Running head: ICTPRG502 MANAGE A PROJECT USING SOFTWARE MANAGEMENT TOOLS
ICTPRG502 Manage a Project using Software Management Tools
Name of the Student
Name of the University
Author note
ICTPRG502 Manage a Project using Software Management Tools_1
1ICTPRG502 MANAGE A PROJECT USING SOFTWARE MANAGEMENT TOOLS
Table of Contents
Introduction......................................................................................................................................3
The project...................................................................................................................................3
The objective and scope...............................................................................................................3
The project management plan..........................................................................................................4
The Team.....................................................................................................................................4
Departments.............................................................................................................................4
Technology requirements............................................................................................................5
The budget...................................................................................................................................5
Other resources............................................................................................................................6
Scheduling...................................................................................................................................7
The proposed software development methodology.........................................................................8
Agile Methodology......................................................................................................................8
Source control procedures...............................................................................................................8
Bibliography....................................................................................................................................9
ICTPRG502 Manage a Project using Software Management Tools_2
2ICTPRG502 MANAGE A PROJECT USING SOFTWARE MANAGEMENT TOOLS
Introduction
The project
The project is to develop an exclusive eCommerce website for the organization dealing
with the gifts as the product and services and allow the organization to perform all the
operational activities those need to be accomplished while delivering the products and services to
the consumers. The purpose of this project is to develop an eCommerce website that can allow
the organization to provide products and services to the consumers in an efficient and effective
manner.
The objective and scope
To develop an eCommerce website that can facilitate all the operation activities
To provide the consumers and the employees better and enhanced services and products
To enhanced the way of service and product delivery
To facilitate all the necessary operations
To effectively manage the data and information
To deliver the project within the timeline
To manage the project constraints
To limit the budget within the expected deadline
ICTPRG502 Manage a Project using Software Management Tools_3
3ICTPRG502 MANAGE A PROJECT USING SOFTWARE MANAGEMENT TOOLS
The project management plan
The Team
Departments
Business: This department will focus on the analysis of the business that can be identified
for the establishment of the strategies that can promote and support the functioning of the
organization.
Government bodies: These will be providing the necessary legal approvals on the
hosting, outsourcing, and platforms of the website including the privacy and security policies
related to the user and the services being offered to them.
Vendors: providing the platform and services including the risk handling and other
constraints necessary for the operational activities.
Resource management: the resource manager will be responsible for the management of
the resources those are necessary for the development and growth of the project.
Stakeholder management: The project manager will assure that the roles and
responsibilities of the stakeholders are well defined and the developed project can utilize the
maximum efficiency of the stakeholders.
Decision making: The project executives, managers, and partners will be responsible for
making better decision making and assuring that the taken decision is capable of fulfilling the
satisfaction of level of the users.
ICTPRG502 Manage a Project using Software Management Tools_4
4ICTPRG502 MANAGE A PROJECT USING SOFTWARE MANAGEMENT TOOLS
Technology requirements
Development platform, website development tool, database tool, .php for the
development of the back end coding. Hardware, Software, Computer Systems, network, network
configuration and other technical requirements.
The budget
Following is the milestones and budget of the project:
Task Name Duration Start Finish Cost
Ecommerce Website
development 186 days Mon 6/11/18 Mon 2/25/19 $91,420.00
Phase 1: Initiation 16 days Mon 6/11/18 Mon 7/2/18 $5,120.00
Milestone 1: draft
approval 0 days Mon 7/2/18 Mon 7/2/18 $0.00
Phase 2: Planning 45 days Tue 7/3/18 Mon 9/3/18 $18,000.00
Milestone 2: Planning
phase completed 0 days Mon 9/3/18 Mon 9/3/18 $0.00
Phase 3: Execution 71 days Tue 9/4/18 Tue 12/11/18 $36,560.00
Milestone 3:
managerial aspects
completed
0 days Tue 12/11/18 Tue 12/11/18 $0.00
Phase 3: Website
development 16 days Wed 12/12/18 Wed 1/2/19 $12,620.00
Milestone 4: Website
development completed 0 days Wed 1/2/19 Wed 1/2/19 $0.00
Phase 4: Monitoring
and controlling 12 days Thu 1/3/19 Fri 1/18/19 $5,760.00
Milestone 5:
evaluation completed 0 days Fri 1/18/19 Fri 1/18/19 $0.00
Phase 5: Quality
assurance 15 days Mon 1/21/19 Fri 2/8/19 $7,200.00
Milestone 6: quality
check completed 0 days Fri 2/8/19 Fri 2/8/19 $0.00
Phase 6: Project
Closure 11 days Mon 2/11/19 Mon 2/25/19 $6,160.00
Milestone 7:
Completed 0 days Mon 2/25/19 Mon 2/25/19 $0.00
ICTPRG502 Manage a Project using Software Management Tools_5
5ICTPRG502 MANAGE A PROJECT USING SOFTWARE MANAGEMENT TOOLS
Other resources
Resource Name Type Std. Rate
Project Manager Work $20.00/hr
Software Developer Work $10.00/hr
Technical Writer Work $5.00/hr
Resource Manager Work $10.00/hr
Business Analyst Work $10.00/hr
Market Analyst Work $10.00/hr
IT technicians Work $5.00/hr
Hardware Material $500.00
Software Material $500.00
Miscellaneous Materials Material $250.00
Network engineer Work $10.00/hr
Vendor Work $5.00/hr
ICTPRG502 Manage a Project using Software Management Tools_6

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
(PDF) Writing IT Project Proposal document
|9
|2279
|4

Building an E-commerce Presence: Strategies and Challenges
|13
|2753
|346

Project Scope Statement
|7
|1199
|259

Project Management Plan for Establishment of a New Business
|11
|1808
|472

Development Of Online Management System
|15
|2241
|40

Project Management Introduction to Project Management
|12
|2056
|362