Construction Management Project Of Volcano World
VerifiedAdded on 2022/11/25
|15
|2245
|176
AI Summary
This document discusses the construction management project of Volcano World, including project integration management, project quality management, project scope management, project resource management, project schedule management, project communication management, project cost management, project procurement management, project risk management, project stakeholder management, and project environmental management.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
![Document Page](https://desklib.com/media/document/docfile/pages/construction-management-project-of-volca-tyw3/2024/09/27/8ea3c5f2-6cf4-4d1a-9bee-3f54daf4f92c-page-1.webp)
Running head: CONSTRUCTION MANAGEMENT PROJECT OF VOLCANO WORLD
Construction Management Project Of Volcano World
Name of the Student
Name of the University
Author note
Construction Management Project Of Volcano World
Name of the Student
Name of the University
Author note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
![Document Page](https://desklib.com/media/document/docfile/pages/construction-management-project-of-volca-tyw3/2024/09/27/ee42fa26-d5e9-4e54-943a-5f6b541d7fcd-page-2.webp)
1CONSTRUCTION MANAGEMENT PROJECT OF VOLCANO WORLD
Table of Contents
1. Project Integration Management..................................................................................................2
2. Project Quality Management.......................................................................................................2
3. Project Scope Management.........................................................................................................4
4. Project Resource Management....................................................................................................5
5. Project Schedule Management....................................................................................................7
6. Project Communication Management.........................................................................................9
7. Project Cost Management..........................................................................................................10
8. Project Procurement Management.............................................................................................10
9. Project Risk Management..........................................................................................................11
10. Project Stakeholder Management............................................................................................11
11. Project Environmental Management.......................................................................................11
Bibliography..................................................................................................................................13
Table of Contents
1. Project Integration Management..................................................................................................2
2. Project Quality Management.......................................................................................................2
3. Project Scope Management.........................................................................................................4
4. Project Resource Management....................................................................................................5
5. Project Schedule Management....................................................................................................7
6. Project Communication Management.........................................................................................9
7. Project Cost Management..........................................................................................................10
8. Project Procurement Management.............................................................................................10
9. Project Risk Management..........................................................................................................11
10. Project Stakeholder Management............................................................................................11
11. Project Environmental Management.......................................................................................11
Bibliography..................................................................................................................................13
![Document Page](https://desklib.com/media/document/docfile/pages/construction-management-project-of-volca-tyw3/2024/09/27/302103a0-c7f3-40be-861c-bc72ad97b3a8-page-3.webp)
2CONSTRUCTION MANAGEMENT PROJECT OF VOLCANO WORLD
1. Project Integration Management
Deliverables – The project is based on delivering a recreational park that would comprise
of every basic necessities. The project would also be completed in the given time frame and also
within the estimated budget.
Milestones – The certain milestones for the project are:
Approval of the project management plan and financial plan
Completion the setup phase for the project
Completion of the implementation phase
Key Performance Indicators – The certain KPI’s for the project are:
Scope – The components include: a course for treetop adventure, swimming lagoon and
course for white water rapids, general infrastructure and facilities, management of event for the
celebration of Utopia National Day.
Time – The time taken for the completion of the project is 389 days.
Cost – The cost incurred for the project is AUD $ 497,040
Risk – Construction related risks such as wrong estimation of costs, resources and many
others could affect the project.
Measure of Success – The measurement of success for the project would be measured
based on the achievement of each of the ideas generated during the start of the project.
1. Project Integration Management
Deliverables – The project is based on delivering a recreational park that would comprise
of every basic necessities. The project would also be completed in the given time frame and also
within the estimated budget.
Milestones – The certain milestones for the project are:
Approval of the project management plan and financial plan
Completion the setup phase for the project
Completion of the implementation phase
Key Performance Indicators – The certain KPI’s for the project are:
Scope – The components include: a course for treetop adventure, swimming lagoon and
course for white water rapids, general infrastructure and facilities, management of event for the
celebration of Utopia National Day.
Time – The time taken for the completion of the project is 389 days.
Cost – The cost incurred for the project is AUD $ 497,040
Risk – Construction related risks such as wrong estimation of costs, resources and many
others could affect the project.
Measure of Success – The measurement of success for the project would be measured
based on the achievement of each of the ideas generated during the start of the project.
![Document Page](https://desklib.com/media/document/docfile/pages/construction-management-project-of-volca-tyw3/2024/09/27/d06d6d8f-abef-4c7c-b454-393dd59e609d-page-4.webp)
3CONSTRUCTION MANAGEMENT PROJECT OF VOLCANO WORLD
2. Project Quality Management
ISO Standards – In accordance to the construction of Volcano World, the ISO 9000
standard could be defined as perfect to progress over the project stages. Different forms of risks
may arise in any construction project. Hence, the standard could help in reducing the amount of
complexity. The standard proposes an informal form of inspection and a qualified test system
that would perform a thorough check over the system and the end product.
Australian Standards and Codes (ASC) – The National Construction Code (NCC)
Series was primarily proposed by the Australian Buildings Code Board (ABCB). They comprise
of the Building Code of Australia (BCA), which covers the aspects of buildings such as sheds,
houses and many others. The other part is the Plumbing Code of Australia (PCA), which covers
the aspect of drainage and plumbing in regards to every class of building.
Quality Assurance – This is defined as a major component for checking the quality of
systems. During the planning and design over the project, the project manager would be
responsible for designing the plan for the entire project.
Reducing Process Complexity – The project deals with the various ways in which the
complexity could be reduced from the project. In order to deal with the certain ways, the
concerned project team would work together to plan the most appropriate ways in which the
project could be designed.
Acceptance Criteria – The project would be finally accepted by the UNHCR, which is
the governing body of UTOPIA. The final project outcomes would be accepted by UNHCR by
checking over each of the aspects. They would also ensure whether each of the deliverables have
been made as per the standards of acceptance.
2. Project Quality Management
ISO Standards – In accordance to the construction of Volcano World, the ISO 9000
standard could be defined as perfect to progress over the project stages. Different forms of risks
may arise in any construction project. Hence, the standard could help in reducing the amount of
complexity. The standard proposes an informal form of inspection and a qualified test system
that would perform a thorough check over the system and the end product.
Australian Standards and Codes (ASC) – The National Construction Code (NCC)
Series was primarily proposed by the Australian Buildings Code Board (ABCB). They comprise
of the Building Code of Australia (BCA), which covers the aspects of buildings such as sheds,
houses and many others. The other part is the Plumbing Code of Australia (PCA), which covers
the aspect of drainage and plumbing in regards to every class of building.
Quality Assurance – This is defined as a major component for checking the quality of
systems. During the planning and design over the project, the project manager would be
responsible for designing the plan for the entire project.
Reducing Process Complexity – The project deals with the various ways in which the
complexity could be reduced from the project. In order to deal with the certain ways, the
concerned project team would work together to plan the most appropriate ways in which the
project could be designed.
Acceptance Criteria – The project would be finally accepted by the UNHCR, which is
the governing body of UTOPIA. The final project outcomes would be accepted by UNHCR by
checking over each of the aspects. They would also ensure whether each of the deliverables have
been made as per the standards of acceptance.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
![Document Page](https://desklib.com/media/document/docfile/pages/construction-management-project-of-volca-tyw3/2024/09/27/12db26b3-722c-4b0c-b293-2fede01aefa2-page-5.webp)
4CONSTRUCTION MANAGEMENT PROJECT OF VOLCANO WORLD
Continuous Process Improvement – The factor of CPI could be measured by UNHCR
based on the certain objectives.
Maintaining good communication between the staff members
Measurement and evaluation of work progress based on certain benchmarks and KPIs.
Development training sessions for the staff involved within the recreational park.
3. Project Scope Management
Scope Baseline (kpi variable) – The scope baseline is being referred as the version for
the scope statement, WBS and the associated WBS dictionary. The KPI could be defined as a
certain metric that would have the ability for directly putting an impact over the cash flow and
measuring conversions.
Design brief – The project based on the design of a recreational park, Volcano World
would be accommodated with well-designed facilities. This park would feature the best and
world-class facilities. Different adventure courses would also be provided for the benefit of the
people visiting the park. The other objective for the project is to provide exclusive enjoyment for
the Utopian citizens.
Continuous Process Improvement – The factor of CPI could be measured by UNHCR
based on the certain objectives.
Maintaining good communication between the staff members
Measurement and evaluation of work progress based on certain benchmarks and KPIs.
Development training sessions for the staff involved within the recreational park.
3. Project Scope Management
Scope Baseline (kpi variable) – The scope baseline is being referred as the version for
the scope statement, WBS and the associated WBS dictionary. The KPI could be defined as a
certain metric that would have the ability for directly putting an impact over the cash flow and
measuring conversions.
Design brief – The project based on the design of a recreational park, Volcano World
would be accommodated with well-designed facilities. This park would feature the best and
world-class facilities. Different adventure courses would also be provided for the benefit of the
people visiting the park. The other objective for the project is to provide exclusive enjoyment for
the Utopian citizens.
![Document Page](https://desklib.com/media/document/docfile/pages/construction-management-project-of-volca-tyw3/2024/09/27/1616b58f-1015-43c2-b8bc-ae696b97207b-page-6.webp)
5CONSTRUCTION MANAGEMENT PROJECT OF VOLCANO WORLD
Standards – The necessity of standards within the construction project of the recreational
park would be highly important. Hence, the ISO 9000 standard would be highly useful as it
would form some documents in which the different benchmarks would be classified.
Assumptions and Constraints – The assumptions for the project could be classified as:
1. The project would facilitate with each of the defined scope variables.
2. The project will be completed within the deadline and budget.
The constraints for the project would be classified as:
1. The project would not cover a tourist catalogue for the display of every activity.
4. Project Resource Management
Organisational Breakdown Structure -
Leadership Roles and Responsibilities –
Project Resources Roles and Responsibilities
UNHCR This body governs the entire management of the project
Deloitte, Australia Sponsor for the event
Project manager Managing each of the aspect of development of project plan
Trainers Giving a proper kind of training for the different adventure courses
Labours Maintaining the level of design as mentioned within the project plan
Work Task Resources – The resources required for performing the work task are:
UNHCR, Deloitte, Australia, Project manager, Trainers and labours.
Industrial Awards – Different working awards that would be provided for the
employees working over the project are: leave for the employees, overtime facilities, and extra
pay for the employees who would complete their target within an estimated time.
Standards – The necessity of standards within the construction project of the recreational
park would be highly important. Hence, the ISO 9000 standard would be highly useful as it
would form some documents in which the different benchmarks would be classified.
Assumptions and Constraints – The assumptions for the project could be classified as:
1. The project would facilitate with each of the defined scope variables.
2. The project will be completed within the deadline and budget.
The constraints for the project would be classified as:
1. The project would not cover a tourist catalogue for the display of every activity.
4. Project Resource Management
Organisational Breakdown Structure -
Leadership Roles and Responsibilities –
Project Resources Roles and Responsibilities
UNHCR This body governs the entire management of the project
Deloitte, Australia Sponsor for the event
Project manager Managing each of the aspect of development of project plan
Trainers Giving a proper kind of training for the different adventure courses
Labours Maintaining the level of design as mentioned within the project plan
Work Task Resources – The resources required for performing the work task are:
UNHCR, Deloitte, Australia, Project manager, Trainers and labours.
Industrial Awards – Different working awards that would be provided for the
employees working over the project are: leave for the employees, overtime facilities, and extra
pay for the employees who would complete their target within an estimated time.
![Document Page](https://desklib.com/media/document/docfile/pages/construction-management-project-of-volca-tyw3/2024/09/27/8b210400-6b74-4829-a416-89dc8ee56994-page-7.webp)
6CONSTRUCTION MANAGEMENT PROJECT OF VOLCANO WORLD
Working time – The working time for the employees would be 8 hours a day, which
would initiate from 8 AM till 12:30 PM and 2 PM till 5:30 PM.
Labour histogram – The people who would be present on site during the project period
are: labours, project manager and contractors.
Accommodation and catering – The accommodation of materials needed for the project
would be kept at a certain safe side that would be protected from intruders. The catering for the
labours would be provided on a one-time basis, which would during the time of the day when
they would work on-site.
Training – A training session would be provided to the employees who would be
working within the park. This training would be essential for the workers in order to guide the
tourists who would visit the park to access the rides and other adventure courses.
Health and Safety – The committee within the park would arrange the health and safety
equipment that would be highly necessary to ensure that every tourist would be safe while they
would perform any ride.
Working time – The working time for the employees would be 8 hours a day, which
would initiate from 8 AM till 12:30 PM and 2 PM till 5:30 PM.
Labour histogram – The people who would be present on site during the project period
are: labours, project manager and contractors.
Accommodation and catering – The accommodation of materials needed for the project
would be kept at a certain safe side that would be protected from intruders. The catering for the
labours would be provided on a one-time basis, which would during the time of the day when
they would work on-site.
Training – A training session would be provided to the employees who would be
working within the park. This training would be essential for the workers in order to guide the
tourists who would visit the park to access the rides and other adventure courses.
Health and Safety – The committee within the park would arrange the health and safety
equipment that would be highly necessary to ensure that every tourist would be safe while they
would perform any ride.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
![Document Page](https://desklib.com/media/document/docfile/pages/construction-management-project-of-volca-tyw3/2024/09/27/f24d9742-9ea6-46cd-b79b-34153d7ed80a-page-8.webp)
7CONSTRUCTION MANAGEMENT PROJECT OF VOLCANO WORLD
5. Project Schedule Management
WBS
(Figure 1: The WBS for the project)
(Source: Created by author)
5. Project Schedule Management
WBS
(Figure 1: The WBS for the project)
(Source: Created by author)
![Document Page](https://desklib.com/media/document/docfile/pages/construction-management-project-of-volca-tyw3/2024/09/27/3b20c53d-39a1-48a2-907e-ed3e1291b31c-page-9.webp)
8CONSTRUCTION MANAGEMENT PROJECT OF VOLCANO WORLD
Work tasks
ID Outline
Number
Task
Mode
Task Name Duration Start Finish PredecessorsResource Names Cost
0 0 Development
Project of Volcano
World
389 days Mon 08-07-19 Thu 31-12-20 $497,040.00
1 1 Start Project 0 days Mon 08-07-19 Mon 08-07-19 $0.00
2 2 Initial planning
over Project'
38 days Mon 08-07-19 Wed 28-08-19 $22,400.00
3 2.1 Meeting with
the owners
6 days Mon 08-07-19 Mon 15-07-19 1 Project
manager
$9,600.00
4 2.2 Determing the
requirements
5 days Tue 16-07-19 Mon 22-07-19 3 Project
manager,Contractors
$12,800.00
5 2.3 Proposing the
plan for land
acquisition
5 days Tue 23-07-19 Mon 29-07-19 4 $0.00
6 2.4 Gaining land
acquisition
approval
10 days Tue 30-07-19 Mon 12-08-19 5 $0.00
7 2.5 Defining of a
project plan and
financial plan
12 days Tue 13-08-19 Wed 28-08-19 6 $0.00
8 3 Acquisition of
Resources
31 days Thu 29-08-19 Thu 10-10-19 $76,720.00
9 3.1 Preparing a
resource list
6 days Thu 29-08-19 Thu 05-09-19 7 Project
manager
$9,600.00
10 3.2 Deciding the
human
resources
7 days Fri 06-09-19 Mon 16-09-19 9 Project
manager
$11,200.00
11 3.3 Finalising the
contractors
5 days Fri 06-09-19 Thu 12-09-19 9 $0.00
12 3.4 Gathering the
materials
required
8 days Tue 17-09-19 Thu 26-09-19 10,11 Contractors,Labours,Project
manager,Materials[1]
$37,520.00
13 3.5 Preparing the
site
10 days Fri 27-09-19 Thu 10-10-19 12 Contractors,Labours $18,400.00
14 4 Implementation of
the Construction
Project
206 days Fri 11-10-19 Fri 24-07-20 $295,520.00
15 4.1 Boring of tunnels10 days Fri 11-10-19 Thu 24-10-19 13 Labours $8,800.00
16 4.2 Implementation
of the
construction
materials
17 days Fri 25-10-19 Mon 18-11-19 15 Contractors,Labours $31,280.00
17 4.3 Designing of
infrastructure
90 days Tue 19-11-19 Mon 23-03-20 16 Contractors,Labours $165,600.00
18 4.4 Designing
interior works
30 days Tue 24-03-20 Mon 04-05-20 17 Labours $26,400.00
19 4.5 Bringing of rides 12 days Tue 05-05-20 Wed 20-05-20 18 Contractors,Labours $22,080.00
20 4.6 Setting of rides
in proper places
47 days Thu 21-05-20 Fri 24-07-20 19 Labours $41,360.00
21 5 Finishing stage of
Project
114 days Mon 27-07-20 Thu 31-12-20 $102,400.00
22 5.1 Final quality
checking
80 days Mon 27-07-20 Fri 13-11-20 20 Trainers $51,200.00
23 5.2 Preparing the
documentation
plan
30 days Mon 16-11-20 Fri 25-12-20 22 Project
manager
$48,000.00
24 5.3 Making of final
payments
2 days Mon 28-12-20 Tue 29-12-20 23 Project
manager
$3,200.00
25 5.4 Project Sign-off 2 days Wed 30-12-20 Thu 31-12-20 24 $0.00
26 6 End Project 0 days Thu 31-12-20 Thu 31-12-20 25 $0.00
08-07
Project manager
Project manager,Contractors
Project manager
Project manager
Contractors,Labours,Project manager,Materials[1]
Contractors,Labours
Labours
Contractors,Labours
Contractors,Labours
Labours
Contractors,Labours
Labours
Trainers
Project manager
Project manager
31-12
F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T
30 Jun '19 28 Jul '19 25 Aug '19 22 Sep '19 20 Oct '19 17 Nov '19 15 Dec '19 12 Jan '20 09 Feb '20 08 Mar '20 05 Apr '20 03 May '20 31 May '20 28 Jun '20 26 Jul '20 23 Aug '20 20 Sep '20 18 Oct '20 15 Nov '20 13 Dec '20 10 Jan '21
(Figure 2: The Schedule for the project)
(Source: Created by author)
Work tasks
ID Outline
Number
Task
Mode
Task Name Duration Start Finish PredecessorsResource Names Cost
0 0 Development
Project of Volcano
World
389 days Mon 08-07-19 Thu 31-12-20 $497,040.00
1 1 Start Project 0 days Mon 08-07-19 Mon 08-07-19 $0.00
2 2 Initial planning
over Project'
38 days Mon 08-07-19 Wed 28-08-19 $22,400.00
3 2.1 Meeting with
the owners
6 days Mon 08-07-19 Mon 15-07-19 1 Project
manager
$9,600.00
4 2.2 Determing the
requirements
5 days Tue 16-07-19 Mon 22-07-19 3 Project
manager,Contractors
$12,800.00
5 2.3 Proposing the
plan for land
acquisition
5 days Tue 23-07-19 Mon 29-07-19 4 $0.00
6 2.4 Gaining land
acquisition
approval
10 days Tue 30-07-19 Mon 12-08-19 5 $0.00
7 2.5 Defining of a
project plan and
financial plan
12 days Tue 13-08-19 Wed 28-08-19 6 $0.00
8 3 Acquisition of
Resources
31 days Thu 29-08-19 Thu 10-10-19 $76,720.00
9 3.1 Preparing a
resource list
6 days Thu 29-08-19 Thu 05-09-19 7 Project
manager
$9,600.00
10 3.2 Deciding the
human
resources
7 days Fri 06-09-19 Mon 16-09-19 9 Project
manager
$11,200.00
11 3.3 Finalising the
contractors
5 days Fri 06-09-19 Thu 12-09-19 9 $0.00
12 3.4 Gathering the
materials
required
8 days Tue 17-09-19 Thu 26-09-19 10,11 Contractors,Labours,Project
manager,Materials[1]
$37,520.00
13 3.5 Preparing the
site
10 days Fri 27-09-19 Thu 10-10-19 12 Contractors,Labours $18,400.00
14 4 Implementation of
the Construction
Project
206 days Fri 11-10-19 Fri 24-07-20 $295,520.00
15 4.1 Boring of tunnels10 days Fri 11-10-19 Thu 24-10-19 13 Labours $8,800.00
16 4.2 Implementation
of the
construction
materials
17 days Fri 25-10-19 Mon 18-11-19 15 Contractors,Labours $31,280.00
17 4.3 Designing of
infrastructure
90 days Tue 19-11-19 Mon 23-03-20 16 Contractors,Labours $165,600.00
18 4.4 Designing
interior works
30 days Tue 24-03-20 Mon 04-05-20 17 Labours $26,400.00
19 4.5 Bringing of rides 12 days Tue 05-05-20 Wed 20-05-20 18 Contractors,Labours $22,080.00
20 4.6 Setting of rides
in proper places
47 days Thu 21-05-20 Fri 24-07-20 19 Labours $41,360.00
21 5 Finishing stage of
Project
114 days Mon 27-07-20 Thu 31-12-20 $102,400.00
22 5.1 Final quality
checking
80 days Mon 27-07-20 Fri 13-11-20 20 Trainers $51,200.00
23 5.2 Preparing the
documentation
plan
30 days Mon 16-11-20 Fri 25-12-20 22 Project
manager
$48,000.00
24 5.3 Making of final
payments
2 days Mon 28-12-20 Tue 29-12-20 23 Project
manager
$3,200.00
25 5.4 Project Sign-off 2 days Wed 30-12-20 Thu 31-12-20 24 $0.00
26 6 End Project 0 days Thu 31-12-20 Thu 31-12-20 25 $0.00
08-07
Project manager
Project manager,Contractors
Project manager
Project manager
Contractors,Labours,Project manager,Materials[1]
Contractors,Labours
Labours
Contractors,Labours
Contractors,Labours
Labours
Contractors,Labours
Labours
Trainers
Project manager
Project manager
31-12
F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T
30 Jun '19 28 Jul '19 25 Aug '19 22 Sep '19 20 Oct '19 17 Nov '19 15 Dec '19 12 Jan '20 09 Feb '20 08 Mar '20 05 Apr '20 03 May '20 31 May '20 28 Jun '20 26 Jul '20 23 Aug '20 20 Sep '20 18 Oct '20 15 Nov '20 13 Dec '20 10 Jan '21
(Figure 2: The Schedule for the project)
(Source: Created by author)
![Document Page](https://desklib.com/media/document/docfile/pages/construction-management-project-of-volca-tyw3/2024/09/27/8aad2e27-38f5-4db2-9102-fcd22872bcd6-page-10.webp)
9CONSTRUCTION MANAGEMENT PROJECT OF VOLCANO WORLD
PERT Chart
(Figure 3: The PERT chart for the Project)
(Source: Created by author)
6. Project Communication Management
Project management – The designers of the work would design a 3D model of the park
in order to gain a proper form of approval from the UNHCR. They would also maintain a proper
documentation in order to note the specific areas and sections that would be included within the
plan.
Communication Protocols – Any form of communication that would be maintained
within the project would be managed on an external and internal basis. The internal
communication would be maintained by face-to-face communication, documentation and
distributing pamphlets. The external communication would be maintained with the help of
emails and video calling.
PERT Chart
(Figure 3: The PERT chart for the Project)
(Source: Created by author)
6. Project Communication Management
Project management – The designers of the work would design a 3D model of the park
in order to gain a proper form of approval from the UNHCR. They would also maintain a proper
documentation in order to note the specific areas and sections that would be included within the
plan.
Communication Protocols – Any form of communication that would be maintained
within the project would be managed on an external and internal basis. The internal
communication would be maintained by face-to-face communication, documentation and
distributing pamphlets. The external communication would be maintained with the help of
emails and video calling.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
![Document Page](https://desklib.com/media/document/docfile/pages/construction-management-project-of-volca-tyw3/2024/09/27/5fd7d5f5-f6b4-40c9-94db-9d673fbf3b97-page-11.webp)
10CONSTRUCTION MANAGEMENT PROJECT OF VOLCANO WORLD
7. Project Cost Management
Task Name Cost
Development Project of Volcano World $497,040.00
Start Project $0.00
Initial planning over Project' $22,400.00
Acquisition of Resources $76,720.00
Implementation of the Construction Project $295,520.00
Finishing stage of Project $102,400.00
End Project $0.00
8. Project Procurement Management
Supply chain management – The requirements of the supplies that need to be made
within the park would be maintained by the SCM team.
Contracts – The contract would be provided by the UNHCR, which is the governing
body for the project.
Sustainable procurement practices – Different practices of procurement of the items
would be managed by the project team. The materials required for procurement would be
managed on an earlier basis.
Material supplies – The materials that would be required by the project team would be
managed by the UNHCR. They would make the arrangements of the materials as they would
near their completion.
7. Project Cost Management
Task Name Cost
Development Project of Volcano World $497,040.00
Start Project $0.00
Initial planning over Project' $22,400.00
Acquisition of Resources $76,720.00
Implementation of the Construction Project $295,520.00
Finishing stage of Project $102,400.00
End Project $0.00
8. Project Procurement Management
Supply chain management – The requirements of the supplies that need to be made
within the park would be maintained by the SCM team.
Contracts – The contract would be provided by the UNHCR, which is the governing
body for the project.
Sustainable procurement practices – Different practices of procurement of the items
would be managed by the project team. The materials required for procurement would be
managed on an earlier basis.
Material supplies – The materials that would be required by the project team would be
managed by the UNHCR. They would make the arrangements of the materials as they would
near their completion.
![Document Page](https://desklib.com/media/document/docfile/pages/construction-management-project-of-volca-tyw3/2024/09/27/ca3893aa-1d88-40e6-bea1-ce8ab2109458-page-12.webp)
11CONSTRUCTION MANAGEMENT PROJECT OF VOLCANO WORLD
Warranties – The project would be covered under a certain warranty.
Materials handling and storage – The materials would be handled and stored by the
project team. They would be stored under a warehouse from where the supplies would be
provided to the labours.
Tools and work gear – The work gear would be provided to each of the labours during
the performing of the task. The tools for safety and work would be provided to them prior to
their start of the work.
9. Project Risk Management
The different risks approachable towards the project would be managed by the project
manager. They would manage each of the aspects in relation to the project. Each of the risks that
approach towards the project would be properly assessed and evaluated by the project manager.
10. Project Stakeholder Management
11. Project Environmental Management
Environmental Protocols – Different protocols based on protection of the environment
would be implemented during the construction work over the project.
SWOT analysis – Strengths – The strengths of the project is that it would open a new
business venture for UNHCR.
Weakness – The project does not provide an advertisement plan, which restricts the
access of people to the site.
Opportunities – The UNHCR would have a huge opportunity to attract people and thus
increase the business revenue.
Warranties – The project would be covered under a certain warranty.
Materials handling and storage – The materials would be handled and stored by the
project team. They would be stored under a warehouse from where the supplies would be
provided to the labours.
Tools and work gear – The work gear would be provided to each of the labours during
the performing of the task. The tools for safety and work would be provided to them prior to
their start of the work.
9. Project Risk Management
The different risks approachable towards the project would be managed by the project
manager. They would manage each of the aspects in relation to the project. Each of the risks that
approach towards the project would be properly assessed and evaluated by the project manager.
10. Project Stakeholder Management
11. Project Environmental Management
Environmental Protocols – Different protocols based on protection of the environment
would be implemented during the construction work over the project.
SWOT analysis – Strengths – The strengths of the project is that it would open a new
business venture for UNHCR.
Weakness – The project does not provide an advertisement plan, which restricts the
access of people to the site.
Opportunities – The UNHCR would have a huge opportunity to attract people and thus
increase the business revenue.
![Document Page](https://desklib.com/media/document/docfile/pages/construction-management-project-of-volca-tyw3/2024/09/27/4ab2d613-078b-4bf7-a829-61519c9178d4-page-13.webp)
12CONSTRUCTION MANAGEMENT PROJECT OF VOLCANO WORLD
Threats – Different other recreational park that would imply other form of world class
facilities could impose a major threat for the Volcano World.
Material waste management and recycling – Different policies would be followed by
the management in order to recycle the items that would be produced as waste in the park.
Pollution and erosion control – Activities would be imposed by the management in
order to impose pollution free environment within the park during the period of construction.
Clean up – The clean-up of wastes would be done by the authorities of the park after the
entire construction have been completed.
Threats – Different other recreational park that would imply other form of world class
facilities could impose a major threat for the Volcano World.
Material waste management and recycling – Different policies would be followed by
the management in order to recycle the items that would be produced as waste in the park.
Pollution and erosion control – Activities would be imposed by the management in
order to impose pollution free environment within the park during the period of construction.
Clean up – The clean-up of wastes would be done by the authorities of the park after the
entire construction have been completed.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
![Document Page](https://desklib.com/media/document/docfile/pages/construction-management-project-of-volca-tyw3/2024/09/27/b3f9109d-b812-4408-a9b1-7a31ec4a0d70-page-14.webp)
13CONSTRUCTION MANAGEMENT PROJECT OF VOLCANO WORLD
Bibliography
Conforto, E.C., Salum, F., Amaral, D.C., Da Silva, S.L. and De Almeida, L.F.M., 2014. Can
agile project management be adopted by industries other than software development?. Project
Management Journal, 45(3), pp.21-34.
Eskerod, P. and Jepsen, A.L., 2016. Project stakeholder management. Routledge.
Fewings, P. and Henjewele, C., 2019. Construction project management: an integrated
approach. Routledge.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management.
Project Management Institute.
Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach.
Routledge.
Heagney, J., 2016. Fundamentals of project management. Amacom.
Heizer, J., Render, B. and Munson, C., 2017. Operations management. Pearson Education
Limited.
Hornstein, H.A., 2015. The integration of project management and organizational change
management is now a necessity. International Journal of Project Management, 33(2), pp.291-
298.
Kerzner, H., 2019. Using the project management maturity model: strategic planning for project
management. Wiley.
Bibliography
Conforto, E.C., Salum, F., Amaral, D.C., Da Silva, S.L. and De Almeida, L.F.M., 2014. Can
agile project management be adopted by industries other than software development?. Project
Management Journal, 45(3), pp.21-34.
Eskerod, P. and Jepsen, A.L., 2016. Project stakeholder management. Routledge.
Fewings, P. and Henjewele, C., 2019. Construction project management: an integrated
approach. Routledge.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management.
Project Management Institute.
Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach.
Routledge.
Heagney, J., 2016. Fundamentals of project management. Amacom.
Heizer, J., Render, B. and Munson, C., 2017. Operations management. Pearson Education
Limited.
Hornstein, H.A., 2015. The integration of project management and organizational change
management is now a necessity. International Journal of Project Management, 33(2), pp.291-
298.
Kerzner, H., 2019. Using the project management maturity model: strategic planning for project
management. Wiley.
![Document Page](https://desklib.com/media/document/docfile/pages/construction-management-project-of-volca-tyw3/2024/09/27/2f871207-a1d7-411a-8d8e-68594a0e2b91-page-15.webp)
14CONSTRUCTION MANAGEMENT PROJECT OF VOLCANO WORLD
Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A.M.E. and Villanueva, P., 2014. Project
risk management methodology for small firms. International journal of project
management, 32(2), pp.327-340.
Meredith, J.R., Mantel Jr, S.J. and Shafer, S.M., 2017. Project management: a managerial
approach. John Wiley & Sons.
Špundak, M., 2014. Mixed agile/traditional project management methodology–reality or
illusion?. Procedia-Social and Behavioral Sciences, 119, pp.939-948.
Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A.M.E. and Villanueva, P., 2014. Project
risk management methodology for small firms. International journal of project
management, 32(2), pp.327-340.
Meredith, J.R., Mantel Jr, S.J. and Shafer, S.M., 2017. Project management: a managerial
approach. John Wiley & Sons.
Špundak, M., 2014. Mixed agile/traditional project management methodology–reality or
illusion?. Procedia-Social and Behavioral Sciences, 119, pp.939-948.
1 out of 15
Related Documents
![[object Object]](/_next/image/?url=%2F_next%2Fstatic%2Fmedia%2Flogo.6d15ce61.png&w=640&q=75)
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.