Running head: CONTRACTS AND PROCUREMENT
Contracts and Procurement: New Royal Adelaide Hospital
Name of the Student
Name of the University
Author’s Note:

1
CONTRACTS AND PROCUREMENT
Table of Contents
1. Introduction..................................................................................................................................2
2. Discussion....................................................................................................................................2
2.1 Part A.....................................................................................................................................2
2.2 Part B.....................................................................................................................................5
2.3 Part C.....................................................................................................................................7
3. Conclusion...................................................................................................................................9
References......................................................................................................................................10

2
CONTRACTS AND PROCUREMENT
1. Introduction
Procurement can be referred to as the core procedure to find as well as agree to different
terms and conditions for acquiring different types of goods or services from various external
sources through a tendering or a competitive bidding process (Lloyd-Walker & Walker, 2015). It
eventually includes making purchasing decision under any scarcity condition. The respective
corporations eventually define various processes that are intended in promoting fairer as well as
open competition for then business during minimization of the risks like exposure to collusion
and fraud. The major factors impact this specific procurement like handling, delivery, price
fluctuation and marginal benefits (Fleming, 2019). This report will be outlining a detailed
discussion over contracts and procurement for the popular as well as significant case scenario of
New Royal Adelaide Hospital with relevant details related to different procurement components,
complexities with suitable mitigations.
2. Discussion
2.1 Part A
2.1.1 Introduction and Summarization of the Procurement Context and Scope
The New Royal Adelaide Hospital is the largest and the most significant social
infrastructure project. The respective project was required to be made, maintained, financed as
well as provided with all types of non medical equipment and services with the help of PPP or
public private partnership arrangement (de Araújo, Alencar & de Miranda Mota, 2017). There
would be some of the most distinct and noteworthy features of this new project, which would be
providing major advantages to the customers under every distinct circumstance. The
procurement context of the project work was extremely effective and they have focused on their

3
CONTRACTS AND PROCUREMENT
project delivery on top priority (Brahm & Tarziján, 2015). The designing and construction works
are being eventually progressed by the respective subcontractor builders. There existed a lack of
proper framework for contract management present within the organization for their clinical
equipment procurement program. For several aspects of procurement, it is being analysed that
the scope, cost or time of the project modification was not subsequently agreed with the
respective Project Co and was even considered as the highest risk or threat (Walker & Rahmani,
2016). It was checked that clinical equipment procurement program could be improvised in
respect to content and frequency of the project.
There had been effective system or process for decision making, which are being timely
studied by the respective management for providing better growth scope to the respective
hospital. The project is segregated into different phases and also help out the project manager in
achieving distinct milestones eventually (Carithers et al., 2015). The issues related to
governance, cost or project delays would be removed if the procurement plan is revised and the
project work would be made much more effective and efficient. As a result, better scope of the
procurement would be gained and the project would be becoming successful.
2.1.2 Identifying the Project Procurement Components as well as Tender Evaluation
The current growth of the project is being expected to go extremely well; however there
might be some of the most distinct and important issues in their respective progress and hence
delays might be faced in the plan (Ruparathna & Hewage, 2015). Moreover, there exists some of
the most distinct and important project procurement components for the respective project of
New Royal Adelaide Hospital. These project procurement components are provided in the
following paragraphs:

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Contract & Procurement Management for Royal Adelaide Hospital Project
|4
|816
|179

Procurements and Contracts: Review of New Royal Adelaide Hospital Auditor General Report
|17
|3339
|187

Contracts and Procurement at the new Royal Adelaide Hospital
|15
|3458
|130

Contracts and Procurement
|10
|2158
|323

Contract and Procurement Management
|13
|3496
|17

Contracts and Procurement
|5
|719
|339