Construction and Installation Sequence for Building a Double Brickwall and Ground Slab

   

Added on  2023-06-04

4 Pages626 Words292 Views
SOLUTIONS TO THE TOPIC EXERCISES
TOPIC 2
1. Setting out the plan of the building
Figure 1: Setting out plan
Construction and Installation Sequence for Building a Double Brickwall and Ground Slab_1
Figure 2: Double brickwall and ground slab interaction
TOPIC 3
2. Construction and installation sequence
(a) Site clearing
Firstly, bring all the required machinery to site. Such machineries would include:
excavators, rock drills, compacting machine among others. Bulldozers are to be used
where vegetation is thick and matured. Properly de-stump the site and remove trees
nearby that are likely to affect the building structural integrity. Undertake proper
landscaping.
Construction and Installation Sequence for Building a Double Brickwall and Ground Slab_2

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Construction Footing System Assignment
|16
|1495
|199

CPCCBC5018A Apply Structural Principles to Construction of Medium Rise Buildings
|10
|900
|220

Applying Structural Principles to Residential Low-Rise Constructions
|9
|1005
|146

CPCCBC4011B: Assessment 4 - Footing, Retaining Wall, Structural, Floor, Wall, Roof, Services, Fire Prevention, Quality
|9
|843
|328

Residential Construction: Concrete Footings, Hydraulic Services, Load Bearing Walls, Scaffold Systems
|21
|4697
|236

Construction Management
|11
|1575
|71