CE 2.1 Project InformationName of the project: Construction of Abu Baker Siddiq Road Phase 2Location of the project: Riyadh, Saudi ArabiaProject Duration: From November of 2015 to presentOrganization: Ferrovial Agroman Role and Designation during the time: Site Civil Engineer (Project Engineer)CE 2.2 Project BackgroundCE 2.2.1 Characteristics of the projectConstruction of the Abu Baker Siddiq Road Phase 2 project was carried out in Riyadh,Saudi Arabia. Abu Baker Siddiq Road Phase 2 has three intersections: Al-Thumama intersection,King Salman intersection and Anas Bin Malek Intersection. The duration of the project was fromNovember of 2015 to present. This project was undertaken by Ferrovial Agroman Company.This company is responsible for carrying out building, construction and industrial projects. Thisproject was about the overall construction of 20.1 km road. The Abu Baker Siddiq Road Phase 2project about constructing a main bridge of 2 km; fly over bridge of 2.2 km, underpass of 1 km,retaining wall length of 3.2 km and 200 manholes. The value of this project was USD 200million. The client of this project was ADA. CE 2.2.2 Objectives developed for the projectRoad construction is carried out for the purpose of reducing travel time, reducingaccidents and providing a route that helps in economic development. The main objective of this
Construction of Abu Baker Siddiq Road Phase_1
project was to execute all the major project control strategies in the civil and constructionactivities of the construction of the Abu Baker Siddiq Road Phase 2. The major activities of thisproject were project schedule controlling and reporting of details to the management. CE 2.2.3 My Area of workI was the Site Civil Engineer of the construction of the Abu Baker Siddiq Road Phase 2project from November of 2015 to present. I had to report to the Construction Manager. Beingthe Site Civil Engineer, my area of work was to supervise all the activities of the project. Myarea of work was the designing of the project or task plan with genuinely created assignmentschematics. I was mainly involved in the interpretation of the task specifications along with afew isometric drawings. I had systematically controlled the challenge of resources as well as thetotal value of the project. I had also designed several painting techniques for the project team. Ihad utilized my skills and knowledge in supervising the performance of the project work thatwas being carried out.
Construction of Abu Baker Siddiq Road Phase_2
CE 2.2.4 Project GroupFigure 1: People involved in the projectCE 2.2.5 My responsibilities throughout the projectI had various core responsibilities in the Construction of the Abu Baker Siddiq RoadPhase 2 project. Being the Site Civil Engineer, my main responsibility was to assist theConstruction Manager in supervising all the site activities of the project. I was responsible forcarrying out analysis and making the break down for the activities and the items that wasrequired in the start of the actual and theoretical project for the purpose of comparing it with ourprices. I had undertaken the responsibility of preparing purchase orders, change orders andsubcontractors. My responsibility was to review the shop drawings and coordinate it with thetechnical department for making the modification of the drawings and site. I was responsible for
Construction of Abu Baker Siddiq Road Phase_3

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Competency Demonstration Report - PDF
|9
|1791
|116

Assignment on Competency Element
|6
|1669
|236

Competency Demonstration Report (CDR) for Professional Engineering
|13
|2127
|204

Professional Engineering Summary Statement Assignment
|6
|1000
|444

Construction of 18 ft Wide Road in Zone 6 of Bathinda City - Project Overview
|8
|1761
|306

Business Problems and Issues Report
|3
|306
|229