Construction Management Payment: Interim and Final Payment Process

Verified

Added on  2023/04/06

|11
|531
|441
Presentation
AI Summary
This presentation provides an overview of the payment process in construction management procurement. It explains the contractual terms related to payment, including interim and final payment. The steps involved in applying for and approving interim and final payments are also discussed. The presentation emphasizes the importance of payment notices and provides a reference to the Housing Grants, Construction and Regeneration Act 1996.

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
CONSTRUCTION
MANAGEMENT
Part 2: Presentation and
Q&A

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
As in the construction management procurement
rout the contractor engages into the advising the
client or the employer on fee basis therefore the
payment and as the procurement route allows
better interaction between the contractor and the
client the transaction or the payment can be
segregated into goal based interims along with the
final payment. The sub-contractors along with the
main contractor interact with the client. Therefore
the client has better chance of appraising the main
contractor’s work and make payment accordingly.
Introduction
Document Page
The total payment would be segregated in
two major parts
Final payment (60%)
Interim payment (40%)
The interim payment would be provided on
quarterly installments
Contractor has to apply for both the kinds of
payments in appropriate format
Contractual terms related to
payment to the contractor
Document Page
As per section 109 of Housing Grants, Construction and
Regeneration Act 1996 in case of construction contracts
that exceed the period of 45 days, the parties are
entitled to interim or stage payments (Housing Grants,
Construction and Regeneration Act 1996, (n.d.).
The amount of the payment can be agreed by both the
parties.
For the current case 40% of the total fee would be paid
as interim payment
This 40% of the fee would be divided in equal parts of
quarterly payment for the length of the contract period
and paid at every three months.
Interim payment legislature

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Contractor applies for quarterly interim payment
The advisor or the construction manager of the
builders will have to review the payment
application made by the contractor
The work done will be reviewed
Quantity surveyor would prepare bills for
approximate payment required based on
contractual terms
The construction manager would review and
approve the payment suggestion by quantity
surveyor
Steps of interim payment
Document Page
Once approved by construction manager
the payment certificate would be sent to
the employers, here the builders for
payment
The construction manager would monitor
the payment status to make sure that the
contractual obligations related to payment
is met
Steps of interim payment
(Cont…)
Document Page
After completion of the final work the
contractor applies for final payment
Construction manager review the
application and appraises the work
completed
The quantity surveyor would appraise the
amount as per the contract and application
of the contractor
Additional works would be reviewed and
their fee would be estimated too
Steps of final payment

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Appraisal would be reviewed by
construction manager and sent to the
employers or the builders in this case
Builders would approve if they are satisfied
with the final work
Construction manager would make sure that
the final payment is made as per the
obligation of the contract
Steps of final payment
(cont…)
Document Page
Every payment needs to be accompanied
by a payment notice that contained details
of the payment such as the following:
Name of the receiver
Date
Amount
Cause
Contractual causes
Conclusion
Document Page
Housing Grants, Construction and
Regeneration Act 1996, (n.d.) Housing
Grants, Construction and Regeneration Act
1996 [online]. Available from:
http://www.legislation.gov.uk/ukpga/1996/5
3/section/109 [Accessed 15 March 2019]
Reference

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1 out of 11
[object Object]

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]