DISPUTE MANAGEMENT AND CONTRACT IMPLEMENTATION
Name of the student
Name of the university
Author note
Dispute Management and Contract Implementation | Report_1

DISPUTE MANAGEMENT AND CONTRACT IMPLEMENTATION1
Introduction
The claim of the contractor for expenses and loss have an argumentative concern on
various building agreement. The claims are settled during the process of final accounting
however where there is the failure of negotiation becomes disputes with the respective parties
implement the legitimate method to decide the differences (McNamara and Sepasgozar 2018).
The claims of contractor is labelled as an appeal for additional expense reimbursement resulting
from the act of employer or employer’s representative which disrupt or delay the progress of
contractor and that which is not recuperating under the agreement. They evolve typically due to
the instruction or administrators, postponement, late information, employer's default or employer
intervention (Levin 2016).
Discussion
The claims in practice labelled findings by the respective parties as a delay which
primarily caused by employer’s team and get difficult some by shortcomings, misunderstanding
or mismanagement by sub-contractor, contractor or by both (Haapio and Siedel 2017).
Claim may evolve due to failure inefficient management of procurement procedure, for instance,
failure to make adequate planning to the project at the stage of pre-contract, delivering
insufficient data during tendering, application of the procedure of inappropriate tendering,
engaging lacking procedures of nomination and creating delay due to the deficiencies of design
team (Ashworth and Perera 2018). The conventions of public work and several conventions that
are of standard form in the application in United Kingdom that contained detailed provisions of
claims under what the sub-contractor or contractor can assert as against the supplementary party
for the expense and loss that is incurred as the consequence of disruption or delay due to
specified reasons (Akintoye, Beck and Kumaraswamy 2015). The majority of contractor alleges
Dispute Management and Contract Implementation | Report_2

DISPUTE MANAGEMENT AND CONTRACT IMPLEMENTATION2
for the disruption and delay under the contractual terms there may have simultaneous liberty at
common legislation to assert damages for the infringement of contract. Cause 30 (g) of RIAI
contract deals with the extension and delays of time envisages that the contractor is authorized
for time extension where it is held that the contractor not obtained in a reasonable time the
requisite notification from Architect for which they execute specifically in written form.
The delay caused by the artist, contractors, or tradesmen who are appointed by an
employer comes within the ambit of Clause 20 of the Act where the contractor is entitled to be
indemnified by the employer against claims evolving from the engagement of specialist (El-
Adaway et al. 2018). The legislation provides that the default or any action of the organization
delays the works progress then contractor with the period of five days of working of default or
action provide written intimation to the architect on the effect (Tayeh 2018).
The protocol of disruption and delay designate disruption as distinctive from the
disturbance of delay interruption or obstruction to normal operational process of the contractor
that is resulting in inferior efficiency (Burr 2016). The delay led to the forfeiture of profit as it
prevented the contractor from receiving income as resulting directly from the default of the
employer, for instance, inability to adopt other projects due to continuation of the deferred
project (Bock, 2015). Thus it is concluded that the disruption or delay of the contractor due to the
act of employer or his representative seek reasonable compensation for incurring additional cost
(Perera, Sutrisna and Yiu 2016).
The conception of practical completion as outlined in Building Control (Amendment)
Regulations, 2014 is attained when the building is used and taken over for the purpose that is
Dispute Management and Contract Implementation | Report_3

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Construction Law Assignment
|13
|3263
|337

Construction Contracts
|4
|562
|411