Introduction
The purpose of this demolition plan is to provide the techniques and the procedures for
Blue Mountains College to follow for the safer and resourceful demolition of the New Facility
for Beauty Therapy and Complementary Health, Class Rooms and Offices. All the procedures of
work and demolition will be in line with AS2061 of the Australian Building Code.
Building Description
The project is inclusive of the demolition of a one (1) story mixed-use building. The
mixed-use building is about 2500 square feet per floor. The structure is one storey above the
setting of the ground and has two levels of the ground floor: the lower ground floor and the
ground floor with a full basement. Construction of the structure has been done on standard steel
framing having a brick exterior finish on all the external facades.

Figure 1: Building Section Details
The scope of the task in this work plan involves the demolition of the single (1) story
structure that is located in WSI Blue Mountains College, Parke St, Blue Mountains, NSW all the
way to the slab of the property where possible. Categorically, all the structures of the building
that is above the ground floor inclusive of the ground floor itself and any other extraneous non-
structural wall that is found within the basement of the building will be brought down. The
properties are two stories of the lower ground floor and the ground floor alongside the basement.
Each of the floors is 2500 square feet and the building has a perimeter of about 450 feet (Jadhav
& Dhawale, 2016). This demolition work is to be inclusive of both the interior and exterior of the
building. This will extend even to the exterior walls of the basement that will not be left
undisturbed.

Ground Floor Plan of the building to be demolished
Guideline for Demolition
i. WSI Blue Mountains College, Parke St, Blue Mountains, NSW will cooperate and attain
all the required permits among them the building permit as well as public space permit in
undertaking this task. Upon obtaining the permits, they will be posted on the site.
ii. There shall be the erection of temporary fence by others around the perimeter of the
building
iii. An engineering survey of the building structure will be conducted by WSI Blue
Mountains College, Parke St, Blue Mountains, and NSW prior to the demolition so as to
evaluate the associated structural hazards. A registered Professional Engineer will carry
out the sure vet and the results offered by the recommended body.
iv. Notification of miss utility will be done within at least 48 hours before the beginning of
any work on the site (Chen, Maiti & Agapiou, 2017).
Barricades & Hoardings
Barricades & Hoardings
Barricades & Hoardings
Scaffolds

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Demolition Plan for Blue Mountains College: Techniques and Procedures for Safer and Resourceful Demolition
|19
|3832
|470