Decommissioning project

Project budget
It is found that the decommissioning project will be successfully completed within the budget that is
round $ 199,570
WBS Task Name Duration Cost
0 Decommissioning project 815 days $ 199,570,400.00
1 Initial stage 53 days $ 94,640.00
1.2 Site access 43 days $ 78,640.00
2 Site set up 237 days $ 428,400.00
3 Resources 101 days $ 146,560.00
4 Execution activities 195 days $ 198,502,800.00
5 Monitoring and control 149 days $ 233,040.00
6 Closure and site clean up 80 days $ 164,960.00

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Project Financial Management
|5
|543
|295

prma6049 project and risk management
|10
|1344
|27

Project Management - The Project Execution Phase
|3
|374
|18

Project Management for Family Reunion: Planning, Budgeting and Resource Allocation
|12
|627
|120

Facilities management: Theory and Practice
|5
|738
|20

Report Status and Work Breakdown Structure
|6
|374
|76