Running head: PROJECT MANAGEMENTCase Study- Construction of barbeque in AustraliaName of the StudentName of the UniversityAuthor’s Note
1PROJECT MANAGEMENTTable of Contents1. Project Planning...........................................................................................................................22. Monitoring and Control of Project.............................................................................................43. Quality Management..................................................................................................................54. Estimation of project...................................................................................................................65. Risk management.........................................................................................................................86. Project organization.....................................................................................................................97. Contracts......................................................................................................................................98. WBS...........................................................................................................................................109. Triple Constraints......................................................................................................................10Bibliography..................................................................................................................................12
2PROJECT MANAGEMENT1. Project PlanningThe paper reflects on the construction of barbeque in Australia. The table below reflectsthe activities that are planned in order to execute the project successfully within the estimatedtime.Task NameDurationStartFinishConstruction of barbeque restaurant inAustralia368 daysMon 10/30/17Wed 3/27/19Project planning47 daysMon 10/30/17Tue 1/2/18Requirement analysis6 daysMon 10/30/17Mon 11/6/17Project nature analysis5 daysTue 11/7/17Mon 11/13/17Estimation of resource4 daysTue 11/14/17Fri 11/17/17Time schedule estimation5 daysMon 11/20/17Fri 11/24/17Estimation of budget10 daysMon 11/27/17Fri 12/8/17Estimation of manpower8 daysMon 12/11/17Wed 12/20/17Analysis of resources9 daysThu 12/21/17Tue 1/2/18Project planning completion phase0 daysTue 1/2/18Tue 1/2/18Initiation phase105 daysWed 1/3/18Tue 5/29/18Procurement of fund7 daysWed 1/3/18Thu 1/11/18Appointment of stakeholders8 daysFri 1/12/18Tue 1/23/18Arrangement of meetings6 daysWed 1/24/18Wed 1/31/18Arrangement of financial plan9 daysThu 2/1/18Tue 2/13/18Appointment of workers8 daysWed 2/14/18Fri 2/23/18Preparation of blueprint7 daysMon 2/26/18Tue 3/6/18Procurement of land area5 daysWed 3/7/18Tue 3/13/18Release of legal notice7 daysWed 3/14/18Thu 3/22/18Budget allocation9 daysFri 3/23/18Wed 4/4/18Resource procurement8 daysThu 4/5/18Mon 4/16/18Division of time7 daysTue 4/17/18Wed 4/25/18Duty allocation8 daysThu 4/26/18Mon 5/7/18Analysis of risk9 daysTue 5/8/18Fri 5/18/18Risk mitigation plan7 daysMon 5/21/18Tue 5/29/18Completion of project initiation0 daysTue 5/29/18Tue 5/29/18Execution phase178 daysWed 5/30/18Fri 2/1/19
3PROJECT MANAGEMENTLand area preparation12 daysWed 5/30/18Thu 6/14/18Assortment of resources13 daysFri 6/15/18Tue 7/3/18Construction of restaurant9 daysWed 7/4/18Mon 7/16/18Framework construction of restaurant10 daysTue 7/17/18Mon 7/30/18Selection of entry and exit spaces11 daysTue 7/31/18Tue 8/14/18Application of bricks14 daysWed 8/15/18Mon 9/3/18Plumbing12 daysTue 9/4/18Wed 9/19/18Installation of electric circuit13 daysThu 9/20/18Mon 10/8/18Concrete application15 daysTue 10/9/18Mon 10/29/18Application of color11 daysTue 10/30/18Tue 11/13/18Implementation of system10 daysWed 11/14/18Tue 11/27/18Application of tiles9 daysWed 11/28/18Mon 12/10/18Film processing implementation15 daysTue 12/11/18Mon 12/31/18Dining room construction13 daysTue 1/1/19Thu 1/17/19Central heating zones construction11 daysFri 1/18/19Fri 2/1/19Project execution completion0 daysFri 2/1/19Fri 2/1/19Development phase35 daysMon 2/4/19Fri 3/22/19Restaurant board formation8 daysMon 2/4/19Wed 2/13/19Preparation of statement vision7 daysThu 2/14/19Fri 2/22/19Preparation of standard service9 daysMon 2/25/19Thu 3/7/19Parking a lot implementation6 daysFri 3/8/19Fri 3/15/19Finalization5 daysMon 3/18/19Fri 3/22/19Development phase completion0 daysFri 3/22/19Fri 3/22/19Closure phase3 daysMon 3/25/19Wed 3/27/19Sign off stakeholder2 daysMon 3/25/19Tue 3/26/19Review of post project1 dayWed 3/27/19Wed 3/27/19Completion of project closure phase0 daysWed 3/27/19Wed 3/27/192. Monitoring and Control of ProjectThe processes that are mainly involved in project monitoring as well as control areelaborated below:Scope verification and control:The scope of the project must be verified in order toanalyze whether the deliverables are helpful in fulfilling the requirement of the project or not. Ifnot then the project scope is revisited again.