Running Head: CONSTRUCTION MANAGEMENT Construction Management Name of the Student Name of the University
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1CONSTRUCTION MANAGEMENT Task 3 Resources Required: Resource NameType Max. Units Std. RateOvt. RateCost/UseAccrue At Base Calendar Construction Manager Work100%$200.00/hr$0.00/hr$0.00ProratedStandard Construction Supervisor Work100%$150.00/hr$0.00/hr$0.00ProratedStandard Externaland Internal Works Supervisor Work100%$125.00/hr$0.00/hr$0.00ProratedStandard LaborerMaterial$25.00$0.00Prorated Building Materials Material$15,000.00$0.00Prorated BulldozerWork100%$15.00/hr$0.00/hr$0.00ProratedStandard CraneWork100%$12.00/hr$0.00/hr$0.00ProratedStandard Concrete MixerWork100%$8.00/hr$0.00/hr$0.00ProratedStandard
2CONSTRUCTION MANAGEMENT Other CostsMaterial$15,000.00$0.00Prorated Resource Allocation and Durations: Task Name Duratio n StartFinish Predecessor s Resource NamesCost Constructio nWork Project 200 days Mon 6/11/18 Fri 3/15/19 $475,443.0 0 Site Preparation 25 days Mon 6/11/18 Fri 7/13/18 $3,500.00 Clearing of the Site 5 days Mon 6/11/18 Fri 6/15/18 Bulldozer, Labourer [5]$725.00 Flatten the Site 10 days Mon 6/18/18 Fri 6/29/18 2Bulldozer, Labourer [5]$1,325.00 Remove grassand plantsfrom the land 5 days Mon 7/2/18 Fri 7/6/18 3Bulldozer, Labourer [5]$725.00 Add soil for increasing 5 daysMonFri4Bulldozer, Labourer [5]$725.00
3CONSTRUCTION MANAGEMENT site strength7/9/187/13/18 Foundatio n 40 days Mon 7/16/18 Fri 9/7/18 $155,875.0 0 Excavatio n of the Site 15 days Mon 7/16/18 Fri 8/3/18 5 BuildingMaterials [1],ConstructionManager, ConstructionSupervisor, Labourer [5] $57,125.00 Preparati onof Foundation 5 days Mon 8/6/18 Fri 8/10/18 7 ConstructionManager, ConstructionSupervisor, Labourer [5] $14,125.00 Placemen tof Foundation Slabs 10 days Mon 8/13/18 Fri 8/24/18 8 ConstructionManager, ConstructionSupervisor, Labourer [5] $28,125.00 Install Footings 10 days Mon 8/13/18 Fri 8/24/18 8 ConstructionManager, ConstructionSupervisor, Labourer [ 5] $28,125.00 Apply Concrete 5 days Mon 8/27/18 Fri 8/31/18 9,10 ConstructionManager, ConstructionSupervisor, Labourer [5] $14,125.00
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
4CONSTRUCTION MANAGEMENT Complete Foundation 2 days Mon 9/3/18 Tue 9/4/18 11 ConstructionManager, ConstructionSupervisor, Labourer [5] $5,725.00 Fill the Empty Spaceswith Soil 3 days Wed 9/5/18 Fri 9/7/18 12 ConstructionManager, ConstructionSupervisor, Labourer [5] $8,525.00 Structure95 days Mon 9/10/18 Fri 1/18/19 $204,443.0 0 Start Buildingthe Structure 2 days Mon 9/10/18 Tue 9/11/18 13 BuildingMaterials [1],ConstructionManager, ConstructionSupervisor, Labourer [15] $20,975.00 Develop the Structural Framework 48 days Wed 9/12/18 Fri 11/16/1 8 15 ConstructionManager, ConstructionSupervisor, Labourer [15],Crane $139,383.0 0 Install Bricks 15 days Mon 11/19/1 8 Fri 12/7/18 16 ConstructionManager, ConstructionSupervisor, Labourer [15] $42,375.00 Apply Concrete 15 daysMon 12/10/1 Fri 12/28/1 17Concrete Mixer, Labourer$1,335.00
6CONSTRUCTION MANAGEMENT [1] External Finishes 15 days Mon 1/21/19 Fri 2/8/19 $15,375.00 Dry the Plaster 5 days Mon 1/21/19 Fri 1/25/19 19 ExternalandInternal WorksSupervisor, Labourer [5] $5,125.00 Apply Coloron Walls 5 days Mon 1/28/19 Fri 2/1/19 26 ExternalandInternal WorksSupervisor, Labourer [5] $5,125.00 Add Designsif Necessary 5 days Mon 2/4/19 Fri 2/8/19 27 ExternalandInternal WorksSupervisor, Labourer [5] $5,125.00 External Works 25 days Mon 2/11/19 Fri 3/15/19 $30,750.00 Connect Draining Systemwith Water Tanks 5 days Mon 2/11/19 Fri 2/15/19 24,28 Labourer [10], Other Costs [1] $15,250.00 Connect electrical 5 daysMonFri30Labourer [10]$250.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
7CONSTRUCTION MANAGEMENT wiringswith main line 2/18/192/22/19 Finishing Works 15 days Mon 2/25/19 Fri 3/15/19 31 Labourer [10], Other Costs [1] $15,250.00 Assumptions: It has been assumed that the estimated rates for the resources are standard and feasible for the project. It has been assumed that the number of resources like laborers, materials and others. The dependencies of activities are assumed to be accurate and feasible for the project.