Running head:PROJECT MANAGEMENT PLAN Project Management Plan (Empire State Building, ABC Construction Company) Name of the student: Name of the university: Author Note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1PROJECT MANAGEMENT PLAN Executive summary In the following study, ABC organization is chosen as the construction company to work on Empire State Building, USA. The study aims at convincing clients about the best builders. For this stakeholdermanagement,costmanagement,schedulemanagementandriskmanagementare analyzed for the construction project.
2PROJECT MANAGEMENT PLAN Table of Contents Introduction:..........................................................................................................................................4 1. Project description:............................................................................................................................4 1.1. Type of building:........................................................................................................................4 1.2. Intended use:...............................................................................................................................4 1.3. Delivery method and contract agreement:..................................................................................5 2. Stakeholder Management Plan:.........................................................................................................6 2.1. Stakeholder analysis:..................................................................................................................6 2.2. Suggested Communication Plan:................................................................................................6 2.3. Organization structure and chart of project team:......................................................................7 2.4. Responsibility matrix:.................................................................................................................8 3. Cost Management:.............................................................................................................................9 3.1. Estimated construction baseline cost:.........................................................................................9 3.2. Project Estimate roughly broken down by trade:.....................................................................10 3.3. Project Fee Proposal for Construction Staff Costs:..................................................................10 3.4. Project Change Management Plan:...........................................................................................11 3.5. Change Management Process Chart:........................................................................................13 4. Schedule Management:....................................................................................................................13 4.1. Schedule Qualifications, Assumptions, and Constraints:.........................................................13 4.2. Schedule Management Plan:.....................................................................................................14
Need help grading? Try our AI Grader for instant feedback on your assignments.
4PROJECT MANAGEMENT PLAN Introduction: The “Project Management Plan” or PMP demonstrates the typical responsibilities of project teams. Further, it consists of various plans developed and implemented ensuring compliances with PMP and Federal and State policy. The following research has chosen ABC Company. This is a hypothetical construction company. Here, the study aims to convince the client that they are best builders to take the project on their shoulders. Here the stakeholder management plan is analysed. Then a cost management plan is demonstrated. Schedule management is illustrated along with an investigation of risk management for the project of ABC Company. 1. Project description: 1.1. Type of building: Here, the building assigned is the Empire State Building, at New York, U.S.A. Though it is not the tallest building in New York, it is one of the most famous sites in the city. The building has the plot has been comprising of numerous of distinct owners. Its iconic spire has been developed as the port regarding airship. Thus the building has turned out to be one of the most popular and iconic landmarks. 1.2. Intended use: The United States never created the Empire State Building. The private owners and investors developed this over the site of the previous Waldorf Astoria Hotel at the 5th Avenue on the 34th street. This has been designed before the Great Depression while the economic system has been
5PROJECT MANAGEMENT PLAN blooming and the space of office was under huge demand in Manhattan. Here, at that time it has been developed since it was highly required. However, until it was finished U.S. economy collapsed and the demand for the working area stopped eventually. This has been over two decades till the site became occupied. 1.3. Delivery method and contract agreement: Delivery method: The delivery method must get success through innovation of designing and envisioning projects at the mechanical and short-term manufacturing processes. This has evolved dynamically and organically for meeting the perquisites of schedule and values. This must stand as the confirmation of the method in which the separation and industrials and commercial concerns must be differentiated ostensibly. This has been cross-fertilising the establishments of central management principles that must be adaptable to a broad range of the human endeavours co-operatively. Contract agreement: Firstly, the agreement must consider security. Here no recordable or any lost time or reportable injuries and lesser than the industry must be present. Then the schedule must be considered where the established project milestone must be met. Regarding budget, the risks must be managed to consist of the expenses under the budget. Next, as far as quality is concerned, the project requirements must have adverse effects. For budget or milestones the environment compliances the project should be completed instead of any violations. Regarding public perceptions, there must be strong support through smart communications.
6PROJECT MANAGEMENT PLAN 2. Stakeholder Management Plan: 2.1. Stakeholder analysis: Here the first organisations to construct and design the Empire State Building have been the EmpireState,owners,architect,StarrettBrosandcontractors.Theorganisationshavebeen committed to the companies to the group approach. This was influential regarding the project’s success. This background had influenced project managements close to lean principles before the lean construction got formalised. 2.2. Suggested Communication Plan: The project must achieve success by innovating of designing and envisioning projects as the short-termandself-regulatingprocessofmanufacturing.Thishasevolveddynamicallyand organically for meeting the necessities of schedule and values. This has stood as the confirmation of the method where they must ostensibly distinguish the industrial and commercial concerns. This has been cross-fertilising the establishing of core principles of project management that is adaptable to a broad range of cooperative endeavour of a human.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
7PROJECT MANAGEMENT PLAN 2.3. Organization structure and chart of project team: Figure 1: “Organization structure and chart of project team of Empire State Building” (Source: Created by Author) PresidentAdministration(Accountinggeneraladministrationpayroll,publicrelations,purchasing)ConstructionProjectmanagerBusiness(accounting,administration,payroll)Engineering(changes,claims,costandp[rograms,engineering,plantdesign)Equipment(maintaninence,shopoperations)Purchasing(expedicting,purchasing,warehousisng)SpecialStaff(laborrelationssafety)Superintendent(cpsttructionforces)Engineering(Design,estimating,planning,scheduling)Specialstaff(Laborrelations,legalcounselandsafety)
8PROJECT MANAGEMENT PLAN 2.4. Responsibility matrix: Responsibility Matrix Project Name: Project Manager: Stakeholders WBS ActivitiesNameNameNameNameNameNameName Project Mgr Sponso r Tech Lead Financ e IT Analyst Business Lead Testin g Initiation (Concept Phase) Project RequestP SS-S--- Define Objectives, Deliverables AAI-I- Project Organization AII-II Cost EstimatePPIAIPI Risk Assessment PIPPPP Justification statement IPIII- Develop Project Charter ASSSISI
9PROJECT MANAGEMENT PLAN Code AAccountableResponsible for success/failure of this activity PParticipantActivelyparticipatesinthe activity RReview Required Thispersonmustreviewtheoutputofthis activity IInput RequiredProject Team needs input from this person in this activity SSign-off Required Mustsign-offtheappropriate document 3. Cost Management: 3.1. Estimated construction baseline cost: 01/01/18Delphicost estimation $ 500.0 0 $ 600.00 $ 700.00 $ 600.00 Vendor 01/02/18Empiricalcosting methods $ 400.0 0 $ 500.00 $ 800.00 $ 533.33 Hours, Rate, 01/03/18Reserve analysis$ 300.0 $ 400.00 $ 680.00 $ 430.00 Hours, Rate,
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
10PROJECT MANAGEMENT PLAN 0 01/04/18Resource costing$ 200.0 0 $ 300.00 $ 450.00 $ 308.33 AdditionalItem Details 01/05/18Three-point estimating $ 100.0 0 $ 200.00 $ 480.00 $ 230.00 Vendor, Rep, 3.2. Project Estimate roughly broken down by trade: Moreover, different alterations in construction projects have been very much standard. This has been happening from various sources, causes at any phase of the project. This has been possessing considerable adverse effects over items like schedule and cost delays. Further, any critical change has been causing constant delays at project schedule and re-estimation of activity statement. Moreover, there have been additional demands of overtime, labour, materials, and types of equipment. Further, there have been changes solved though formalised changing methods. This has been turning out as the primary source of different contract disputes. This has been a necessary risk that has contributed to the failure of a project. Different classifications of the changes as per standard terms have applied to changes in the domain of construction. Thus from time, the changes have been emerging and anticipated, reactive and proactive, post-fixity and pre-fixity. From necessitiesofchanges,therehavebeenelective,non-discretionary,discretionary,required preferential regulatory. Besides, as the construction industry has been from projects, the most effectivecategorisationhasbeenanalysingchangesinthecontextofstagesandphasesin construction projects.
11PROJECT MANAGEMENT PLAN 3.3. Project Fee Proposal for Construction Staff Costs: ABC Company must design a change management toolkit for Empire State Building including change dependency system, change prediction applications, workflow tools and an active knowledge management principle. A requirement design relationship has been enabling traceable tolls regarding architectural design. Here, they must develop a prototype. A system dynamics is proposed for creating models of dynamic projects for assisting control and planning of Empire State Building. Here, the dynamic project model has been capturing various non-values to incorporate iterations of change. This includes managerial change cycle and reworks cycle. This simulation can be demonstrated through this case study, and various policies and options can be summarised from this case. Some primary outcomes over proactive changes are present on the change management around the integrated system of change management. This has been consisting of the prediction which is based on fuzzy logic change models. This system dynamics model has been on the based on control methodology and dynamic planning. Here, a “change order management” system and “web- based project management” is mainly created to cope with various changes during the construction project of Empire State Building. Moreover,standardwebtechnologiesareutilisedandvariouschangeorderprocess construction projects. This has been including documents, roles-actors, keeping records and a centralised database is being developed. Further, a change control tool (CCT) can be created that has beenconsistingofrequirementtraceabilityacrosslinksbetweenbuildingdesignandclient requirements. It is also believed that various changes or effects of revisions are managed through capturing client necessities correctly at the starting of the project and through traceability of requirements that have been created afterwards.
12PROJECT MANAGEMENT PLAN 3.4. Project Change Management Plan: The changes in projects and adjustments have always been inevitable as they are the real-life stages of construction and designs. According to the report of “Engineering and Physical Sciences Research Council, at U.K.” it is revealed that more one third amount of the clients has been seen to be dissatisfied with their contractors. This has been kept to the quoted time and price, solving defects and supplying the ultimate product of the needed quality. This can also be concluded that the dissatisfaction of those clients has been the reason changing orders that have been run through construction projects. Moreover, the effort of managing the changing orders has been imposed to the high burden of project management and has been the nightmare of industry people whom people never intended to face. Changes in instruction have been causing severe ethical disputes and problems. As per the ethical survey conducted in 2004, about 80% of the respondents have revealed that they have been encountering cases that are being seen as unethical to deal with business. 61% of the people said that immoral acts had tainted the industry. Moreover, the owners have been blamed to bid shopping and playing various tricks regarding tricks in payments. Here, the contractors have been accused of overbilling, playing change-order games and front-end leading. Further, the change in management has been a genuine issue based on applications and needed innovation in engineering for solving those issues. Thus, by the examination of change of construction in the areas of management and then pressing necessities from industry and scarcity of software tools and pieces of literature at this area has posted the promising scope regarding developments and researches at construction sector.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
13PROJECT MANAGEMENT PLAN Rejection Received Accept Change Update Project Management Plan Implement change Change Type Accept change Change Screening Change proposal Change control Board Review 3.5. Change Management Process Chart: The following diagram illustrates how to deal with the changes in construction: Figure 2: “Change Management Process Chart” (Source: Created by Author) 4. Schedule Management: 4.1. Schedule Qualifications, Assumptions, and Constraints: Here, the qualification standards are expected to recognize applications that must perform successful on the job and screening out those unlikely doing so. The assumptions are been made to be true. However, this has been not necessarily ending up being true. This has been impacting the
14PROJECT MANAGEMENT PLAN current construction project in significant way. Moreover, they have been incorporating risks. The constraints, on the other hand are the restrictions included on the project like cost limitations, resourcesandschedules.ABChasneededtoworkunderboundarieslimitedthroughthose constraints. These constraints has been identified and defined at the starting of the project. 4.2. Schedule Management Plan: The time and schedule project management has been liable of private partners and is the domain of professionals on PP projects. This has been notable significance to government. At the PPS, Government of United States has been depending on completing date for scheduled move-in. 4.3. Rough Baseline Schedule: Task NameDurationStartFinishPredecessors Foundation505 daysMon 5/21/18 Fri 4/24/20 Excavate for foundations92 daysMon 5/21/18 Fri 9/28/18 Forming walls of basement2 daysMon 10/1/18 Tue 10/2/18 2 Putting concrete foundations192 daysWed 10/3/18 Fri 7/5/193 Performing foundation inspection110 daysMon 7/8/19 Fri 12/6/19 4 Backfill foundation100 daysMon 12/9/19 Fri 4/24/20 5 Framing5 daysMonFri 5/1/206
15PROJECT MANAGEMENT PLAN 4/27/20 Drying4 daysMon 5/4/20 Thu 5/7/20 7 Exterior finishes4 daysFri 5/8/20 Wed 5/13/20 8 Utility rough-ins5 daysThu 5/14/20 Wed 5/20/20 9 Landscaping and grounds work2 daysThu 5/21/20 Fri 5/22/20 10 Final acceptance4 daysMon 5/25/20 Thu 5/28/20 11 Figure 3: “Gantt Chart for the project of Empirical State Building” (Source: Created by Author)
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
16PROJECT MANAGEMENT PLAN 5. Risk Management: 5.1. Risk Management Plan: For ABC Company this has enormously complicated and heterogamous. Here, there have been various categorizations of construction differing markedly from others like an industrial highway, massive, non-residential building and housing. The constructing of projects has included renovations,demolitionsandconstructionsfornon-residentialandresidentialprojects.These parameters of success for the plans have been within time completion under particular requirements and budget performance or technical requirements. Here, the primary challenges for achievements have been the change under project environment. This issue has been multiplying the project size as various uncertainties at the project outcome rise with a waist. Here the construction project has been exposed to multiple uncertain scenarios due to large factors like construction complexity, planning and designing. This has included different groups of interests like suppliers, contractors, consultants and owners. This has also included resources like funds, types of equipment, materials and workforce.Moreover, it has consisted of political and economic statutory and environmental regulations. 5.2. Risk Register: Probabilit y Project Severit y Mitigation measuresOwnershi p Adjuste d Impact Adjusted Probabilit y Adjuste d Severity MMECI processProject Manager MLL MHFundsreleasedin advanceof Project Manager MMM
17PROJECT MANAGEMENT PLAN constructionto faciliateplacingof orders. HHConsideralternatives toenableearlyStats Work ContractorHMH HHCloseLiaisonand dedicated Utilities ContractorHMH MHContractortoengage supply chain ContractorMMM MHAgreesuitable programandmanage costs and timescales Contractor and Project Manager MMM LMSite procedures to be defined Project Manager MMM MHSystemtobe establishedsuchthat financialandcost management risk Contractor and Project Manager MMM 5.3. Logistics Plan: Significant HazardAvoidControls RestrictedsiteaccessandLocateofficesandwelfare facilitiesandotherareasof Ensureeffectiveinspection andmaintenanceprocedures
18PROJECT MANAGEMENT PLAN room around site Areas of restricted visibility, width, or weight limits frequentpedestrianactivity away from primary site traffic routes are put in place 5.4. Primary Safety measures in Logistic Plan: EgressABC Company must describe precautions and restrictions and consider that there are secured means of access. This is the vehicular access to sites and confined spaces. They must also incorporate construction workers to continue various hazardous areas of the current structure of Empire State Building. They must be aware that the workers have been falling from fragile roofs or floors such that multiple regions are identified that can be made secured. Besides, they must regard access to site traffic around current structures, pavements and roads. They must attempt separation of operatives, plants and vehicles. Fire extinguishers This has been vital to maintain and inspect the extinguishers periodically. As the fire extinguisher has not been sufficient as needed, there must be proper pressure gauge. It must be indicated that extinguisher gets charged. Moreover, they must understand the water drum or the extinguisher to get a freeze. Here, at least worker at every shift must be trained regarding how to use that fire extinguisher and then taught about extinguishers used on that kind of fires. This first order of priority is known as the fire department. Moreover, the local fire department has been able to help the employees get trained on how to utilise those extinguishers. They must also be made aware of the flammable hazardous and chemical substances to be used on site. FencingThe materials and construction of types of equipment have been precious and
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
19PROJECT MANAGEMENT PLAN has been very tempting for trespassers who never have the means of transporting them to off-site. By creating security, fencing has been eradicating risks. Further, the protection of public has been one of the essential functions for fulfilling constructionsitefencing.Moreover,mostpeoplehavebeenunknowingly trespassingthemalicioussite.However,thathasbeenwanderingtothat accidentally. This has been mainly as they are in a hurry to get into anywhere else. Empire State Building construction site has been a highly populated area. This has been important to fence that off for preventing people from walking around that en-route for those destinations. Conclusion: There have been various scopes arising to mitigate and reduce adverse environmental effects to modify and repair the current project that must be overlooked. The environmental considerations must be incorporated while planning is to be altered and improved the contemporary constructions and create more. Additional attention must be established to analyze, plan, monitor and predict the cumulative impacts of roads. In various cases, the proper spatial scales for that analysis must cross different state boundaries. Particularly in those cases, the cooperation and collaboration among various state agencies can be helpful.