logo

EVM Problems and Solutions 2022

   

Added on  2022-09-15

4 Pages497 Words14 Views
Running head: EARNED VALUE MANAGEMENT
EVM Problems and Solutions
Name of the Student:
Name of the University:

EARNED VALUE MANAGEMENT1
Exercise 2
a. Cost variance, schedule variance, cost performance index (CPI), and schedule
performance index (SPI) for the project
Based on the provided data,
PV = $23,000
EV= $20,000
AC = $25,000
BAC = $120,000
Terms Formula Calculation
Cost Variance (CV) CV= EV – AC = $ (20,000 – 25,000) = - $5,000
Schedule Variance
(SV)
SV= EV- PV = $ (20,000 – 23,000) = - $3,000
Cost Performance
Index (CPI)
CPI = EV/ AC = $20,000 / $25,000 = 0.8
= 80%
Schedule Performance
Index (SPI)
SPI= EV/ PV = $20,000 / $23,000 = 0.8695
= 86.95%
b. Project progressing
The project is not progressing well at all. When the value of CV is negative, then it
means the actual cost is more than its planned value. If the value of SV is negative, then it
takes long time to perform planned work (Miguel, Madria, & Polancos, 2019).
When the value of CPI is less than 100%, then the project is to be over budgeted and
if SPI is less than 100%, then the project is behind the schedule (Chen, Chen, & Lin, 2016).

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Advanced Engineering Project Management - Earned Value Management and Revised Project Plan
|28
|6641
|201

Project Management
|8
|1347
|95

Earned Value Management in Project Management
|4
|828
|264

Solution. Total project Duration = 12 weeks. Total proj
|2
|252
|2

Earned Value Management Assignment PDF
|11
|2174
|80

Earned Value Analysis for Cost and Schedule Variances Calculation
|7
|636
|293