Running head: PROJECT MANAGEMENT
Case Study- Construction of barbeque in Australia
Name of the Student
Name of the University
Author’s Note
Case Study- Construction of barbeque in Australia
Name of the Student
Name of the University
Author’s Note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1
PROJECT MANAGEMENT
Table of Contents
1. Project Planning...........................................................................................................................2
2. Monitoring and Control of Project.............................................................................................4
3. Quality Management..................................................................................................................5
4. Estimation of project...................................................................................................................6
5. Risk management.........................................................................................................................8
6. Project organization.....................................................................................................................9
7. Contracts......................................................................................................................................9
8. WBS...........................................................................................................................................10
9. Triple Constraints......................................................................................................................10
Bibliography..................................................................................................................................12
PROJECT MANAGEMENT
Table of Contents
1. Project Planning...........................................................................................................................2
2. Monitoring and Control of Project.............................................................................................4
3. Quality Management..................................................................................................................5
4. Estimation of project...................................................................................................................6
5. Risk management.........................................................................................................................8
6. Project organization.....................................................................................................................9
7. Contracts......................................................................................................................................9
8. WBS...........................................................................................................................................10
9. Triple Constraints......................................................................................................................10
Bibliography..................................................................................................................................12
2
PROJECT MANAGEMENT
1. Project Planning
The paper reflects on the construction of barbeque in Australia. The table below reflects
the activities that are planned in order to execute the project successfully within the estimated
time.
Task Name Duration Start Finish
Construction of barbeque restaurant in
Australia
368 days Mon 10/30/17 Wed 3/27/19
Project planning 47 days Mon 10/30/17 Tue 1/2/18
Requirement analysis 6 days Mon 10/30/17 Mon 11/6/17
Project nature analysis 5 days Tue 11/7/17 Mon 11/13/17
Estimation of resource 4 days Tue 11/14/17 Fri 11/17/17
Time schedule estimation 5 days Mon 11/20/17 Fri 11/24/17
Estimation of budget 10 days Mon 11/27/17 Fri 12/8/17
Estimation of manpower 8 days Mon 12/11/17 Wed 12/20/17
Analysis of resources 9 days Thu 12/21/17 Tue 1/2/18
Project planning completion phase 0 days Tue 1/2/18 Tue 1/2/18
Initiation phase 105 days Wed 1/3/18 Tue 5/29/18
Procurement of fund 7 days Wed 1/3/18 Thu 1/11/18
Appointment of stakeholders 8 days Fri 1/12/18 Tue 1/23/18
Arrangement of meetings 6 days Wed 1/24/18 Wed 1/31/18
Arrangement of financial plan 9 days Thu 2/1/18 Tue 2/13/18
PROJECT MANAGEMENT
1. Project Planning
The paper reflects on the construction of barbeque in Australia. The table below reflects
the activities that are planned in order to execute the project successfully within the estimated
time.
Task Name Duration Start Finish
Construction of barbeque restaurant in
Australia
368 days Mon 10/30/17 Wed 3/27/19
Project planning 47 days Mon 10/30/17 Tue 1/2/18
Requirement analysis 6 days Mon 10/30/17 Mon 11/6/17
Project nature analysis 5 days Tue 11/7/17 Mon 11/13/17
Estimation of resource 4 days Tue 11/14/17 Fri 11/17/17
Time schedule estimation 5 days Mon 11/20/17 Fri 11/24/17
Estimation of budget 10 days Mon 11/27/17 Fri 12/8/17
Estimation of manpower 8 days Mon 12/11/17 Wed 12/20/17
Analysis of resources 9 days Thu 12/21/17 Tue 1/2/18
Project planning completion phase 0 days Tue 1/2/18 Tue 1/2/18
Initiation phase 105 days Wed 1/3/18 Tue 5/29/18
Procurement of fund 7 days Wed 1/3/18 Thu 1/11/18
Appointment of stakeholders 8 days Fri 1/12/18 Tue 1/23/18
Arrangement of meetings 6 days Wed 1/24/18 Wed 1/31/18
Arrangement of financial plan 9 days Thu 2/1/18 Tue 2/13/18
3
PROJECT MANAGEMENT
Appointment of workers 8 days Wed 2/14/18 Fri 2/23/18
Preparation of blueprint 7 days Mon 2/26/18 Tue 3/6/18
Procurement of land area 5 days Wed 3/7/18 Tue 3/13/18
Release of legal notice 7 days Wed 3/14/18 Thu 3/22/18
Budget allocation 9 days Fri 3/23/18 Wed 4/4/18
Resource procurement 8 days Thu 4/5/18 Mon 4/16/18
Division of time 7 days Tue 4/17/18 Wed 4/25/18
Duty allocation 8 days Thu 4/26/18 Mon 5/7/18
Analysis of risk 9 days Tue 5/8/18 Fri 5/18/18
Risk mitigation plan 7 days Mon 5/21/18 Tue 5/29/18
Completion of project initiation 0 days Tue 5/29/18 Tue 5/29/18
Execution phase 178 days Wed 5/30/18 Fri 2/1/19
Land area preparation 12 days Wed 5/30/18 Thu 6/14/18
Assortment of resources 13 days Fri 6/15/18 Tue 7/3/18
Construction of restaurant 9 days Wed 7/4/18 Mon 7/16/18
Framework construction of restaurant 10 days Tue 7/17/18 Mon 7/30/18
Selection of entry and exit spaces 11 days Tue 7/31/18 Tue 8/14/18
Application of bricks 14 days Wed 8/15/18 Mon 9/3/18
Plumbing 12 days Tue 9/4/18 Wed 9/19/18
Installation of electric circuit 13 days Thu 9/20/18 Mon 10/8/18
Concrete application 15 days Tue 10/9/18 Mon 10/29/18
PROJECT MANAGEMENT
Appointment of workers 8 days Wed 2/14/18 Fri 2/23/18
Preparation of blueprint 7 days Mon 2/26/18 Tue 3/6/18
Procurement of land area 5 days Wed 3/7/18 Tue 3/13/18
Release of legal notice 7 days Wed 3/14/18 Thu 3/22/18
Budget allocation 9 days Fri 3/23/18 Wed 4/4/18
Resource procurement 8 days Thu 4/5/18 Mon 4/16/18
Division of time 7 days Tue 4/17/18 Wed 4/25/18
Duty allocation 8 days Thu 4/26/18 Mon 5/7/18
Analysis of risk 9 days Tue 5/8/18 Fri 5/18/18
Risk mitigation plan 7 days Mon 5/21/18 Tue 5/29/18
Completion of project initiation 0 days Tue 5/29/18 Tue 5/29/18
Execution phase 178 days Wed 5/30/18 Fri 2/1/19
Land area preparation 12 days Wed 5/30/18 Thu 6/14/18
Assortment of resources 13 days Fri 6/15/18 Tue 7/3/18
Construction of restaurant 9 days Wed 7/4/18 Mon 7/16/18
Framework construction of restaurant 10 days Tue 7/17/18 Mon 7/30/18
Selection of entry and exit spaces 11 days Tue 7/31/18 Tue 8/14/18
Application of bricks 14 days Wed 8/15/18 Mon 9/3/18
Plumbing 12 days Tue 9/4/18 Wed 9/19/18
Installation of electric circuit 13 days Thu 9/20/18 Mon 10/8/18
Concrete application 15 days Tue 10/9/18 Mon 10/29/18
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
4
PROJECT MANAGEMENT
Application of color 11 days Tue 10/30/18 Tue 11/13/18
Implementation of system 10 days Wed 11/14/18 Tue 11/27/18
Application of tiles 9 days Wed 11/28/18 Mon 12/10/18
Film processing implementation 15 days Tue 12/11/18 Mon 12/31/18
Dining room construction 13 days Tue 1/1/19 Thu 1/17/19
Central heating zones construction 11 days Fri 1/18/19 Fri 2/1/19
Project execution completion 0 days Fri 2/1/19 Fri 2/1/19
Development phase 35 days Mon 2/4/19 Fri 3/22/19
Restaurant board formation 8 days Mon 2/4/19 Wed 2/13/19
Preparation of statement vision 7 days Thu 2/14/19 Fri 2/22/19
Preparation of standard service 9 days Mon 2/25/19 Thu 3/7/19
Parking a lot implementation 6 days Fri 3/8/19 Fri 3/15/19
Finalization 5 days Mon 3/18/19 Fri 3/22/19
Development phase completion 0 days Fri 3/22/19 Fri 3/22/19
Closure phase 3 days Mon 3/25/19 Wed 3/27/19
Sign off stakeholder 2 days Mon 3/25/19 Tue 3/26/19
Review of post project 1 day Wed 3/27/19 Wed 3/27/19
Completion of project closure phase 0 days Wed 3/27/19 Wed 3/27/19
PROJECT MANAGEMENT
Application of color 11 days Tue 10/30/18 Tue 11/13/18
Implementation of system 10 days Wed 11/14/18 Tue 11/27/18
Application of tiles 9 days Wed 11/28/18 Mon 12/10/18
Film processing implementation 15 days Tue 12/11/18 Mon 12/31/18
Dining room construction 13 days Tue 1/1/19 Thu 1/17/19
Central heating zones construction 11 days Fri 1/18/19 Fri 2/1/19
Project execution completion 0 days Fri 2/1/19 Fri 2/1/19
Development phase 35 days Mon 2/4/19 Fri 3/22/19
Restaurant board formation 8 days Mon 2/4/19 Wed 2/13/19
Preparation of statement vision 7 days Thu 2/14/19 Fri 2/22/19
Preparation of standard service 9 days Mon 2/25/19 Thu 3/7/19
Parking a lot implementation 6 days Fri 3/8/19 Fri 3/15/19
Finalization 5 days Mon 3/18/19 Fri 3/22/19
Development phase completion 0 days Fri 3/22/19 Fri 3/22/19
Closure phase 3 days Mon 3/25/19 Wed 3/27/19
Sign off stakeholder 2 days Mon 3/25/19 Tue 3/26/19
Review of post project 1 day Wed 3/27/19 Wed 3/27/19
Completion of project closure phase 0 days Wed 3/27/19 Wed 3/27/19
5
PROJECT MANAGEMENT
2. Monitoring and Control of Project
The processes that are mainly involved in project monitoring as well as control are
elaborated below:
Scope verification and control: The scope of the project must be verified in order to
analyze whether the deliverables are helpful in fulfilling the requirement of the project or not. If
not then the project scope is revisited again.
Schedule and cost control: By utilizing earned value management, it is quite important
to control both schedule as well as cost of the project so that the project will be completed
successfully within the estimated budget as well as time.
Performing quality control: Before the completion of the restaurant construction, it is
quite important to cross check that all the deliverables of the project are achieved or not. The
tools and techniques that are utilized for controlling quality include control chart, Pareto chart
and more.
Report performance: It is very much important to update the status of the project to the
different stakeholders so that they can work appropriately.
3. Quality Management
Identification of
factors
Purpose Measurement
of project
quality
Analyzing
project quality
Quality control
Proper
training facility
Proper training
must be
Appropriate
training facility
The training that
is provided is
Proper training
facility should
PROJECT MANAGEMENT
2. Monitoring and Control of Project
The processes that are mainly involved in project monitoring as well as control are
elaborated below:
Scope verification and control: The scope of the project must be verified in order to
analyze whether the deliverables are helpful in fulfilling the requirement of the project or not. If
not then the project scope is revisited again.
Schedule and cost control: By utilizing earned value management, it is quite important
to control both schedule as well as cost of the project so that the project will be completed
successfully within the estimated budget as well as time.
Performing quality control: Before the completion of the restaurant construction, it is
quite important to cross check that all the deliverables of the project are achieved or not. The
tools and techniques that are utilized for controlling quality include control chart, Pareto chart
and more.
Report performance: It is very much important to update the status of the project to the
different stakeholders so that they can work appropriately.
3. Quality Management
Identification of
factors
Purpose Measurement
of project
quality
Analyzing
project quality
Quality control
Proper
training facility
Proper training
must be
Appropriate
training facility
The training that
is provided is
Proper training
facility should
6
PROJECT MANAGEMENT
to the workers provided so that
the workers can
do not face any
difficulty in
completing the
project.
is not provided
to the workers
not of
appropriate
quality. It is
reflected with
the challenges as
well as risk that
are faced by the
workers.
be provided.
Utilization of
quality based
materials
Proper quality of
materials are not
used which
creates number
of issues
The quality of
materials used
for construction
is not of
appropriate
quality.
The quality of
the materials
must be
analyzed
properly before
using it.
The materials
that are used
must be of good
quality.
4. Estimation of project
The estimated budget of the project is around $258,568. The picture below reflects the
budget of the project as per the activities.
PROJECT MANAGEMENT
to the workers provided so that
the workers can
do not face any
difficulty in
completing the
project.
is not provided
to the workers
not of
appropriate
quality. It is
reflected with
the challenges as
well as risk that
are faced by the
workers.
be provided.
Utilization of
quality based
materials
Proper quality of
materials are not
used which
creates number
of issues
The quality of
materials used
for construction
is not of
appropriate
quality.
The quality of
the materials
must be
analyzed
properly before
using it.
The materials
that are used
must be of good
quality.
4. Estimation of project
The estimated budget of the project is around $258,568. The picture below reflects the
budget of the project as per the activities.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
7
PROJECT MANAGEMENT
Figure 1: Budget Baseline
(Source: Created by Author)
PROJECT MANAGEMENT
Figure 1: Budget Baseline
(Source: Created by Author)
8
PROJECT MANAGEMENT
5. Risk management
Risk Type of
risk
Risk
statement
Impact Probability Risk
exposure
Risk
mitigation
Improper
management
Negative
risk
Due to
absence of
proper
experienced
project
manager,
the project
related
tasks are
not
managed
properly.
Major Very likely High Adoption of
proper
project
management
strategy will
be helpful in
managing
the project
Improper
budget
estimation
Negative
risk
Due to
improper
market
analysis, it
became
difficult to
complete
Major Probable Medium Proper
market
analysis
must be
done before
budget
estimation
PROJECT MANAGEMENT
5. Risk management
Risk Type of
risk
Risk
statement
Impact Probability Risk
exposure
Risk
mitigation
Improper
management
Negative
risk
Due to
absence of
proper
experienced
project
manager,
the project
related
tasks are
not
managed
properly.
Major Very likely High Adoption of
proper
project
management
strategy will
be helpful in
managing
the project
Improper
budget
estimation
Negative
risk
Due to
improper
market
analysis, it
became
difficult to
complete
Major Probable Medium Proper
market
analysis
must be
done before
budget
estimation
9
PROJECT MANAGEMENT
the project
within the
assumed
budget.
Use of poor
quality of
materials
Negative
risk
If proper
quality of
materials is
not used
then
number of
quality
related
issue will
arise in the
project
Moderate Likely Medium Proper
quality of
materials
must be
used
6. Project organization
The project organization helps in defining the infrastructure of the restaurant. This is
mainly undertaken for defining the various charts of the organization, roles as well as
responsibilities. It is identified that project organization provides number of advantages that
include team specialization, concentrated attention on project work, timely completion as well as
ability to cope with various environmental influences.
PROJECT MANAGEMENT
the project
within the
assumed
budget.
Use of poor
quality of
materials
Negative
risk
If proper
quality of
materials is
not used
then
number of
quality
related
issue will
arise in the
project
Moderate Likely Medium Proper
quality of
materials
must be
used
6. Project organization
The project organization helps in defining the infrastructure of the restaurant. This is
mainly undertaken for defining the various charts of the organization, roles as well as
responsibilities. It is identified that project organization provides number of advantages that
include team specialization, concentrated attention on project work, timely completion as well as
ability to cope with various environmental influences.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
10
PROJECT MANAGEMENT
7. Contracts
The project utilizes contracts for making agreement with other party that agrees to pay
for the deliverables of the project. It is considered as one of the continuous procedures that
generally starts with analysis and evaluation of the inquiry of customers, carrying contract
closure as well as fulfillment of contractual agreements.
8. WBS
Construction of barbeque
resturant in Australia
Project planning
Requirement
analysis
Project nature
analysis
Estimation of
resource
Time schedule
estimation
Estimation of budget
Estimation of
manpower
Analysis of
resources
Project planning
completion phase
Initiation phase
Procurement of fund
Appointment of
stakeholders
Arrangement of
meetings
Arrangement of
finanacial plan
Appointment of
workers
Preparation of
blueprint
Procurement of land
area
Release of legal
notice
Budget allocation
Resource
procurement
Division of time
Duty allocation
Analysis of risk
Risk mitigation plan
Completion of
project initiation
Execution phase
Land area
preparation
Assortment of
resources
Construction of
resturant
Framework
construction of
resturant
Selection of entry
and exit spaces
Application of bricks
Plumbing
Installation of
electric circuit
Concerete
application
Application of colour
Implementation of
system
Application of tiles
Film processing
implementation
Dining room
construction
Central heating
zones construction
Project execution
completion
Development phase
Resturant board
formation
Preparation of
statement vision
Preparation of
standard service
Parking a lot
implementation
Finalization
Development phase
completion
Closure phase
Sign off stakeholder
Review of post
project
Completion of
project closure
phase
Figure 2: WBS
(Source: Created by Author)
PROJECT MANAGEMENT
7. Contracts
The project utilizes contracts for making agreement with other party that agrees to pay
for the deliverables of the project. It is considered as one of the continuous procedures that
generally starts with analysis and evaluation of the inquiry of customers, carrying contract
closure as well as fulfillment of contractual agreements.
8. WBS
Construction of barbeque
resturant in Australia
Project planning
Requirement
analysis
Project nature
analysis
Estimation of
resource
Time schedule
estimation
Estimation of budget
Estimation of
manpower
Analysis of
resources
Project planning
completion phase
Initiation phase
Procurement of fund
Appointment of
stakeholders
Arrangement of
meetings
Arrangement of
finanacial plan
Appointment of
workers
Preparation of
blueprint
Procurement of land
area
Release of legal
notice
Budget allocation
Resource
procurement
Division of time
Duty allocation
Analysis of risk
Risk mitigation plan
Completion of
project initiation
Execution phase
Land area
preparation
Assortment of
resources
Construction of
resturant
Framework
construction of
resturant
Selection of entry
and exit spaces
Application of bricks
Plumbing
Installation of
electric circuit
Concerete
application
Application of colour
Implementation of
system
Application of tiles
Film processing
implementation
Dining room
construction
Central heating
zones construction
Project execution
completion
Development phase
Resturant board
formation
Preparation of
statement vision
Preparation of
standard service
Parking a lot
implementation
Finalization
Development phase
completion
Closure phase
Sign off stakeholder
Review of post
project
Completion of
project closure
phase
Figure 2: WBS
(Source: Created by Author)
11
PROJECT MANAGEMENT
9. Triple Constraints
The triple constraints of the project are as follows:
Schedule: The project must be completed within 368 days. Expansion of the schedule
will enhance project budget.
Scope: The project must follow the scope of the project so the expectation of the
customers can be achieved.
Cost: The project should be completed within the budget that is estimated which is
around $$258,568. The project must not exceed the budget as budget overflow can create
number of financial challenges.
PROJECT MANAGEMENT
9. Triple Constraints
The triple constraints of the project are as follows:
Schedule: The project must be completed within 368 days. Expansion of the schedule
will enhance project budget.
Scope: The project must follow the scope of the project so the expectation of the
customers can be achieved.
Cost: The project should be completed within the budget that is estimated which is
around $$258,568. The project must not exceed the budget as budget overflow can create
number of financial challenges.
1 out of 12
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024  |  Zucol Services PVT LTD  |  All rights reserved.