This report reflects on the various project management practices those are considerable for the successful and efficient delivery of the respective project. The scope of the project is to develop a sophisticated software application that can support the smooth and efficient exchange of the data and information related to the ongoing operations at the construction site.

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Running head: CONSTRUCTION APPLICATION SERVICE CONSTRUCT X-PRO
Project Management
Construction Application Service Construct X-Pro
Name of the Student
Name of the University
Author Note

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
CONSTRUCTION APPLICATION SERVICE CONSTRUCT X-PRO
Abstract
The purpose of this report is to reflect on the various project management practices those are
considerable for the successful and efficient delivery of the respective project. The scope of
the project is to develop a sophisticated software application that can support the smooth and
efficient exchange of the data and information related to the ongoing operations at the
construction site. The EVM Earned Value Management method has been used for assessing
the factors related to the quality, time, and cost of the project during its implementation
phase. The goal of the project is to demonstrate the planning, monitoring and control
techniques those will be allowing the successful and efficient delivery of the project. MS
Project is used as the tool for the calculation and management of the project delivery.
Document Page
CONSTRUCTION APPLICATION SERVICE CONSTRUCT X-PRO
Table of Contents
Introduction................................................................................................................................4
Project Success Definition.........................................................................................................4
Project Planning.....................................................................................................................5
Monitoring (on 24th December 2018).....................................................................................7
Monitoring and Controlling (During Implementation)..............................................................8
Earned Value Analysis...........................................................................................................9
Monitoring and Controlling (After Implementation)...............................................................13
Conclusion................................................................................................................................13
References................................................................................................................................14
Document Page
CONSTRUCTION APPLICATION SERVICE CONSTRUCT X-PRO
Introduction
Project planning phase can be considered as the most crucial phase for the project
growth and development however, project monitoring and controlling is of same importance
throughout the project (Fleming and Koppelman 2016). In order to manage the project
growth and development of the project including the quality, the monitoring and controlling
techniques will be highly effective and efficient in reviewing the ongoing performance of the
project and determine what type of new planning is required for assuring that the further
activities will be meeting the estimated goals and objectives of the project. The aim of the
project is to make sure the project planning that has been developed is delivered successfully
and all the objectives and scope of the project met the estimated values. This will be achieved
through the adoption of proper tools and techniques those could allow in efficient and
effective control and monitoring of the project.
Project Success Definition
Project definition is the prior phase of the project development that needs to be done
with proper considerations. It includes the planning of the scope and objective of the project
that has been already done as mentioned in the last presentation (Batselier and Vanhoucke
2015). Moving forward, the planning is the next phase that will have crucial impact in the
overall delivery and management of the project. The success components of a project are
time, budget, cost and quality (also known as project triangle). The project success can be
measured accordingly through comparing the planned constraints and the final deliveries of
the project (Willems and Vanhoucke 2015). The success measurement can also be defined as
the satisfaction level of the end users. In relation to both the parameter, Earned Value
Management approach best suits the performance measurement in manner to make sure that
the project being delivered meets the expected output of the project.

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
CONSTRUCTION APPLICATION SERVICE CONSTRUCT X-PRO
Project Planning
Considering the previous presentation, the project definition and planning is going to
be completed till 224th December 2018. Considering this, the project execution phase needs to
be initiated. The monitoring and controlling phases have been divided in two phases
including during the project execution and after project execution (Colin and Vanhoucke
2015). The baseline set in the project includes the following project details:
Document Page
CONSTRUCTION APPLICATION SERVICE CONSTRUCT X-PRO
Figure 1: Gantt chart
(Source: Created by author using MS Project)
In order to get success in the project plan, the project manager should plan the entire
project properly as per the client’s and project requirements. It is done throughout drawings
the project plan, scope, schedule as well as project cost of the project. It is also required to
calculate the project budget, resources required and project schedule (Batselier and
Vanhoucke 2015). The project plan is based on encompassing of such technology that helps
in sharing documents and edited pictures to team for keeping the project team members
updated to the project. The company facilitates to plan, document and accelerate field
inspections, safety, quality of work and update and manage the project procurement
(Batselier and Vanhoucke 2017). In order to control and monitor the project plan, the
company stores and access the files on time, track the project progress, help to create reports
and track the construction progress. The scope of this project plan is to establish best
application with high features of editing, managing the team, sharing and statistics of the
project work. The team members are motivated to aid people for keeping track of the
construction work (Colin and Vanhoucke 2015). It enhances and manages the team work and
keeps the team members up to the date.
The project plan benefits in various ways due to implementation of application in
Construct X-pro. At the planning stage, when the project is approved, then the project team
can assemble the project team and start plan how to manage the entire project work to
achieve the project goals in estimated budget as well as on time (Kerkhove and Vanhoucke
2017). The project manager is required to analyze the scope statement and project
deliverables, objectives. The project manager can break down the project deliverables in
smaller ones which help to manage the team. All the project tasks are analyzed on time and
allocated to the project team members focused on skills as well as expertise. The project
Document Page
CONSTRUCTION APPLICATION SERVICE CONSTRUCT X-PRO
manager determines duration of project tasks and set the dates of project completion (Kim et
al. 2015). The project cost is estimated which is involved across the project as well as
formulate of project budget. The project quality objectives are to be meeting through the
project work. Roles and responsibilities of the project team members are done so that all the
project tasks are allocated among them (Webb 2017). The project risks are also determined so
that there should not be any huge impact and influence on the project work.
In order to complete the project work on time, there should be control of the project
activities, which ensures that the project is completed in scheduled time. When the deadline
of project is missed and it is finished out of project sequence, then there is knock out effects
on rest of the project plan (Chen, Chen and Lin 2016). It could be delivered late and as a
result, there is high in project cost. Gantt chart is used to convey the project information to
the project team members. It outlines the project tasks involved in the project work and
showed the timescale of the project work. It will provide an overview of the entire project
work, associated project activities and when it is to be finished within scheduled time. Most
of the projects are failed due to underestimation of time as well as money as significant part
of project work is overlooked (Fleming and Koppelman 2016). The technique which is used
to avoid the problems and issues is work breakdown structure aids in process to determine the
project scope, project activities and estimate budget.
Monitoring (on 24th December 2018)
The MS project tool is used for calculating the earned value analysis on the above
mentioned date considering the baseline set as per the above information. It is identified that
the previous project growth was done as per the planning and hence, considering the above
baseline, following Gantt chart is developed for representing the work being accomplished:

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
CONSTRUCTION APPLICATION SERVICE CONSTRUCT X-PRO
Figure 3: Gantt chart with set Baseline
(Source: Created by Author using MS Project)
The first two phases of the project are completed 100% and hence the project
initiation or definition have same bar for the percentage of the work delivered (Kim et al.
2015). Selecting the critical path, the above demonstrated activities determined the new list of
activities as the critical activities.
Monitoring and Controlling (During Implementation)
It is necessary to assure that the project is being completed within the expected budget
and schedule that can be analysed and identified using the earned value analysis as
demonstrated in the next paragraph (Naeni, Shadrokh and Salehipour 2014). It allows the
project manager to identify the previous, current, and future positions of the project with
Document Page
CONSTRUCTION APPLICATION SERVICE CONSTRUCT X-PRO
respect to the cost and schedule (Kerkhove and Vanhoucke 2017). Schedule variance (SV),
Actual Cost (AC), Planned Value (PV), Estimate at Completion (EAC), and Cost variance
(CV) can be measured in manner to identify the rest of the factors related to the project
growth and development (Abdi,Taghipour and Khamooshi 2018). Based on these values the
following earned value can be calculated:
Earned Value Analysis
The earned value analysis (EVA) is considered as project controlling procedure which
is termed as key performance indicators of the project work. With EVA, the planned as well
as current project cost is being identified on reporting date and earned value. Based on the
earned value, the future course of project plan plus predicted completion cost is being
calculated before end of the project work (Abdi, Taghipour and Khamooshi 2018). EVM is
the project management method to measure project performance along with progress in the
project objectives. It has capability to combine the measurements of project triple constraints
such as scope, time and cost (Batselier and Vanhoucke 2015). The earned value management
is provided proper forecasts of the project performance issues, which is important
contribution for the project management. Required features for EVM implementation is
included of:
The project plan is identified the work to accomplish.
Valuation of the planned work which is termed as planned value and budgeted cost
for the work scheduled (Fleming and Koppelman 2016).
Earning rules to quantify accomplishment of the project work termed as earned value
and budgeted cost of the work performed.
There s proper estimation of project variance based on time and cost (Kerkhove and
Vanhoucke 2017).
Document Page
CONSTRUCTION APPLICATION SERVICE CONSTRUCT X-PRO
Benefits of EVM for this project plan are as follows:
1. There is integration of the work, schedule as well as cost using the work
breakdown structure.
2. There is getting of historical data from the completed project work so that it is
used for the comparative analysis of the project work (Willems and Vanhoucke
2015).
3. There is estimation of cost as well as schedule performance index.
Authorized project work and resources are being integrated with use of product
oriented work breakdown structure. It helps the company to coordinate as well as determine
the contributions of the project area which will ensure the there is proper integration of the
project schedule as well as project cost (Naeni, Shadrokh and Salehipour 2014). Managing as
well as reporting of data across the system is not effective and effective, therefore EVM is
resulted in faster reporting cycles and more time is required for the cost analysis. Importance
of the project cost as well as project schedule is detectable when the planned work is being
reached as little as there is 10% completion of the project work (Colin and Vanhoucke 2015).
Therefore, there are issues related to project performance, productivity, schedule and cost.
In this project plan, the project will get success when EVM will keep the management
on estimated budget and project cost. With use of this technique, the management will make
sure that the project parameters are be on the track and the project will process their tasks as
per scheduled time (Batselier and Vanhoucke 2015). It is presented that the project can track
based on time and cost. Timely performance measurement ensures that the steps are to be
taken to bring the project on track before it impacts the project work on a huge. Schedule and
cost variance is required in the project which can cause difference among the projected

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
CONSTRUCTION APPLICATION SERVICE CONSTRUCT X-PRO
baseline as well as actual project performance (Chen, Chen and Lin 2016). It is based on
three different levels such as estimated to plan, plan to actual and estimate to actual.
Figure 4: Earned value analysis
(Source: Created by author by MS project)
The earned value analysis predicts, the project is going as per the schedule and is
under budget. The further controlling should be based on the management of the rest of the
activities as per the new critical path identified (Chen et al. 2016). The earned value graph
can be represented as:
Figure 5: Graphs of Earned Value
(Source: Created by Author using MS Project)
Monitoring and Controlling (After Implementation)
The end customer satisfaction level can be measured for the post monitoring and
controlling after the implementation (Webb 2017). The proposed project should allow the
construction site’s representative to smoothly exchange the spreadsheet or data that has
been calculated during the deployment of certain constructions. The other side users should
be allowed to access the same data or information without any hurdle.
Conclusion
It can be concluded that the earned value management can allow the efficient and
effective management of the project deliveries. It helped in analysing the past, present and
Document Page
CONSTRUCTION APPLICATION SERVICE CONSTRUCT X-PRO
future prediction of the project schedule and cost variances. These information can be used
for developing the strategies those best suited as per the present information and meet the
final objectives and goals of the project. This report was based on the monitoring and
controlling of the project ‘construction application service construct X-Pro.’ The calculation
demonstrates the variances, planned, value, earned value and others as per the assumption
that the project was on time before the execution phase starts.
Document Page
CONSTRUCTION APPLICATION SERVICE CONSTRUCT X-PRO
References
Abdi, A., Taghipour, S. and Khamooshi, H., 2018. Corrigendum to “A model to control
environmental performance of project execution process based on greenhouse gas emissions
using earned value management”[Int. J. Proj. Manag. 36 (3)(April 2018) 397-
413]. International Journal of Project Management, 36(8), pp.1047-1049.
Batselier, J. and Vanhoucke, M., 2015. Empirical evaluation of earned value management
forecasting accuracy for time and cost. Journal of Construction Engineering and
Management, 141(11), p.05015010.
Batselier, J. and Vanhoucke, M., 2015. Evaluation of deterministic state-of-the-art forecasting
approaches for project duration based on earned value management. International Journal of
Project Management, 33(7), pp.1588-1596.
Batselier, J. and Vanhoucke, M., 2017. Improving project forecast accuracy by integrating
earned value management with exponential smoothing and reference class
forecasting. International journal of project management, 35(1), pp.28-43.
Chen, H.L., Chen, W.T. and Lin, Y.L., 2016. Earned value project management: Improving
the predictive power of planned value. International Journal of Project Management, 34(1),
pp.22-29.
Colin, J. and Vanhoucke, M., 2015. A comparison of the performance of various project
control methods using earned value management systems. Expert Systems with
Applications, 42(6), pp.3159-3175.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management.
Project Management Institute.

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
CONSTRUCTION APPLICATION SERVICE CONSTRUCT X-PRO
Kerkhove, L.P. and Vanhoucke, M., 2017. Extensions of earned value management: Using
the earned incentive metric to improve signal quality. International Journal of Project
Management, 35(2), pp.148-168.
Kim, J., Koo, C., Kim, C.J., Hong, T. and Park, H.S., 2015. Integrated CO2, cost, and
schedule management system for building construction projects using the earned value
management theory. Journal of Cleaner Production, 103, pp.275-285.
Naeni, L.M., Shadrokh, S. and Salehipour, A., 2014. A fuzzy approach for the earned value
management. International journal of project management, 32(4), pp.709-716.
Webb, A., 2017. Using earned value: a project manager's guide. Routledge.
Willems, L.L. and Vanhoucke, M., 2015. Classification of articles and journals on project
control and earned value management. International Journal of Project Management, 33(7),
pp.1610-1634.