This presentation focuses on contract and procurement management in the construction industry, specifically through a case study of Central Queensland University's new campus construction. It discusses different procurement methods, their advantages and disadvantages, and provides recommendations for effective project management.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
CONTRACT AND PROCUREMENT MANAGEMENT TERM1-2019 ASSESSMENT2: CASE STUDY
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
About Central Queensland University Constructing new own campus for meeting the increasing students demand. The construction includes developing a main lecture’s building. Laboratories for computer and engineering department Conference hall A motel
Procurement methods Procurement is basically referred to the term that is used for describing the activities that is taking place with the help of client for making better construction within the building or the organization. The different types of procurement methods are lump sum route, design and model , construction
Procurement route suggested by PPMP20011 Lump Sum procurement method is a traditional way of procuring construction. This includes working on a fixed lump sum price that is agreed by the workers before starting the work.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Reason behind choosing the route Suitable for developing a new site or a building Offers better strategy for small and large scales Flexible for the project Focuses on managing the activities along with stakeholders
Time and Cost It is expected that the project of CQU will get executed within 132days. The campus will be available towards the students by 2020. The total cost that is going to be spent over this project is around $85,720.00
Schedule
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Advantages Offers better result towards the users within less time. Offers better expertise towards the project Reducesclient risk by fixing the price. Huge amount of profit margin towardsthe contractor. The chances of changing orders get minimized in this type ofprocurement route.
Disadvantages Unless a team of contractors are being assigned to the company the whole system may get frustrated. Loss of control over the project tender preparation turns to be costliest activity to perform. Huge time is needed to prepare the documents
Risks with procurement method Once the control is lost over the project it becomes difficult to manage the activities It becomes difficult to make a decision at critical situations Operational decision gets complicated Stakeholders conflicts regarding interesttends to occur
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Recommendations Knowledgeable subcontractors needs to be hired Time management needs to be done effectively Stakeholder engagement needs to be improved
Methodology behind the route Lump sum route is considered to be one of the low financial risks from the perspective of management contract. This is the most commonly used standard for managing the project as it offers better flexibility toward the organization and also insures that the project is being carried out without any defect. However it is observed that this methodology offers the minimum risktowards the contractors anda huge amount of risk remains towards the clients.
Methodology behind the route This methodology offers the minimum risktowards the contractors anda huge amount of risk remains towards the clients.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Recommendation for the CQU Focus on developing a proper time based scheduleon which the project will be developed Choosing appropriate procurement method Hiring better executive Calculating exact number of accommodates
References Behrens, D., Gerwig, C., Schoormann, T. and Knackstedt, R., 2018. Managing the Procurement Process in Service Portals–An Automated Matching Approach with Demand-Side Management Methods.Enterprise Modelling and Information Systems Architectures (EMISAJ)–International Journal of Conceptual Modeling: Vol. 13, Nr. 15. De Araújo, M.C.B., Alencar, L.H. and de Miranda Mota, C.M., 2017. Project procurement management: A structured literature review.International Journal of Project Management,35(3), pp.353-377.