Coventry Rail Station Development Project Risks and Risk Response

   

Added on  2023-06-18

9 Pages2158 Words147 Views
 | 
 | 
 | 
EBUS 534
Coventry Rail Station Development Project Risks and Risk Response_1

TABLE OF CONTENTS
MAIN BODY...................................................................................................................................3
Risks.............................................................................................................................................3
REFERENCES................................................................................................................................9
Books and Journals......................................................................................................................9
Online...........................................................................................................................................9
Coventry Rail Station Development Project Risks and Risk Response_2

Objective: The main objective behind the completion of this project is to meet the needs the
demands of the travellers related to easy accessibility and more capacity in a station outside
London, UK.
Coventry rail station is looking to develop a footbridge and extend the platform canopies.
To create a second entrance for the station which will provide step free excess to the
platforms.
To develop a multi storey car parking area.
To form a bus interchange which will be connected with the building of the station.
To have improvements in the conditions of roads and including new ones.
To develop new bay platform.
MAIN BODY
Q1
This project is made to transform the Coventry station in order to create a aesthetic gateway
which will lead to the city with a more accommodation to the number of passengers. It is to build
a new entrance to the station and proper pedestrian crossing. The project management team is
working on designing and constructing work with a proper strategy and aligning with the
stakeholders while managing the whole program within the budget. The involvement of
stakeholders is given in the table.
Stakeholders\ success
factors
Time Quality Cost
Jeff
Sally
Alessandro
Risks
Working on such large project brings in many risks which can happen during the project
working. It is important to identify these risks and creating a risk response accordingly. Some of
the major risks are given below with their associated risk response.
Coventry Rail Station Development Project Risks and Risk Response_3

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Risk Management on Kilby House Renovation
|7
|1362
|76

Project Management for Education Facilities Construction | Desklib
|7
|391
|439

Risk Management and Procurement Strategy for Wembley Stadium Project
|18
|3990
|89

Risk Management Case Study 2022
|11
|2609
|23

Project Management
|27
|5005
|90

Remedial Options That Might Be Adopted To Mitigate or Prevent Caisson from Hitting and Damaging the Gas Export Line
|11
|2102
|34