logo

Earned Value Analysis of Two Projects: Calculation of Planned and Earned Values, Actual Cost, and Cost & Schedule Variances

   

Added on  2023-06-10

4 Pages908 Words143 Views
 | 
 | 
 | 
The following presentation has been developed for forming the analysis of the earned value analysis of
the project. The two project cases and their progress values had been considered for the project. The
calculation of planned and earned values, actual cost, and cost & schedule variances had been done in
this assignment. The project activities A, B, C, and D have been evaluated for Schedule Performance
Index and Cost Performance Index for the project. The following outcomes has been seen for the
projects,
5.1
Activity
A
Budget (in
dollars)
Work Time (in
weeks)
BAC PV
Expected $150,000.00 100% 15 $150,000.00 $52,500.00
Actual $45,000.00 35% 5
Activity
B
Budget (in
dollars)
Work Time (in
weeks)
Expected $100,000.00 100% 4 $100,000.00 $45,000.00
Actual $50,000.00 45% 2
Activity
C
Budget (in
dollars)
Work Time (in
weeks)
Expected $110,000.00 100% 1 $110,000.00 $100,000.00
Actual $100,000.00 100% 3
Activity
D
Budget (in
dollars)
Work Time (in
weeks)
Expected $450,000.00 100% 6 $450,000.00 $247,500.00
Actual $200,000.00 55% 3
Total BAC $810,000.00
PV $445,000.00
Earned Value Analysis of Two Projects: Calculation of Planned and Earned Values, Actual Cost, and Cost & Schedule Variances_1

EV $421,200.00
AC $395,000.00
SV -$23,800.00
CV $26,200.00
SPI 0.95
CPI 1.07
5.2
Activit
y A
Budget (in
dollars)
Wor
k
Time (in
weeks)
BAC PV EV AC
Expect
ed
$250,000.00 47% 15 $250,000
.00
$117,500.
00
$125,000
.00
$165,000
.00
Actual $165,000.00 50% 7 CV SV CPI SPI
-
$40,000.
00
$7,500.00 0.76 1.06
Activit
y B
Budget (in
dollars)
Wor
k
Time (in
weeks)
BAC PV EV AC
Expect
ed
$190,000.00 50% 4 $190,000
.00
$95,000.0
0
$123,500
.00
$150,000
.00
Actual $150,000.00 65% 2 CV SV CPI SPI
-
$26,500.
00
$28,500.0
0
0.82 1.3
Activit
y C
Budget (in
dollars)
Wor
k
Time (in
weeks)
BAC PV EV AC
Expect
ed
$250,000.00 120
%
1 $250,000
.00
$300,000.
00
$250,000
.00
$200,000
.00
Actual $200,000.00 100 3 CV SV CPI SPI
Earned Value Analysis of Two Projects: Calculation of Planned and Earned Values, Actual Cost, and Cost & Schedule Variances_2

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Earned Value Analysis for Cost and Schedule Variances Calculation
|7
|636
|293

Earned Value Management Assignment PDF
|11
|2174
|80

Cost Estimation and Total Productive Maintenance
|8
|1335
|433

Earned Value Management
|4
|975
|92