COIT 20248: Information Systems Analysis and Design
Term 2, 2018
Assessment 1 - Systems Analysis
Lecturer:
Tutor:
Prepared by:
Student Name:
Student Number:
Term 2, 2018
Assessment 1 - Systems Analysis
Lecturer:
Tutor:
Prepared by:
Student Name:
Student Number:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Table of Content
1. Introduction.......................................................................................................................................1
2. Approach to Systems Development..................................................................................................2
3. Systems Requirements......................................................................................................................3
4. Project Cost and Benefit Analysis......................................................................................................4
5. Project Schedule................................................................................................................................6
6. System Information Requirement Investigation Techniques.............................................................8
7. Reflections and Conclusions..............................................................................................................9
REFERENCES:.......................................................................................................................................10
1. Introduction.......................................................................................................................................1
2. Approach to Systems Development..................................................................................................2
3. Systems Requirements......................................................................................................................3
4. Project Cost and Benefit Analysis......................................................................................................4
5. Project Schedule................................................................................................................................6
6. System Information Requirement Investigation Techniques.............................................................8
7. Reflections and Conclusions..............................................................................................................9
REFERENCES:.......................................................................................................................................10
1. Introduction
The report that is being developed basically highlights of the case study for the organization of
International Charity Foundation and there is a need to develop an information system for the
organization, the discussion for which has been provided in this report (Fleming and Koppelmann
2016). I am the software consultant who has been asked to perform an analysis on the design of the
system that the organization is looking to implement.
The main objective of the project is the development of a Global Business Management
System.
The main aims of this report is to provide a detailed description of the analysis of the
project and provide a design which is to be used for the development of the system for the
organization.
Page 1
The report that is being developed basically highlights of the case study for the organization of
International Charity Foundation and there is a need to develop an information system for the
organization, the discussion for which has been provided in this report (Fleming and Koppelmann
2016). I am the software consultant who has been asked to perform an analysis on the design of the
system that the organization is looking to implement.
The main objective of the project is the development of a Global Business Management
System.
The main aims of this report is to provide a detailed description of the analysis of the
project and provide a design which is to be used for the development of the system for the
organization.
Page 1
2. Approach to Systems Development
For the development of the system the Waterfall model is to be adopted, since the
project which being considered in this report is basically a linear project and all the metrics
and the measurements are fixed hence the selection is of this model is very apt for the
development of the project (Marchewka 2014). The major phases which are to be involved
in the project development in this method are requirement gathering phase in which the
major requirements and the deficiencies in the current system for the organization are
identified. After the requirement gathering or the project analysis phase is over the project
planning is considered where the project schedule is designed and the budget for the
project is allocated. The project implementation phase involves the procedures of designing
if the software intended for the project, the database and the integration of the backend
procedures of the database. After the project has been implemented the testing phase is
done where the software is subjected to various type of testing methods and the software is
developed according feedbacks received from testing the system. After the risks involves in
the project are mitigated through the testing procedure the maintenance phase for the
project is covered and the schedule for the maintenance and resource allocation for the
maintenance of the project is done. After the maintenance phase is done with the further
development in the project takes place and the delivery of the project is done by uploading
the project on the domain of the organization and submitting the documents related to the
project.
Page 2
For the development of the system the Waterfall model is to be adopted, since the
project which being considered in this report is basically a linear project and all the metrics
and the measurements are fixed hence the selection is of this model is very apt for the
development of the project (Marchewka 2014). The major phases which are to be involved
in the project development in this method are requirement gathering phase in which the
major requirements and the deficiencies in the current system for the organization are
identified. After the requirement gathering or the project analysis phase is over the project
planning is considered where the project schedule is designed and the budget for the
project is allocated. The project implementation phase involves the procedures of designing
if the software intended for the project, the database and the integration of the backend
procedures of the database. After the project has been implemented the testing phase is
done where the software is subjected to various type of testing methods and the software is
developed according feedbacks received from testing the system. After the risks involves in
the project are mitigated through the testing procedure the maintenance phase for the
project is covered and the schedule for the maintenance and resource allocation for the
maintenance of the project is done. After the maintenance phase is done with the further
development in the project takes place and the delivery of the project is done by uploading
the project on the domain of the organization and submitting the documents related to the
project.
Page 2
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
3. Systems Requirements
The system requirements analysis of any type of project deals with an analysis of the
functional requirements and the non-functional requirements of the project. The functional
requirements of the project are provided below (Walker 2015):
ï‚· The children should be able to enrol themselves into the ICF programs.
ï‚· The system should also be able to provide the institutions and the organizations to
donate money for the welfare of the organization.
ï‚· The system should also be able to keep track of the stock levels in n each of the
braches and the income level and expenses of all the branches of the organization.
ï‚· In addition to this, the organization would also like to provide the login and
registration features for their clients.
The main non-functional requirements of the project are provided below:
Data integrity: The system should be able to store the data of the organization efficiently
and this would help the management of the data for the braches of the organization
efficiently. Thus it is very important feature as the data storage options for any type of
organization is a very important feature and the loss of data from any sector would hamper
the sector effectively.
Availability: The system is to made available for the client on daily basis 24x7 so that they can login
to the system whenever they want to and also this would reduce the response time of the
organization for the clients which would help them in increasing the customer satisfaction level for
the organization.
Page 3
The system requirements analysis of any type of project deals with an analysis of the
functional requirements and the non-functional requirements of the project. The functional
requirements of the project are provided below (Walker 2015):
ï‚· The children should be able to enrol themselves into the ICF programs.
ï‚· The system should also be able to provide the institutions and the organizations to
donate money for the welfare of the organization.
ï‚· The system should also be able to keep track of the stock levels in n each of the
braches and the income level and expenses of all the branches of the organization.
ï‚· In addition to this, the organization would also like to provide the login and
registration features for their clients.
The main non-functional requirements of the project are provided below:
Data integrity: The system should be able to store the data of the organization efficiently
and this would help the management of the data for the braches of the organization
efficiently. Thus it is very important feature as the data storage options for any type of
organization is a very important feature and the loss of data from any sector would hamper
the sector effectively.
Availability: The system is to made available for the client on daily basis 24x7 so that they can login
to the system whenever they want to and also this would reduce the response time of the
organization for the clients which would help them in increasing the customer satisfaction level for
the organization.
Page 3
4. Project Cost and Benefit Analysis
The project cost and benefit analysis is a very important factor that effects towards
the economic feasibility of the project for the organization (Heagney 2016). It has been
given that the monthly income is $9000. Hence, the annual savings for the project is
$108000. Additionally, the maintenance cost of the project annually is $7,200. The cost
benefit analysis of the project is provided below:
Cost benefit analysis for Global Business System
Year 0 Year 1 Year 2 Year 3 Year 4 Year 5
Overall savings $0 $1,08,000 $1,08,00
0
$1,08,00
0
$1,08,00
0
$1,08,00
0
Development cost ($2,50,000
) $0 $0 $0 $0 $0
Maintenance Cost $0 ($7,200) ($7,200) ($7,200) ($7,200) ($7,200)
Net benefit/costs $0 $0 $0 $0 $0 $0
Net cash flow ($2,50,000
) $1,00,800 $1,00,80
0
$1,00,80
0
$1,00,80
0
$1,00,80
0
Discount factors
Discount rate 10%
Year Index 0 1 2 3 4 5
Discount factor 1 0.91 0.83 0.75 0.68 0.62
Discounted flows
Cost ($2,50,000
) ($6,545) ($5,950) ($5,409) ($4,918) ($4,471)
Benefit $0 $98,182 $89,256 $81,142 $73,765 $67,060
Net ($2,50,000
) $91,636 $83,306 $75,733 $68,848 $62,589
Cumulative ($2,50,000
)
($1,58,364
) ($75,058) $675 $69,522 $1,32,11
1
Net present value $1,32,111
Page 4
The project cost and benefit analysis is a very important factor that effects towards
the economic feasibility of the project for the organization (Heagney 2016). It has been
given that the monthly income is $9000. Hence, the annual savings for the project is
$108000. Additionally, the maintenance cost of the project annually is $7,200. The cost
benefit analysis of the project is provided below:
Cost benefit analysis for Global Business System
Year 0 Year 1 Year 2 Year 3 Year 4 Year 5
Overall savings $0 $1,08,000 $1,08,00
0
$1,08,00
0
$1,08,00
0
$1,08,00
0
Development cost ($2,50,000
) $0 $0 $0 $0 $0
Maintenance Cost $0 ($7,200) ($7,200) ($7,200) ($7,200) ($7,200)
Net benefit/costs $0 $0 $0 $0 $0 $0
Net cash flow ($2,50,000
) $1,00,800 $1,00,80
0
$1,00,80
0
$1,00,80
0
$1,00,80
0
Discount factors
Discount rate 10%
Year Index 0 1 2 3 4 5
Discount factor 1 0.91 0.83 0.75 0.68 0.62
Discounted flows
Cost ($2,50,000
) ($6,545) ($5,950) ($5,409) ($4,918) ($4,471)
Benefit $0 $98,182 $89,256 $81,142 $73,765 $67,060
Net ($2,50,000
) $91,636 $83,306 $75,733 $68,848 $62,589
Cumulative ($2,50,000
)
($1,58,364
) ($75,058) $675 $69,522 $1,32,11
1
Net present value $1,32,111
Page 4
ROI 10%
Payback Analysis
Years Months
1 23
Payback Period in
Years 2.90
Table 1: Cost Benefit Analysis
Source: (created by Author)
Page 5
Payback Analysis
Years Months
1 23
Payback Period in
Years 2.90
Table 1: Cost Benefit Analysis
Source: (created by Author)
Page 5
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
5. Project Schedule
The schedule of the project is provided below:
Task Name Duration Start Finish Predecessors
Global Information System 40 days Mon 03-09-18 Fri 26-10-18
Project Initiation 3 days Mon 03-09-18 Wed 05-09-18
Meeting with the clients 2 days Mon 03-09-18 Tue 04-09-18
Identifying the Project aims and
objective 1 day Wed 05-09-18 Wed 05-09-18 2
Requirement Analysis 5 days Thu 06-09-18 Wed 12-09-18
Identifying Functional
Requirements 2 days Thu 06-09-18 Fri 07-09-18 3
Identifying the Non-Functional
Requirements 1 day Mon 10-09-18 Mon 10-09-18 5
Construction of the project
schedule and work breakdown
structure
2 days Tue 11-09-18 Wed 12-09-18 6
Project Implementation 19 days Thu 13-09-18 Tue 09-10-18
System interface design 6 days Thu 13-09-18 Thu 20-09-18 7
Database Development 5 days Fri 21-09-18 Thu 27-09-18 9
Integration of the back end
process with the database 8 days Fri 28-09-18 Tue 09-10-18 10
Project Testing 7 days Wed 10-10-18 Thu 18-10-18
System testing 2 days Wed 10-10-18 Thu 11-10-18 11
Analysis of the test results 2 days Fri 12-10-18 Mon 15-10-18 13
System update 3 days Tue 16-10-18 Thu 18-10-18 14
Project Deployment 2 days Fri 19-10-18 Mon 22-10-18
Page 6
The schedule of the project is provided below:
Task Name Duration Start Finish Predecessors
Global Information System 40 days Mon 03-09-18 Fri 26-10-18
Project Initiation 3 days Mon 03-09-18 Wed 05-09-18
Meeting with the clients 2 days Mon 03-09-18 Tue 04-09-18
Identifying the Project aims and
objective 1 day Wed 05-09-18 Wed 05-09-18 2
Requirement Analysis 5 days Thu 06-09-18 Wed 12-09-18
Identifying Functional
Requirements 2 days Thu 06-09-18 Fri 07-09-18 3
Identifying the Non-Functional
Requirements 1 day Mon 10-09-18 Mon 10-09-18 5
Construction of the project
schedule and work breakdown
structure
2 days Tue 11-09-18 Wed 12-09-18 6
Project Implementation 19 days Thu 13-09-18 Tue 09-10-18
System interface design 6 days Thu 13-09-18 Thu 20-09-18 7
Database Development 5 days Fri 21-09-18 Thu 27-09-18 9
Integration of the back end
process with the database 8 days Fri 28-09-18 Tue 09-10-18 10
Project Testing 7 days Wed 10-10-18 Thu 18-10-18
System testing 2 days Wed 10-10-18 Thu 11-10-18 11
Analysis of the test results 2 days Fri 12-10-18 Mon 15-10-18 13
System update 3 days Tue 16-10-18 Thu 18-10-18 14
Project Deployment 2 days Fri 19-10-18 Mon 22-10-18
Page 6
Installation of the project in the
office 2 days Fri 19-10-18 Mon 22-10-18 15
Project Maintenance 4 days Tue 23-10-18 Fri 26-10-18
Submitting project deliverables 1 day Tue 23-10-18 Tue 23-10-18 17
Assigning personnel for project 1 day Wed 24-10-18 Wed 24-10-18 19
Scheduling Project maintenance 2 days Thu 25-10-18 Fri 26-10-18 20
TABLE 1: Project Schedule
Source: (created by Author)
Global Information
System
Project Initiation
Meeting with the
clients
Identifying the
Project aims and
objective
Requirement Analysis
Identifying
Functional
Requirements
Identifying the
Non-Functional
Requirements
Construction of the
project schedule and
work breakdown
structure
Project Implementation
System interface
design
Database
Development
Integration of the
back end process
with the database
Project Testing
System testing
Analysis of the test
results
System update
Project Deployment
Installation of the
project in the office
Project Maintainance
Submitting project
deliverables
Assigning personnel
for project
Scheduling Project
maintainance
FIGURE 1: Work breakdown Structure
Source: (created by Author)
ID Task
Mode
Task Name Duration Start Finish Predecessors
0 Global Information System40 days Mon 9/3/18 Fri 10/26/18
1 Project Initiation 3 days Mon 9/3/18 Wed 9/5/18
2 Meeting with the clients2 days Mon 9/3/18 Tue 9/4/18
3 Identifying the Project
aims and objective
1 day Wed 9/5/18 Wed 9/5/18 2
4 Requirement Analysis 5 days Thu 9/6/18 Wed 9/12/18
5 Identifying Functional
Requirements
2 days Thu 9/6/18 Fri 9/7/18 3
6 Identifying the
Non-Functional
Requirements
1 day Mon 9/10/18 Mon 9/10/18 5
7 Construction of the
project schedule and
work breakdown
structure
2 days Tue 9/11/18 Wed 9/12/18 6
8 Project Implementation 19 days Thu 9/13/18 Tue 10/9/18
9 System interface design 6 days Thu 9/13/18 Thu 9/20/18 7
10 Database Development 5 days Fri 9/21/18 Thu 9/27/18 9
11 Integration of the back
end process with the
database
8 days Fri 9/28/18 Tue 10/9/18 10
12 Project Testing 7 days Wed 10/10/18 Thu 10/18/18
13 System testing 2 days Wed 10/10/18 Thu 10/11/18 11
14 Analysis of the test results2 days Fri 10/12/18 Mon 10/15/18 13
15 System update 3 days Tue 10/16/18 Thu 10/18/18 14
16 Project Deployment 2 days Fri 10/19/18 Mon 10/22/18
17 Installation of the
project in the offi ce
2 days Fri 10/19/18 Mon 10/22/18 15
18 Project Maintainance 4 days Tue 10/23/18 Fri 10/26/18
19 Submitting project
deliverables
1 day Tue 10/23/18 Tue 10/23/18 17
20 Assigning personnel for
project
1 day Wed 10/24/18 Wed 10/24/18 19
21 Scheduling Project
maintainance
2 days Thu 10/25/18 Fri 10/26/18 20
S M W F S T T S M W F S T T S M W F S T T S M W F S T T S M
Aug 26, '18 Sep 2, '18 Sep 9, '18 Sep 16, '18 Sep 23, '18 Sep 30, '18 Oct 7, '18 Oct 14, '18 Oct 21, '18 Oct 28, '18
FIGURE 2: Gantt Chart
Source: (created by Author)
Page 7
office 2 days Fri 19-10-18 Mon 22-10-18 15
Project Maintenance 4 days Tue 23-10-18 Fri 26-10-18
Submitting project deliverables 1 day Tue 23-10-18 Tue 23-10-18 17
Assigning personnel for project 1 day Wed 24-10-18 Wed 24-10-18 19
Scheduling Project maintenance 2 days Thu 25-10-18 Fri 26-10-18 20
TABLE 1: Project Schedule
Source: (created by Author)
Global Information
System
Project Initiation
Meeting with the
clients
Identifying the
Project aims and
objective
Requirement Analysis
Identifying
Functional
Requirements
Identifying the
Non-Functional
Requirements
Construction of the
project schedule and
work breakdown
structure
Project Implementation
System interface
design
Database
Development
Integration of the
back end process
with the database
Project Testing
System testing
Analysis of the test
results
System update
Project Deployment
Installation of the
project in the office
Project Maintainance
Submitting project
deliverables
Assigning personnel
for project
Scheduling Project
maintainance
FIGURE 1: Work breakdown Structure
Source: (created by Author)
ID Task
Mode
Task Name Duration Start Finish Predecessors
0 Global Information System40 days Mon 9/3/18 Fri 10/26/18
1 Project Initiation 3 days Mon 9/3/18 Wed 9/5/18
2 Meeting with the clients2 days Mon 9/3/18 Tue 9/4/18
3 Identifying the Project
aims and objective
1 day Wed 9/5/18 Wed 9/5/18 2
4 Requirement Analysis 5 days Thu 9/6/18 Wed 9/12/18
5 Identifying Functional
Requirements
2 days Thu 9/6/18 Fri 9/7/18 3
6 Identifying the
Non-Functional
Requirements
1 day Mon 9/10/18 Mon 9/10/18 5
7 Construction of the
project schedule and
work breakdown
structure
2 days Tue 9/11/18 Wed 9/12/18 6
8 Project Implementation 19 days Thu 9/13/18 Tue 10/9/18
9 System interface design 6 days Thu 9/13/18 Thu 9/20/18 7
10 Database Development 5 days Fri 9/21/18 Thu 9/27/18 9
11 Integration of the back
end process with the
database
8 days Fri 9/28/18 Tue 10/9/18 10
12 Project Testing 7 days Wed 10/10/18 Thu 10/18/18
13 System testing 2 days Wed 10/10/18 Thu 10/11/18 11
14 Analysis of the test results2 days Fri 10/12/18 Mon 10/15/18 13
15 System update 3 days Tue 10/16/18 Thu 10/18/18 14
16 Project Deployment 2 days Fri 10/19/18 Mon 10/22/18
17 Installation of the
project in the offi ce
2 days Fri 10/19/18 Mon 10/22/18 15
18 Project Maintainance 4 days Tue 10/23/18 Fri 10/26/18
19 Submitting project
deliverables
1 day Tue 10/23/18 Tue 10/23/18 17
20 Assigning personnel for
project
1 day Wed 10/24/18 Wed 10/24/18 19
21 Scheduling Project
maintainance
2 days Thu 10/25/18 Fri 10/26/18 20
S M W F S T T S M W F S T T S M W F S T T S M W F S T T S M
Aug 26, '18 Sep 2, '18 Sep 9, '18 Sep 16, '18 Sep 23, '18 Sep 30, '18 Oct 7, '18 Oct 14, '18 Oct 21, '18 Oct 28, '18
FIGURE 2: Gantt Chart
Source: (created by Author)
Page 7
6. System Information Requirement Investigation Techniques
The system information requirement technique involves two parts one of which is
stakeholder’s analysis and the others are interviews and questionaries methods which are
to be used for the investigation of the project and effect towards the betterment of the
project (Verzuh 2015). The stakeholders mainly involved in the project are project manager,
database designer, project manager, system engineer, back end developer, customers, staffs
and sponsors for the system which is to be developed. In addition to the stakeholders there
are other methods which are to be followed for the further development of the project and
hence, the procedures such as the interview sessions, questionaries and feedback
procedures are to be adopted.
Interviews: The sessions of the interviews are conducted by the project manager where he
asks the stakeholders a certain amount of questions in a one on one sessions and gathers
very useful information about the development of the project (Mir and Pinnington 2014).
Sometimes the information provided by the stakeholders are very important for the
development of the project and also goes to a great extent for defining of the particulars for
the project.
Questionnaire: The process of questioning the stakeholder for every aspect of the project.
The process is generally conducted after the completion of the project and in this process a
set of questions are handed over to the targeted stakeholders and project is reworked
according to their insights.
Feedbacks: In the feedback process a beta version of the project product is provided to the
stakeholders and they provide an efficient feedback/suggestions to the developers for
improvement of the project to a great extent.
Page 8
The system information requirement technique involves two parts one of which is
stakeholder’s analysis and the others are interviews and questionaries methods which are
to be used for the investigation of the project and effect towards the betterment of the
project (Verzuh 2015). The stakeholders mainly involved in the project are project manager,
database designer, project manager, system engineer, back end developer, customers, staffs
and sponsors for the system which is to be developed. In addition to the stakeholders there
are other methods which are to be followed for the further development of the project and
hence, the procedures such as the interview sessions, questionaries and feedback
procedures are to be adopted.
Interviews: The sessions of the interviews are conducted by the project manager where he
asks the stakeholders a certain amount of questions in a one on one sessions and gathers
very useful information about the development of the project (Mir and Pinnington 2014).
Sometimes the information provided by the stakeholders are very important for the
development of the project and also goes to a great extent for defining of the particulars for
the project.
Questionnaire: The process of questioning the stakeholder for every aspect of the project.
The process is generally conducted after the completion of the project and in this process a
set of questions are handed over to the targeted stakeholders and project is reworked
according to their insights.
Feedbacks: In the feedback process a beta version of the project product is provided to the
stakeholders and they provide an efficient feedback/suggestions to the developers for
improvement of the project to a great extent.
Page 8
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7. Reflections and Conclusions
For the summarization of the project it can be considered that analysis of the project and
the requirements of the company were very important for the development of a Global
management system. The report has been used for the appropriate discussion of the analysis and
the design of the project.
I would like to acknowledge that the course has helped me a great deal in gathering
knowledge about the project management techniques which would be further useful in my
future project in practical life.
Page 9
For the summarization of the project it can be considered that analysis of the project and
the requirements of the company were very important for the development of a Global
management system. The report has been used for the appropriate discussion of the analysis and
the design of the project.
I would like to acknowledge that the course has helped me a great deal in gathering
knowledge about the project management techniques which would be further useful in my
future project in practical life.
Page 9
REFERENCES:
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project
Management Institute.
Marchewka, J.T., 2014. Information technology project management. John Wiley & Sons.
Walker, A., 2015. Project management in construction. John Wiley & Sons.
Heagney, J., 2016. Fundamentals of project management. Amacom.
Verzuh, E., 2015. The fast forward MBA in project management. John Wiley & Sons.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking project
management performance and project success. International journal of project management, 32(2),
pp.202-217.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking project
management performance and project success. International journal of project management, 32(2),
pp.202-217.
Page 10
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project
Management Institute.
Marchewka, J.T., 2014. Information technology project management. John Wiley & Sons.
Walker, A., 2015. Project management in construction. John Wiley & Sons.
Heagney, J., 2016. Fundamentals of project management. Amacom.
Verzuh, E., 2015. The fast forward MBA in project management. John Wiley & Sons.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking project
management performance and project success. International journal of project management, 32(2),
pp.202-217.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking project
management performance and project success. International journal of project management, 32(2),
pp.202-217.
Page 10
1 out of 12
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024  |  Zucol Services PVT LTD  |  All rights reserved.