logo

Construction Management: Project Information, Planned Data, and Actual Data Analysis

   

Added on  2023-03-31

35 Pages5380 Words76 Views
 | 
 | 
 | 
Construction management
Student name
Institution affiliation
Construction Management: Project Information, Planned Data, and Actual Data Analysis_1

Contents
Q1. Project Information...................................................................................................................3
1.1 introduction...........................................................................................................................3
1.2 project information table............................................................................................................3
Q2. Project planned data..................................................................................................................3
2.1 analyzed approaches..............................................................................................................3
2.2 project planned data table.................................................................................................5
2.3 Appendix................................................................................................................................5
Q3: Analyze Actual Data.................................................................................................................7
3.1 Analyzing industry approaches.............................................................................................7
3.2 Project Actual Data Table......................................................................................................8
3.3 Appendices.............................................................................................................................8
Figure 1 work breakdown structure, clear copy in excel.................................................................6
Figure 2 cost pre estimates..............................................................................................................8
Figure 3 costs overview, the graph was drawn based on data from the contractor, refer to MS file
for clear copy...................................................................................................................................8
Figure 5 costs overview.................................................................................................................23
Table 1 activity schedule, cost, start, finish date, percentage, milestone, costs time and
dependencies in the project..............................................................................................................8
Table 2 cash flow forecasting........................................................................................................21
Construction Management: Project Information, Planned Data, and Actual Data Analysis_2

Q1. Project Information
1.1 introduction
The project is a bus repair facility . it sits on a site with average gross area of 2400 square metre.
The project is located at wellington city. The plans for the site have been attached in appendix A.
The following requirements, sketches and descriptions should be given in order to
complete a thorough review of the building plan.
1. Architectural plans
2. Structural plans
3. Site plan
4. Material description of all the works to be done
The above requirements should satisfy all the building codes, complete,
authenticated by relevant bodies or engineers, and should be sealed.
Review of site plan
Figure 1 site plan review
Construction Management: Project Information, Planned Data, and Actual Data Analysis_3

Scale and location of all new buildings and all current site structures have been
provided. Lot rows lengths given . The street grades have been developed and the
grades proposed.
A licensed architect, landscape architect, builder, surveyor or designer shall seal the
drawings in respect of their expertise The plans of the site must be drawn to the engineer’s scale as shown on project
plan. Elevations and heights of the building can be built to the level of the architect. The person or company responsible for the preparation of the letter, name,
telephone and fax numbers, and contact information must be included in site
plan. North arrow, distance, date. Devolution name(s) in the title block, on the cover sheet, and each after sheet, if
necessary, national identity numbers. Data on land, including an adjacent map, legal description and, where
applicable, general description of deed limitations provided.
Review of architectural plans
The plan of the architectural floor determines the planned configuration of the
workspace. The plan shows circulation routes to and within the egress space and paths.
Indicate all existing and new partitions and doors, built in case work, furniture, monitors
and permanent floor space equipment: caps, tanks, chemical storage cases. Indicate all
old, new and existing partitions and doors.
It should Specify which items (where applicable) are to be accessible such as labs,
kitchens, etc.
Figure 2 first floor plan snapshot, from CIC architectural plans provided
a. Building style proposed for the house
Construction Management: Project Information, Planned Data, and Actual Data Analysis_4

b. Suitable information and sizes for determining exit modes, including floor loads,
exit design and sizes, halls, gates have been provided
c. Evacuation signs / means, have not been indicated on this plan
d. Description and uses for all areas of the building and the proposed group(s). The
definition of mixed applications (as applicable) have been provided
e. Fully sized drawings to define areas and the height of the house provided.
f. Provisions of access.
g. Definition and descriptions of special arrangements planned, such as a mall
elevated, high-rise, mezzanine, atrium, public garage, etc.
h. Sufficient information, with data that support required scores, to determine fire
resistive construction specifications.
i. Plastic measurements, reinforcement and installation of safety glazing.
j. Fire protection systems information needed
1.2 project information table
Title Description
Project type Construction of bus repair facility
Location Wellington city
Gross floor Area Structure 9009 sq metre, 3500 sq. metre
site area
Number of stories 2 story
Contract type One time
Project team roles and responsibilities Managing, execution planning and
controlling processes in the contract
Q2. Project planned data
The contractor gave some insights on the approaches utilized in controlling and managing the
project. This have been discussed in the subtopics below.
Construction Management: Project Information, Planned Data, and Actual Data Analysis_5

The Building Manager is responsible for supervising the design from beginning to end.
Depending on the project size and complexities, they can individually manage or
collaborate with other building managers. We prepare, budget and supervise
development. It is the responsibility. We will have to determine during the planning
process what resources to use, how to assign staff and build a project schedule. You
have to interact regularly with everyone else on the plan and the customer. They are
always on-call, as if anything goes wrong with the plan, it is their duty. Because of the
variety of jobs in a construction manager, a number of people have advantages in
implementing cloud-based software that helps them prepare, execute and connect from
start to finish.
The following list of activities summarizes the main tasks to be done ins constructing
the building and its surrounding.
Processing of land acquisition, holding, or land and upgrading.
Studies in planning and feasibilities.
Engineering and architectural design.
Building, including construction materials, machinery, and labour.
Financing of construction.
Land insurance and taxes
Owner's general office overhead
Not included in construction equipment and furnishings.
Testing and inspection.
2.1 analyzed approaches
a. planning
In order to support project planning and implementation, the contractor developed participatory
approaches in the project planning . The objective was to create better and sustainable projects
which apply suitable methods to address real problems, especially from a beneficiary or right-
holder perspective in projects based on client’s goals. These strategies also lead to monitoring
and analysis during the project planning process.
The planning approach was based on appreciative inquiry. Based on client’s initiative, resources
and achievements. The objective is to increase the client’s self-esteem and initiative, and
eventually to enhance contractor’s capacity . The clients approach included 4 stages listed below
definition,
hypothesis,
Construction Management: Project Information, Planned Data, and Actual Data Analysis_6

design and
destiny
b. budgeting
The project budget was derived using an analogous approach. The contractor had done a similar
project for another client. This made the project budgeting easier.
c. project estimation.
Despite the budgeting, project costs were estimated by the quantity surveyor. The plans of the
proposed structure were used to estimate the project costing and time.
d. project scheduling
Project scheduling is a method for communicating the activities to be carried out and the
administrative resources that are allocated in which time. A project plan is a file that contains
everything needed in time to deliver the project.
The following approaches were used to schedule the project
1. Gant chart - Also known as bar charts are Gantt charts. Activities are shown as bars and
the operation period is the width of each bar. The start date of the bar is indicated and the
end date of the bar is indicated. Both bars can be run sequentially or concurrently
depending on the project execution plan and availability of resources. Gantt Charts can
therefore be easy to understand and manage projects by project management teams and
stakeholders.
2. Pert diagram
Based on the data and information provided by the client, a Ms project document with the
detailed schedule was generated.
e. cash flow forecasting
Microsoft project was utilised in producing a cash forecast. This has been remodelled and
provided in the appendices
2.2 project planned data table
Title description
Project planned duration 200 days
Estimated budget $300000
Milestones Milestones have been remodeled and
provided in Ms project file
Activities with duration Each activities duration not provided, the
actual data has beeeen used to remodel in
ms project
Interdependencies Project predecessors provided in ms file
Construction Management: Project Information, Planned Data, and Actual Data Analysis_7

The contractor did not provide Project first baseline planning file (Microsoft Project) with all
planned data (Resources and budge ) , based on the data provided, a copy with the above data
was modelled.
2.3 Appendix
WORK BREAKDOWN STRUCTURE FOR BUS REPAIR CONSTRUCTION PROJECT
Bus Repair Facility COMPANY NAME
PROJECT MANAGER 5-Oct-19
s
COMPLETION
Bus repair fac ility Construc tion Projet
Project idealization (2000)
project
specific ations
and definition
Develop project
management tool
contractors tendering ($2000) Actual C onstruction ($ 60000) Project C lose/ Post Project ( $ 2000 )
all drawings-
arc hitec turals,
structural and civil
approved ( $1000)
sc heduling works
project activity
c hec klist
short brief,
business
implic ations
c ost olan, project
plan generation
submit results
site c leaners (
asbestos, bushes
and remaining
earthworks )
provision of
c omplete detailed
drawings
c hoose tenderes -
mechanical works,
c ivil works,
electric al works
End reports
Switc h off heat
Certify all areas
c lear
Contractor
mobilization
supply of
c onstruc tion
absetos removed,
soils aproved and
c onstruc tion works
starts
surveying,
foundation works -
earthworks, slabs
superstructure
c onstruc tion-
walls,structural
c omponets,buildin
all finishes
Assessthe
deliverables
Project report
Award of
c ertific ate of
c ompletion
Contractor
demobilization
Figure 3 work breakdown structure, clear copy in excel
Construction Management: Project Information, Planned Data, and Actual Data Analysis_8

End of preview

Want to access all the pages? Upload your documents or become a member.