Competency Demonstration Report (CDR) - Career Episode 1
Verified
Added on 2023/06/09
|8
|1393
|499
AI Summary
This CDR report describes a project on the compressible strength of bio-concrete with different SRB concentrations. It includes project background, objectives, distinctive activities, identified issues and their solutions, and project review.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Competency Demonstration Report (CDR) Career Episode 1
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
CE 1.1: Project Introduction Name of the Project:Determination of Compressible Strength of Bio-Concrete with Different SRB Concentrations Geographical Location:Please Fill Project Duration:[Please Fill] Organization:Please Fill Position in the Project:Team Member of the project CE 1.2: Project Background CE 1.2.1:Characteristics of the Project This project is generally based on the analysis of the compressible strength of concrete when various concentrations of sulphate reduction bacteria are applied on it. It has been found that in spite of being a very popular construction material, concrete has a number of problems that include low tensile strength, little resistance to cracking and limited ductility. However, the main focus of this particular project is the chemical attack on concrete i.e. effects of acidic chemicals like sulphate on the concrete. Due to acidic effects of sulphate, the concrete often erodes and causes bad impact on the overall structure. Furthermore, the chemical changes result in weakening of the cement binder. Sulphate reduction bacteria can absorb the sulphate from the concert and convert it into Hydrogen disulphide gas so that the concrete is not affected by the acidic chemical reaction of the sulphate.
CE 1.2.2: Objectives developed for project The main objectives that were developed for the purpose of the project were as follows. To determine the compressive strength of bio concrete when it is incorporated with various concentrations of sulphate reducing bacteria (3%, 5%, 7%) in 3% sodium chloride solution To collect regular concrete and compare results with the same CE 1.2.3: My area of work My field of work in this project was Civil Engineering whereas I was assigned in the project specifically as a Structural Engineer. In this project, I needed to use my technical expertise that I developed during my course in Structural Engineering and I used various concepts, theories and technologies learned during the course for fulfilling my duties in the project. CE 1.2.4: Project Group
Figure 1: Members of the Project Group CE 1.2.5: My responsibilities throughout the project Being selected as the leader of the project team, I was assigned with a number of responsibilities that are listed as follows. I needed to divide the project into several phases and work packages and allocate the work packages to myself and other team members. I needed to undertake some verbal meeting sessions to discuss the project including the concept, possible technical problems and solutions. I needed to conduct Sieve Analysis in order to determine the standard size that is used in concrete mix. I needed to assist my team mates during the slump test to determine workability of concrete matrix. I needed to assist my team mates during data analysis and documentation of the results obtained from the project. CE 1.3: Distinctive Activity CE 1.3.1: Comprehending the Theory of the project This project is mainly based on the study of concrete and the application of sulphur reduction bacteria in order to prevent corrosion of the concrete from sulphate action. Concrete is a strong material that is widely used around the world to build large structures like buildings, monuments and others. Although concrete has high compressive strength, it has very low tensile strength and hence can easily break with the application of strong tensile force. Again, concrete can be easily corroded by sulphate compounds resulting in deformation of the structures. Hence,
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
our focus was to minimize the issues for more efficient use of concrete in construction. I determined that on application of sulphate reduction bacteria (SRB), the sulphate chemicals can be neutralized and corrosion of concrete can be prevented. CE 1.3.2: Engineering Knowledge and Skills applied in the project In this project, I needed to use my engineering skills and knowledge that were helpful for me throughout the course of the project. Since our target was to develop a proper solution of sulphur corrosion of concrete, I first determined a number of possible feasible solutions. I determined the positives and negatives of each of them and then finally selected the sulphur reduction bacteria as the most feasible solution. However, there were significant challenges in implementing the same and I needed to conduct various analyses and tests with various concentrations of RSB in order to find the best possible solution. CE 1.3.3: Accomplishment and Task Performed I accomplished a number of activities in the project including sieve analysis, slump test and pH control. For the purpose of the slump test, I wanted to determine the workability of concrete mix and also to ensure the mixture of the concrete was not too liquid. The slump test results are shown in the following table. MixtureSlump (mm)Types of slump Control35True 3% SRB32True 5% SRB33True 7% SRB33True The solution that I prepared for the concrete was alkaline in nature but also, I needed to maintain the pH level of the solution in order to avoid chemical changes in the solution. Hence, I conducted the pH control test throughout the project and found out the following results.
WeeksPH value Week 112.25 Week 212.23 Week 312.20 Week 412.21 Week 512.2 Week 612.22 Week 712.18 Week 811.5 Week 912.18 CE 1.3.4: Identified Issues and Their Solutions One main technical issue that I faced in the project was that I needed to maintain the alkalinity of the RSB solution during the entire course of the test period. Unless the pH level of the solution was maintained, the chemical tests could not have been conducted. I solved this problem by using NaCl (sodium chloride) in the solution that helped to maintain the pH level of the sample. I maintained the pH level at around 12 and conducted the chemical tests over the entire test period of 9 weeks. CE 1.3.5: Plan for producing creative and innovative work During the project, I planned to produce some creative or innovative work that improved the quality of the project. I used graphical representation to determine the differences between control and microbial samples. When I compared control sample with 3% RSB microbial sample, I generated the following graph.
Figure 2: Strength Differences between Control and Microbial Samples CE 1.3.6: Collaborative work The projectwassignificantlycomplexand individualeffortwasnot sufficientto complete all the duties within time or scope of the project. Hence, I chose to collaborate with other members of my team and together, we set out to execute the project and solve challenges and issues faced during the same. We helped each other during the entire project and ensured all the problemsare solved together before we proceeded to completeour own dutiesand responsibilities in the project. CE 1.4: Project Review CE 1.4.1: Project Overview The entire project was conducted to determine the effect of various RSB concentrations on the strength of concrete. From the results of the project, I determined that this particular bacterium used in the project can grow and replicate even in critical environmental conditions.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Moreover, during the entire sulphur absorption process by the bacteria, CaCO3was deposited that increased the strength of the concrete solution. CE 1.4.2: My contribution to work I was an active contributor in the project as I took responsibilities of many roles in the project. While I took part in duty allocation and managing my team members, I conducted team meetings as well as assisted my team members in various activities in the project. I fulfilled my duties in the project as well and also ensured all requirements of the project have been met.