Procurement System for Enviro Park Project

Verified

Added on  2023/01/17

|26
|7229
|97
AI Summary
This report analyzes the procurement selection systems for the park project related to environment and compares the contract for timing, costing, and quality parameters. It also explores the relationship between supply chains and partnering schemes and strategies for various stakeholders in the construction industry.

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
CONTENTS
1.0 EXECUTIVE SUMMARY
2.0 INTRODUCTION
3.0 DEVELOPMENT PLAN / ENVIORENMENTALLY SENSITIVE DESIGN/
CONSTRUCTION CONCEPT
4.0 DETERMINING THE APPROPRIATE PROCUREMENT SYSTEM BASED ON
EVALUATING CLIENTS OBJECTIVES AND STRATERGIES FOR DESIGN AND
CONSTRUCT SERVICES.
5.0 APPROPRIATE CONDITION OF CONTRACT AND IMPACT OF CONDITION
OF CONTRACT FOR TIME, COST & QUALITY PARAMETERS.
6.0 SUPPLY CHAIN RELATIONSHIPS & PARTNERING SCHEMES EVALUATING.
7.0 STRATERGIES FOR VARIOUS STAKEHOLDERS IN THE CONSTRUCTION
INDUSTRY
8.0 CONCLUSIONS
9.0 REFERENCE LIST.

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1.0 Executive Summary
In this report the analysis will be related to the perfect procurement selection
systems for the park project related to environment and also provide a comparison
of the contract on how to deal with the problems of timing, costing and also quality
related parameters. In addition to all of these this project is also selected to
understand the relationship between the supplying chains and the schemes related
to partnering for any kind of future projects and also develop the techniques for
stakeholders related issues.
The intension of the client is to do the project as the cutting-edge sustainable
development, and also implement best and the most innovative and updated
practices.
Requirement of the project, the constraints, dangers, and the capability of the client
and the marketing position was analyzed in order to determine the perfect system of
procurement and also show a comparison between various delivery models such as
traditional, build and design, directly managed , alliance and many more in order to
identify the most appropriate model for the project related to enviro park. The necessary
steps and approaches to the market include the tender processing , pricing strategies
and the contract form were analyzed.
The designing and the build structure were detected as the most appropriate approach
to get the opportunity to the employer in order to select a appropriate design by quality
maximization within the budgetary constraints and also to proceed with a continuation of
the designing effort. Further the clients are preferring to remove all the inefficiencies and
the delay related to the preparation of the designs and also to speed up the project in
order to get the best value related to the return on the investment, transfer the
responsibility of the contractor for a large fixed pricing and bespoke designing, and also
utilize the technique in order to select a perfect design to establish a landmarking
construction and also to immediately commence the projects. The most common type of
contacts like the FIDIC, JBCC2000 , NEC3 and the GCC are compared among each
other in order to find the most appropriate form on order to make the contract. After
comparing all the contacts, the FIDIC Yellow Book- Conditions is chosen in case of the
Plant and Design-Build for the electrical as well as the mechanical plants and also for
building of works that were planned by the service contract taker. In the recent module
of the contract the saying “electrical and mechanical works” moves away from title of the
assignments and which is aligned with that of FIDIC suite and attention is much on what
is the procurement type rather than the nature of the work.
The relation between the supply chain and also the schemes that is related to
partnering were evaluated that was based on the long duration commitment that
embraces the business philosophy that was basically described with the help of the
elements of the mutual trust, long-term perspective, communication, solving of the
problems, mutual targets and also the equity. As all the clients are eager, so that they
can expand their portfolio and are also searching for two different potential sites that are
under development of similar kind of nature in the country of Sri Lanka, it is very
Document Page
essential to keep a focus on the relationship between the supply chains and also the
partnering schemes to achieve high cost, time benefits as well as quality.
Identification of the stakeholders who are involved in the project, and to set up a perfect
coordination and also facilitation in order to manage their prospects by applying a
practical approach starting from the initial stages of project were illustrated. By
identifying the possible threats and then taking the necessary approach which will be
resulting in the delay of the project is very important in order to avoid any kind of
unnecessary delay. Before setting up the time line the project management team should
analyze these factors.
2.0 Introduction
This assignment or rather considered as report is basically created as one of the
part of the graduation academic task. The intention over creating this report is
mentioned below.
In order to create a different between short as well as long-term advantages
of taking numerous contractual conditions
Must be able to determine the correct system of procurement for the enviro
parking project which is based on the client target.
Be able to give the suggestion on the developing techniques for the
partnering as well as the stakeholders of project.
In this study comparison is made between the different models of delivery and
also different forms of the contract in order to choose the perfect procurement
system for the project related to the enviro park with the objective of the client
related to the time, quality and the costing parameters.
In this report we have included the proper justification of the procurement
systems and how relationship with that of the suppliers or the subcontractors
partners suppose to create a relation with the future projects.
In this report the description is provided related to the different stakeholders and
also their expectations with the help of a proactive approach by maintaining a
strong relationship with project.
The author in this report have a total experience of 15 years within the
construction industry in numerous company of the country Srilanka and the past
4 years were commenced as – Tenders Estimation & Post Contract Cost
Management in Al Tasnim Enterprises LLC, which is considered to be the
Document Page
leading and an excellent grading construction organization situated in Oman.
This report is also based on academic theories as well as field experience.
3.0 DEVELOPMENT OF PLAN AS WELL AS ENVIROMENTALLY DESIGN WHICH IS
SENSIVE/ CONSTRUCTIONAL CONCEPT
Energy Trust can be defined as an international company with investors in the
flagship proposals for the green technological center, sporting center also commonly
known to be Enviro park and conservation locality. With the help of proposal
development 3000 full time jobs and an assumed constriction of over 100 million US
dollar can be developed. This approach has obtained the outlining planning
approvals.
The sports complex will be the principle aspects of the development , which is
situated at the new home to Kalutara Cricket Club(KCC). The club will be
complemented as well as supported by green technological club of the northern site.
This club will be basically used as a funding of sporting complex on southern site.
The conservation area that is situated in the western site will be basically used for
the biological immigration as per the approach to ensure the substantial
improvement of the biodiversity crossways the whole site. This site is established at
the southern expressway E01 which is near to dodangoda exit in kalutara district
perfectly 50 km to the si]outh of the Colombo. It is at present used for agricultural
purpose.
Project Employer
1. Energy Trust
2. Kalutara Cricket Clud
3. Sports Ministry(Srilanka)
The Enviro Park consist of three appropriate but elements that are
complementary
1. Green Technology Hub(GTH) (the northern area) (34 x (900-3800 sq. m)
blocks
2. Sports Complex (SC) (the southern area)
a. Indoor pitch
b. Transport hub
c. Cricket Stadium 3000 capacity
d. Athletic pitch
e. Training pitches
f. Supporting facilities
3. Nature Conservation Area(NCA) (western area). (5 hectares)

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
The location basically cosists of the three rudiments that are distinct blue
area(GTH) , green area(NCA), red area(SC)
Fig-1- Extracting of the ‘Land Use Parameter Plan’ with different elements
color coding. The NCA (West) in Green, the GTH(North) in blue and the SC
(South) in Red.
Dimensions of the Environments
Several environmental activities are displayed in this project
1. Backfilling should be done with the help of Site excavated material /
Without disposal of the earthwork material
2. Flood controlling should be done with the help of proper drainage
system/ with the permanent waste watering system of treatment.
3. Minimize the consumption of the energy with the help of natural lights ,
AC systems that are efficient , using trees and also provide natural
ventilation in order to reduce the heating loads for foot prints with low
carbon.
4. Solar photovoltaic energy by the usage of the roof areas, cars park
having electric car with the charging points and also power plant of the
wind turbine.
5. Garbage re-cycling or Waste managing strategies
6. Environment effect watering spray for controlling the dust or eithn the
help of proper hoardings to boundary of site.
Specified designing proposals will be emerging from evolution of outlining
planned Revised Concept Design and also will be subjected to the reserving
matters. Outlined below are the principles considering the Enviro Park
design. The benchmark related that is basically used in the Enviro Park is
expected LEED Certified. United State s Green Building Council administers
the quality of leadership in the Energy and Environmental Design(LEED) as
the globalized market leader in the systems related to rating.
Document Page
4.0 DETERMINATION OF THE APPROPRIATE PROCUREMENT SYSTEM WHICH IS
BASED ON THE EVALUATING CLIENTS OBJECTIVES AND STRATEGIES
RELATED TO THE DESIGN AND CONSTRUCT SERVICES
Determination of the perfect contract or the procurement strategies will be becoming
apparent as there is a progress in the evaluation progress starting from the initial
appraisals to that of the full analysis, includes the consideration of the potential
structure in case of dispute because of the unknown and the known dangers. The
client must ensure that perfect risk strategy is chosen before entering into the
contractual relationship, and are also reflected by the structure of the organization
and the payment methods as well. Smith (1995)
Procurement strategy in three stages:
a. Determination of the delivery model that are perfect such as design and build,
traditional, direct managed, alliance and others.
b. Gathering and analyzing of the project information
c. Approaching to the market which includes the pricing strategies, tendering
process and forms of the contract (New Zealand government procurement guide
2015)
Analysis of the Key procurement issues
Factors that are considered to be out of control of the project team
1. Performance and quality
2. Client resources
3. Costing issues
4. Project character
5. The need to accommodate to the changes, variation
6. Risk management
7. Timing issue
These are the factors that needs consideration for determination of the
procurement systems for the Enviro park project by the analysis of the
project related data.
a. Constructed budget already estimated
b. Project controlling design completed
c. Energy Trusting company profile and the experience (founded in 1995 as world
first green energy company)
d. Project classifies the several packages (Ex; Green technology hub (GTH)/ Sports
Complex (SC)/, the Solar PV, wind turbines power plants and Natural
Conservation Area(NCA)/ Infrastructure & landscaping)
e. Project designing concept is almost completed
f. Complexity in design and complexity
g. Environment sensitive construction and design
Document Page
h. Returning of the investment(ROI)
i. Desired milestones target dates
j. Unforeseen factors of risk (Ex Soil condition, impact of flood due to heavy rain,
earth slips and others)
k. Requirements in the quality standards
l. Future maintenance and the operation requirements
m. Site conditions
n. Flexibility for the changes during the construction
o. Client involvement
p. Accountability
q. Boundaries of the technology
r. Project assurance quality
Concern of the clients in project achievements
1. Return of the investment(ROI)
2. Client budget
3. Minimization in claims or vacation
4. Minimize and also share risk with the contractor
5. Unique design in order to build a landmark project
6. Elimination of delays and inefficiencies
7. Environment sensitive design
8. Faster in delivery
9. Relationship for the future expansions
10. Safety and Health aspects
Involvement of the client and the initial inputs that are required for the delivery of
the project
a. Establishment of the process or the mechanism in instruction to monitor the
project process and also the excellence
b. Preparation of the client requirement and the necessary speciation’s by the
client in house contractors and the teams
c. Preparation of the project program and time lines
d. Preparation of the organizational structure
e. Ensure the understanding of the entire context before the evaluation of the
deigns or the technology or materials quality and also to satisfy with every
performance levels and also meet the requirements of the project
Steps to become a successful Enviro Park project
In order to make the projects successful, certain steps should be taken
a. Distribute the requirement of the project to all the parties that include the
employer, delivery partners and the stakeholders
b. Creation of the project mechanism and also to meet the requirement of
the project
c. Achieve the project timing targets
d. Managing of the projects within that of the financial budgets

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
e. Appointment of experienced and commitment employee to the project
f. Use all the resources that are available in the inhouse or outside as well
g. Proper coordination of the relavent authorities for the necessary
approvals.
h. Management of the risks and also identification of the risk in early stage
i. Arrangement of the required developing and the delivery models and
the procurement strategies for the designing and the construction of the
Enviro park project.
Identification of the delivery models related to the project and the
procurement strategies for the enterprise and the building of the Enviro
park development.
1. In order to develop the necessary strategies employer team must
follow the necessary steps. There should be identification of the
proper delivery models in order to achieve the project requirements
on time, quality related matters and also to minimize the danger to
the client.
2. As it is considered as a huge project which is split into numerous
packages such as the Sport Complex(SC), Green technology
hub(GTH), Natural Conservation Area(NCA) , solar PV,
Landscaping & Infrastructure, Wind Power plants), proceeding with
the different delivery models and the procurement strategies.
Interconnection between the packages must be documented with
the help of the procurement strategies.
The objectives of the project must be translated in the procurements
objectives. This gives a relation between the delivery of the product
or that can be promoted with the help of the product delivery. The
primary target can be also related to the budget, quality or the
performance , delivery rate , environmental or the health of the
safety aspects , involvement of the client in the project, end-user
satisfaction also the maintenance and the satisfaction of the project
and the operational Scope work Develop concept Develop and the
documentation design Constructs works Hand over work Parties
agree in the target pricing and the sufficient data is also available to
do(Watermeyer, 2010)
Procurement Method Construction or the Model Selection
The feature of this method in the project management structure or
the client’s consultant decisions is to choose the perfect method that
is based on time, quality, cost and the project complexity.
All the above issues has resulted in a need to conduct a process of
selection in a systematic as well as in a disciplined manner. Some of
the factors needs to be taken into consideration before making any
kind of informed decision on the correct choice of that of the PM.
Document Page
These factors can be categorized in as the internal as well as the
external factors factors (Love et al., 1998; Luu, and Chen, 2005), as
presented in Fig. 1 (Ratnasabapathy et al., 2006).”
Figure 2 Source: Ratnasabapathy et al., 2006
The employers has to choose a delivery model that are suitable and
also create a usual agreement form in order to solemnize which is
grounded on the delivery model. Proffering processes and also the
evacuation process that re based on the contract. Activities such as
Government services purchasing and also the evacuation process
that is related to the infrastructure works requires parallel activities
and also to incorporate with the working program.
Type of delivery models that are widely used in the project
procurements
a. Construction systems that are traditional
b. Managed Contracts (Construction Management or the
Management Construction)
c. Construction & Design or the Engineer Procure Construct(EPC)
d. Private-public relationship (PPP)
e. Relationship related contracts Ex. Early contractor involvement ,
alliance
f. Early contractor involvement
g. Alliance
This step is related to the initiative that is aimed at the
standardization in order to boundary the high-quality of the
contractual procedures. The forms of the contract that are
suggested includes the following series data:
FIDIC (French acronym for International Federation of Consulting Engineers)
1999
Construction
procurement
selection
External
environment
Internal
environment
Project
characteristics
Client
characteristics
Client
requirements
Cost related Quality related
Time related
Natural disasters
EconomicPolitical & legal
Document Page
General Conditions of Contract for Construction Works (GCC 2004)
JBCC Series 2000 ·
NEC3 family of normal bonds
FIDIC, NEC3 and GCC can be considered as the forms of the contracts that is
basically used for every types of construction and the engineering bonds. JBCC 2000
is, confined to the structure the whole thing.
(BEST PRACTICE GUIDELINE #C2 Choosing an appropriate form of contract for engineering
and construction works September 2005 Second edition of CIDB document 1010)
Selection of the perfect contract form
These are the factors that needs to be considered while creating of the decision for a
suitable contract form (FIDIC, GCC, JBCC or NEC3).
1. Working is complex
2. Capability of Management, capabilities and the expectation of the agents and
also the parties.
3. Requires the specific pricing and contracting strategies
4. Compatibility with the administrative procedures with that of the company.
5. Requirements that are related to :
a. The management as well as the assignment danger
b. Engagement back to back for all the types of the subcontractors and also
managing the time and the cost overruns.
6. In order to grip the diverse managerial techniques in case of the construction and
the civil engineering agreements the ability and also the capacity of the skilled
resources.
7. Single system standardization which has the capacity to handle the disciple and
also the contracting strategies within a single documents with respect to the
construction and the building works and all the procurements.
8. Requirements in training

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Fig 3 Selection of a perfect contract
Fig 4 Average supplies in each contract relating to valuing and diminishing approaches
NEC3
Engineeri
ng and
Construct
ion
Contract
(ECC2)
NEC
3Engineer
ing and
Constructi
on
Short
Contract.
(ECSC)
FIDIC
Conditions
of
Contract
for
Construc
tion and
Building
and
Engineering
Works
Designed
by the
Employer
(Red
Book)
FIDIC
Conditio
ns of
Contrac
t for
Plant
and
Design
(Yellow
Book)
FIDIC
Conditio
ns of
contract
for EPC
Turnkey
Projects
(Silver
Book)
FIDIC
Short
Form of
Contrac
t
General
Conditio
ns
(Short
Form)
JBCC
Principal
Building
Agreeme
nt
JBCC
Minor
Works
Agreem
ent
GCC
2004
Contract × × × × × ×
Document Page
strategy
Construction
Management
× ×
Design by
Employer
× ×
Managemen
t Contract
× × × × × × ×
Design and
Build
× × × ×
Develop and
Construct
× × × ×
Pricing
strategy
Activity
schedule
Bill of
quantitie
s
Cost
reimburs
able
Target
cost






×
×
×

×
×

Not fully
develop
ed
×
×

×
×
×
No
standar
d
provisio
ns


×
×


×
×


×
×
Backtoback
subcontracts
Two
standard
subcontract
s available
(Engineerin
g and
Constructio
n
Subcontract
(ECS) and
the
Engineering
and
Construction
Short
Subcontract
ECSS)).
ECC2 and
ECSC can
also be
used as
subcontract
documents.
None available Nominat
ed /
selected
subcontr
act
agreeme
nt
available
.
None
availa
ble
(BEST PRACTICE GUIDELINE #C2 Picking an suitable form of agreement for engineering and
building works September 2005 Second edition of CIDB document 1010)
5.0 SUITABLE CONTRACT DISORDER AND IMPACT OF THE AGREEMENT
COMPLAINT FOR TIME, QUALITY & COST LIMITATIONS.
Delivery selection method under FIDIC forms of the contract
Document Page
Fig-5 FIDIC global presence (source; FIDIC Annual Report_2014)
a. Contractual Conditions for the purpose of Construction
b. Short Form Contract( Green Book)
c. Situations of the Contract for EPC/ Turkey Projects(Silver Book)
d. Situations of the Contract for the Plant and Design-Build(Yellow Book0
e. Conditions of the Contract for the Designing, Building and the Operate
projects( Gold Book)
Green Book -Short Form of Contract First Edition 1999
For the purpose of engineering and the building works of the relatively smaller capital
values, the Short Form of the Contract is recommended. The Leadership Minutes for
the Green Book recommends will not be considered for on schemes having a
commerce value that is superior than US$500,000.
Red Book- The contract of the conditions for the structure and the Engineering the
whole thing that is basically calculated by Employer First Edition 1999
Red Book supplies a condition of the agreement for the building works in which the
designing is approved by the Employer.
Red Book is not considered to be appropriate for any kind of use where the works
are designed with the help of the Contractor and for that kind of the projects it will be
perfect for the Silver Book of the Yellow Book.
(Source; http://docplayer.net/21472350-The-fidic-suite-of-contracts.html)
Building works, Yellow Book condition is used for better understanding of the
Contract plant design and hence better management of the entire process is
condemned, designed with the help of the Contractor First Edition 1999 Second
Edition 2017

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
The Yellow Book is used to provide a contract for the construction related works
where the designing is carried out with the help of the contractor in accordance with
the requirements of the employer that basically includes an combination of
mechanical, civil, electrical and as well as construction related work. The Yellow
Book is able to bear smaller resemblance of that f that of the predecessors. In the
current edition drops words “mechanical and electrical work” from title and also in line
with all the rest FIDIC suite which focuses on the type of procurement rather than the
working nature.
Project Administration and also the works of supervisors is basically carried upon
with the help of the Engineer those are employed by Employer.
A vital area of the consideration with the preparation of a particular condition is
considered to be the risk allocation for the grounding conditions which proves to be a
danger in the standard draft.
(Source; http://docplayer.net/21472350-The-fidic-suite-of-contracts.html)
PLANT AND DESIGN-BUILD CONTRACT SECOND EDITION (2017 YELLOW BOOK)
The Second Edition is basically build for the FIDIC Yellow Book with consists of the
FIDIC’s fundamental principles of the balanced sharing of risk which seek to build on
considerable knowledge from use for the historical 18 years. The publication delivers:
1. Clarity and details regarding the necessities for the posters and also other
infrastructures.
2. Necessities related to the addressing of the Employers and the Contractors that
basically claims the treatment of the equally and separated form of the disputes.
3. Provisions related to the management of quality, and also the confirmation of the
Contractor’s pledged acquiescence.
4. Mechanism for the avoidance of the disputes
Silver Book - Conditions of Contract for EPC/Turnkey Projects
First Edition 1999
The Silver Book is basically used for certain processes, private-infrastructure and
also power projects where the responsibility has to be taken by the contractors
for the designing and the execution of the projects. Cost, quality and completion
of time related issues has to be managed by the contractors and in this case
Silver Book provides to be perfect for the experienced Contractors who are
familiar with the risk management approach.
Silver Book basically requires Contractor acceptation in a higher level of the risk
that is considered to be difficult in most forms of the contract.
Gold Book- Conditions of Contract for Design, Build and Operate Projects
First Edition 2008
Document Page
The technique that DBO contract follows is quite similar with that of the FIDIC
Silver Book than other contracts in the FIDIC suite. Under this contract the
contractor of the DBO do not have any responsibility for the financing of the
project or for the ultimate commercial success.
For the contracts that are traditional DBO sequence based, DBO contract is not
recognized to be suitable or the Operational Period differs from 20 years that are
adopted. (Source; http://docplayer.net/21472350-The-fidic-suite-of-contracts.html)
Figure 6 - WHICH FIDIC CONTRACT SHOULD I USE?
(Source ; http://fidic.org/bookshop/about-bookshop/which-fidic-contract-should-i-use)
Why anyone should select the Design-Build for the Enviro park project?
In order to enable and also regulate the particular project delivery performance
systems which is predominantly based in three concepts:
1. Partnering principles
2. Performance specification
Document Page
3. Fast- tracking technique in order to combine the time of construction processes
and the design. Giovanni Di Folco (2016)
Selecting of the “design and build” obtaining Model for the Enviro Park Project
that is grounded on the Excellence and the Time supplies and the customer
character
1. Contractor responsibility for a lump fixed pricing and the bespoke designing
2. In order to reduce the inefficiencies and the delays of design preparation by
the employer’s management team and also to speed up the project in
command to get the best return of the speculation.
3. Employers get the access to reduce the time as well as cost for the designs
and the possibility of reduction of the cost of the contractors able to design
the specialist contractors, suppliers and the sub-contractors.
4. Building and Design of the Contractor, enables different designing for the
users for the satisfaction of the employer and is also based on the designing
specialist elements at a very low cost than the professional consultants.
5. Employers or the contractors will be able to utilize the design by selecting the
opportunity that are built on the landmark project in order to promote the
business related targets and also to get attractions.
6. As the requirements of the client are finalized, the project will start
immediately after the evaluation of the tender and also as far client
satisfaction. Consultant of the Client can be able to do the necessary
negotiations with the contractors at a post tendering stage in order to fit the
budget and also designing satisfaction.
7. In case of any quality shortfalls or in case of the inexperience of the client the
contact administrator will cover it.
8. Only the single contractor will be able to lower the cost and the time related
to the project responsibility.
9. Designing and the built will provide the opportunity to the employer so that
they can select a suitable design by maximizing the quality with the help of
the budgetary constraints and also there is a continuation of the designing
effort.
10. The period of the project is shortened and is also ready for the revenue that
are generated early, construction will start parallel to the design works.

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
11. Clients confirms the design during preparation and also the designing
stages that is related to the asthetic requirements and architectural
significance. Clients basically connect with a single party in case of any
change in the design.
Figure 7 Design & Build Vs Traditional
(Source; https://www.lundaconstruction.com/how-we-build/design-build)
Contractor’s roles and the responsibility
a. Contractors has to comprehend the artistic or the construction values in order to
ensure the high excellence production
b. In this method the responsibilities is in the contractor side, contractor has to do it in
order to accomplish the necessities of the employee within the period and in the
economical as well. Any kind of delay or something that is beyond the control of the
contractor would prove to be a risk for the contractor.
As the trust related to Energy have many years of the involvement in this
manufacturing and they are also well recognized, the servicers have to get
contributions from the past schemes and from their earlier involvement. .
(https://.ukessays.com/essays/construction/analysis-of-the-key-procurement-issues-
construction-essay.php)
Typical Built & Design arrangements
Document Page
Figure 8 Contractual and Functional Relationships in Design & Build (Source; Masterman,
J. W. E. (2008))
The benefits of Consultant engagement for the purpose of Designing & Build the projects as
the Employer’s typical for administration of the agreement:
Speed:
Decision making is rapid which is based on the experience and the knowledge in order to
avoid the unnecessary delays and is also effective in project period reduction.
Return of the Investment (ROI):
The experience and the knowledge that are required for the preparation of the clients
supports for the tendering evaluations and also calculation of the figures for the ROI in order
to mitigate the danger.
Objectivity:
On the behalf of the employer deal with the outside parties such as the government, politics,
societies, authorities and others.
Document Page
Expertise:
The senior levels has the expectation to provide a expertise with the employer in order to
make sure the required requirements of the management level.
Effectiveness:
Project management grants the authority and the creditability to the changing or the
transition of the consultant to make it effective.
Accountability:
Take the responsibility in order to manage the program or the project and also provide the
advertisement to the contractors, the supplier and the employer.
Commitment:
From the project management consultant, high professionals’ standard is expected who are
having proper knowledge and the reputations of the tracking records.
FIDIC published Client/Consultant Model Services Agreement in 1998 Third Edition
(White Book)
The Client’s Consultant Model are basically optional for the purpose of universal usage of
the before investment stage and also the viability studies for designing and the construction
of the plan administration , where the approaches for such kind of the facilities are invited on
the basis of global and also national services. For the Contract Management Projects FIDIC
declares that this type of form is considered to be suitable, however in case of practice this
type of model is not generally used. Considering Risk Allocation,
Employer and the design and the Building Contractors consider consider the major factors
for the cost and time overrunning issues.
a. Variations of the work
b. Procurement systems issues
c. Material shortage
d. Delay of the subcontractors
Quality performance includes functional facility, appearance, durability, efficiently and
the reliability. The characteristics that are mentioned above determines the cost as
well as time. Designing and the build sometimes meets the better quality for

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
innovative as well as complex projects rather than that of traditional procurement
systems.
Stages of Tendering
Public procurements can be subdivided in the following tendering processes:
1. Preparation of the complete tendering documents
2. Contractor invitations for the expression of interest.
3. Contractor’s Pre-qualification requirements
4. Research on the bids as well as the award of the work to all the contractors that
are successful.
Pre-Qualification of Contractor
The experience of the contractors related to similar kind of project experience,
quality, reliability, and the financial capability supposed to be satisfactory, before
contract awarding. The procurement team of the client reduces the danger of the
increasing costs and the poor quality as well by contract awarding that basically
demonstrate the qualifications, the reliability as well as experience.
The responsibility of the contractors before the evaluation of the bid opening is
considered to be more suitable- by the prequalification of the bidders in the stepping
process. In initial stage, contractors evaluate based on the numerous qualification-
based criteria that is related to past performance. In order to submit the bid the
contractors meeting must be minimum. This is done just to
1. Reduction in the administrative time and also save the bidding costs.
2. Saving of time by performing the contractor prequalification side by side
completing construction documents.
3. If the contractors fail in qualification at the process beginning , before the
collection of the bid and also submitting of the bid, without any kind of investment
in project.
(Sourcehttp://procureware.com/choosing-right-construction-procurement-method);
Document Page
THE EVALUATION PROCESS
Pointing statement might be used as the guidance:
Technical bid:
1. Equipment’s/Resource and Staff
2. Similar kind of Project Experience
3. Location of Contractor
4. Working Program or design
Financial bid:
1. Commercial bid value
The following steps must be followed:
Step 1: Bid Reception
Step 2: Bid Opening
Step 3: Reviewing of the Document
Step 4: Commercial or technical evaluations
6.0 PARTNERING SCHEMES EVALUATION & SUPPLY CHAIN RELATIONSHIPS
Contractor /Supplier/Sub contractor Partnering
The main reason of success behind every project will be revolving around the
relationship quality which is between the client and the service providers. The relationship
should be based on the understanding and the trust between the parties and also if properly
managed, leads to a permanent contracts between both the parties , for a longer period of
time. (Dave Friar 2018).
The experience as well as the perceptions of the partnering relationships are
considered to be positive, in spite of the earlier optimism at starting of such kinds of
arrangements is seldom sustaining throughout the project lifecycles. In case of
upstream as well as downstream attitudes pertaining to the relationship is similar.
The growing popularity of the alternative procuring strategies and methods and the
statutory adjustments are considered as the contracting parties on equal footing. In
case of today’s environments, contractors will continue to operate basis on the tight
margins and are also common to all the stakeholders, the financial imperative will be
considered as commercial manager’s principle consideration. Relationship are
Document Page
characterized on the basis of cost driven agenda and the trust is also hard-earned
(Gerard D. Wood ,Robert C. T. Ellis 2007).
The contractors that are main in the list must have through expertise in certain
areas, To make the project success specialized subcontractors are required.
Numerous sub-contracting packages are required for Sports Complex (SC)/
Nature Conservation Area (NCA)/ Green technology hub (GTH)/ landscaping &
infrastructure and in solar PV , wind power plants.
With the need of specialized contractors, its necessary to maintain
relationship between contractors and subordinators, should not be treated as
disposable. To have the proper communication, respecting of the parties is
important main contractor and the relationship with the sub-contractor.
In order to understand the proper method selection, methodology shown
below:
1. Improving main contractor's overall performance.
2. Improving subcontractors' industry performance.
3. Identification of the critical areas of the subcontractors' performance
improvement.
4. Identification of new parts for the subcontractors management development.
5. Generate a subcontractors' catalogue based on the presentation.
SUCCESSFUL SUBCONTRACTOR MANAGEMENT
Administration Performs Positive schemes involves the subcontractors.
a. The efforts are integrated in the cohesive planning with the subordinators in
the overall picture.
b. All have unambiguous and clear establishment that will include in the
statement of work.

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
c. Before proceeding with a work, the subcontractors or the co-workers grant
authorization in order to continue. This type of approval is given in a written
form with the help of the effort approval form.
d. A team structure procedure is first recognized and then applied. This type of
performs leads to danger reduction of any kind of misunderstanding or any kind of
isolation.
Figure 9 Vision and Strategy for Supplier Selection
(Source; https://dashboardexcel.com/index.php/management-kpi-reporting-
templates-for-excel)
7.0 VARIOUS STAKEHOLDERS STRATEGIES IN THE CONSTRUCTION OF
INDUSTRY
Precise definition of stakeholders will be : “those groups or individuals with whom
the organization interacts or has interdependencies…any individual or group who
can affect or is affected by the actions, decisions, policies, practices or goals of the
organization”. (Carroll, 1993).
Document Page
Stakeholders include Energy trust, Ministry of Sri Lanka. , Facilities managers,
Project management team members, designers, shareholders, public authorities and
their administration, workers, subcontractors, services suppliers’ competitors, banks
and regional development agencies.
Figure 10 -Project Life Cycle & Stakeholder Involvement
Energy trusts might face initial difficulties to work in the stakeholders in Srilanka due
to some cultural differences, difference in the ideas and in the professionals ethics
as well.
Effective Stakeholders management
Strategic Techniques- The priority is given ti the stakeholders rather than
management.
Stackholder Synthesis Approach- The assumption is moral but responsibly to
stakeholders.
(http://salineropampliega.com/2013/10/stakeholder-management-in-
construction.html)
Stakeholders Participation in the Scheme Stakeholders provide subsequent
advantage-
a. Advises/ideas to improve construction operations.
Document Page
b. After recognizing the objectives or the target, involves the development of
an appropriate designing specifications.
c. Exchange of ideas for creative solutions
d. Suggestions regarding higher customer satisfaction can be made.
e. Project procedure leading can be performed in each step..
8.0 Conclusion
In order to deliver the enviro park project, requires identification of identity, how the
project parties are involved and there is interaction with users. This facilitation
should be done by considering all the factors which is based on the client objectives.
FIDIC Yellow Book were selected for the construction related work .The attributes
are chosen on behave of the organization and the business. Implication of the project
stakeholders should be done. .All the attributes that are chosen in order to measure
the supplier contract, that has fundamental implications in order to detect how the
behave, and business correlate with each other. The stakeholders must be managed
by the company in a better manner.
9.0 References List
Realyst (November 2015) Project and Contract Management Guideline
Jonathan Hosie (November 2007) Turnkey contracting under the FIDIC Silver Book
Lucas Klee (2013) Delivery Methods Under FIDIC Forms of Contract
BEST PRACTICE GUIDELINE CIDB document 1010 (September ,2005) #C2 Choosing an
appropriate form of contract for engineering and construction works.
Procurement Leaders (June 2013) STRATEGY GUIDE; Supplier relationship Management
SCI Network (2011) Procuring Innovation
Himal Suranga Jayasena, Gihan Geethanath Seram, Jery Johnson (2013) Frequently
Challenged Determinations of the Engineer in Srilankan Construction Contracts
FIDIC Procurement Procedure Guide (1st Edition 2011)
Research Gate Article (May 2016) Criteria For Selection Of Design And Build Procurement
Method
Clamp, H. (2012) Which Contract? Choosing the appropriate building contract (5th edition), RIBA

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Prof. Nicholas Gould (2016) An introduction to FIDIC, international procurement and
development bank procurement
R. B. Watermeyer (2012) A framework for developing construction procurement strategy
Kohetal. (2011). Sustainable procurement through construction project
A framework for developing construction procurement strategy (R. B. Watermeyer)
Gerard Wood (March 2005) Partnering practice in the relationship between clients and
main contractors (RICS Research Paper Series) search paper series
Volume 5, Number 2
N. A. Mirawati, S. N. Othman, and M. I. Risyawati (2015) Supplier-Contractor Partnering Impact
on Construction Performance: A Study on Malaysian Construction Industry
Roham Nikinosheri and Filip Staxang (2016) Contractor-supplier relationships in the construction
industry
New Zealand Government Procurement (2016) A guide to developing your procurement strategy
Jeremy Glover (2007) Framework Agreements: Practice and Pitfalls
http://fidic.org/books/plant-and-design-build-contract-2nd-ed-2017-yellow-book
Thomas, G. and Thomas, M. (2008) Construction Partnering and Integrated Teamworking
http://docplayer.net/21472350-The-fidic-suite-of-contracts.html
A Guide London 2012 Olympic and Paralympic Games the Legacy: Sustainable Procurement for
Construction Projects
Turner, A. (1997) Building Procurement (2nd ed), Palgrave Macmillan
Gerard D. Wood &Robert C. T. Ellis (Feb 2007) Main contractor experiences of partnering