EPC of 33 KV Switching Station’ in Saudi Arabia. Empirical data collected andanalysed from this running project. ( The approval to use this data was granted fromauthorized Project Manager" Mr. Kundan S. Mehta (Project Manager) Contract # xxxxxx,Contract Title xxxxxx, Mobile # +xxxxxxxx, email address .....................)Keywords:Liquidated damages, culpable and concurrent delay, extension of time, disruptionand delay claims2
CERTIFIED COST PROFESSIONAL (CCP) TECHNICAL PAPERHOW TO GET EXTENSION OF TIME & COST CLAIMS – CASE STUDY ON SUBSTATION PROJECT INSAUDI ARABIA.Table of Contents1 Introduction.............................................................................................................................52 LR............................................................................................................................................53 Typical Delays in Electrical Substation Project.....................................................................84 Case Study...............................................................................................................................84.1 Revised Project Technical Specification (PTS) Excusable Compensable Delay.............84.2 Delay in Construction of Duct Banks & Detour removal by the Interface Contractors“A” & “B” on the Cable Route (Excusable Non-Compensable Delay).................................95 Completion Time...................................................................................................................165.1 Extension Time...............................................................................................................165.2 Applying for time extension...........................................................................................166 Condition precedent.............................................................................................................177 Record keeping.....................................................................................................................188 Construction Program...........................................................................................................189 Causation and Types of Delay...............................................................................................219.1 Culpable and concurrent delay.......................................................................................219.2 Organizing Evidence of Delay.......................................................................................2110 Resolution of Problem........................................................................................................2110.1 Delay Claim Analysis...................................................................................................2110.2 Liquidated Damages.....................................................................................................2211 Conclusion...........................................................................................................................223
CERTIFIED COST PROFESSIONAL (CCP) TECHNICAL PAPERHOW TO GET EXTENSION OF TIME & COST CLAIMS – CASE STUDY ON SUBSTATION PROJECT INSAUDI ARABIA.List of Tables4
CERTIFIED COST PROFESSIONAL (CCP) TECHNICAL PAPERHOW TO GET EXTENSION OF TIME & COST CLAIMS – CASE STUDY ON SUBSTATION PROJECT INSAUDI ARABIA.1IntroductionElongation and time extension claim for disruption and delay in construction industryappear to experience the same issues over time, and in some way, it is still challenging tocome up with a collective approach to handle contractual frameworks and other possiblesituations16.In spite of the presence of the advanced software for construction schedules andprogrammes, enhance delay analysis methods, and the sceptical simplicity of its usability,evaluating the extension time is frustrating due to the failure of keeping up to dateprogramme which is made more complex by pathetic lack of concurrent record11.Thediagram (Figure 1) below illustrates the primary components of EOT claims. The nextsection will review the relevant literature from books, journals, and the internet in relation tothe extension of the time claims.2LRIn the case study project’s scope consists of Engineering, Procurement and Construction of: -Two (2) numbers of 33kV Switching Stations CC-1 & CC-2.33kV Direct Buried underground cable network including fiber optic cablefrom CC-1 to Source Substation # 1 (S/S# 1) & CC-2 to S/S # 1.Modification work to connect the 33kV Switching Station feeder Cables at theSource Substation 380/115/33kV S/S # 1.Table 1 below illustrated the contract milestones for the project, contractor developedbaseline schedule based on contract milestone provided in the contract and the same wassubmitted and get approved by Client accordingly.5
CERTIFIED COST PROFESSIONAL (CCP) TECHNICAL PAPERHOW TO GET EXTENSION OF TIME & COST CLAIMS – CASE STUDY ON SUBSTATION PROJECT INSAUDI ARABIA.Table1:ContractualMilestone6
desklib-logo
You’re reading a preview
Preview Documents

To View Complete Document

Become a Desklib Library Member.
Subscribe to our plans

Download This Document