Corporate Database Development for First National Bank (FNB)

   

Added on  2023-06-04

15 Pages2745 Words80 Views
 | 
 | 
 | 
Name Hassan Mustafa
Subject Name Project Management Capstone
Submitted to Luke Webster
Assignment Name Business Case
Submission Date 07.10.2018
Corporate Database Development for First National Bank (FNB)_1

Table of Contents
Introduction.............................................................................................................................................3
Project Title........................................................................................................................................3
Project Aim.........................................................................................................................................3
Project Background.............................................................................................................................3
Project Benefits...................................................................................................................................3
Project Objectives...............................................................................................................................3
Project Scope...........................................................................................................................................3
Organizational Context.......................................................................................................................3
In-Scope & Out-of-Scope Items..........................................................................................................4
Project Deliverables............................................................................................................................5
Success Criteria...................................................................................................................................5
Resources............................................................................................................................................5
Linkages..............................................................................................................................................7
Risk Plan.................................................................................................................................................7
Assumptions.......................................................................................................................................7
Constraints..........................................................................................................................................7
Risk Register.......................................................................................................................................7
Work Breakdown....................................................................................................................................9
Timeframe & Milestones.......................................................................................................................10
Communication Plan.............................................................................................................................11
Change Management Plan.....................................................................................................................13
Project Team Roles...............................................................................................................................13
High Level Timeline.............................................................................................................................14
Current Knowledge and skills...............................................................................................................15
Specific area of theory...........................................................................................................................15
References.............................................................................................................................................17
Appendix...............................................................................................................................................18
Gantt chart........................................................................................................................................18
Corporate Database Development for First National Bank (FNB)_2

Introduction
Project Title
Corporate Database Development for First National Bank (FNB)
Project Aim
The aim of the project is to implement a corporate database at FNB and make sure
that the employees adapt to the changes.
Project Background
First National Bank (FNB) is one of the finest banks that are set up in the Midwest.
The bank has been involved in purchasing small banks in Ohio. The expansion of the
business operations and activities will lead to the requirements and involvement of
increased number of data sets. It will be required to implement a corporate database in
the bank.
Project Benefits
The resources of the bank will be better utilized with the implementation of
the corporate database.
The business services and operations will be streamlined leading to higher
returns on investment.
The business risks and cost of business will come down leading to higher
investor engagement and customer satisfaction levels.
Project Objectives
To successfully implement the corporate database in the First National Bank
To migrate and manage the existing information and data sets in a secure
manner
To adhere with the estimated schedule and budget for the project (Wearne,
2014)
Project Scope
Organizational Context
First National Bank (FNB) is one of the finest banks that are set up in the Midwest.
The bank has been involved in purchasing small banks in Ohio. The expansion of the
Corporate Database Development for First National Bank (FNB)_3

business operations and activities will lead to the requirements and involvement of
increased number of data sets. It will be required to implement a corporate database in
the bank. The resources of the bank will be better utilized with the implementation of
the corporate database. The business services and operations will be streamlined
leading to higher returns on investment. The business risks and cost of business will
come down leading to higher investor engagement and customer satisfaction levels
(Teller, 2013).
In-Scope & Out-of-Scope Items
The following tasks will be completed by the members of the project team:
Observation & Analysis of the Current System
Aims and Objectives Definition
Development of the Project Proposal
Meeting with Stakeholders
Project Approval
Risks Assessment and management
Scope Definition and Project Estimations
Change Management Planning
Resource Allocation
Security Planning & Communication Guidelines
Technical Infrastructure Analysis
Procurement of database and other tools
Designing of the database set-up
Setting up of the environment and infrastructure (Dalcher, 2015)
Network Compatibility and topologies
Database implementation
Syncing with other tools
Integration with BI tools
Migration of legacy data and systems
User access and permissions
Security Analysis
Trainings to the employees of FNB
Management of changes
Feedback and lessons learned
Corporate Database Development for First National Bank (FNB)_4

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Corporate Database Development for First National Bank (FNB)
|17
|3164
|382

Project Management .
|7
|1461
|85

Corporate Database Development & Implementation for First National Bank (FNB)
|15
|648
|147

Project Management Capstone
|7
|1376
|166

Status Follow up Report for MIS Project Management at First National Bank
|5
|806
|35

Project Management Capstone .
|11
|2673
|169