This article on Desklib provides insights into the work breakdown structure, project milestones, and Gantt chart for the Warka Water Tower project. It covers the completion of research and development phase, testing phase, pilot installation phase, and project closure phase. The article also includes a detailed description of the different milestones and tasks involved in the project.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head: ENGINEERING MANAGEMENT
Engineering management: Warka Water Tower
Name of the student:
Name of the university:
Engineering management: Warka Water Tower
Name of the student:
Name of the university:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1ENGINEERING MANAGEMENT
Part 4: Work Breakdown Structure, project Milestones and Gantt chart
v
Figure 1: Work Breakdown structure for Warka Water Tower Project
(Source: Created by author)
This project has 5 different milestones or work packages and the project milestones are as
follows:
Milestone 1: Completion of project kickoff phase
This is the initial phase of the Warka Water Tower development phase. This particular
phase is divided in small subparts that deal with selection of location, investigation of site. Based
Part 4: Work Breakdown Structure, project Milestones and Gantt chart
v
Figure 1: Work Breakdown structure for Warka Water Tower Project
(Source: Created by author)
This project has 5 different milestones or work packages and the project milestones are as
follows:
Milestone 1: Completion of project kickoff phase
This is the initial phase of the Warka Water Tower development phase. This particular
phase is divided in small subparts that deal with selection of location, investigation of site. Based
2ENGINEERING MANAGEMENT
on the water supply issues in that particular location, the Warka water tower should be installed.
Primarily, just after developing the idea of the concept a prototype will be prepared in this phase.
Obviously that particular prototype should be approved by the project manager and project
sponsors.
Milestone 2: Completion of requirement gathering phase
Before the development of the Warka tower design, all necessary requirements are to be
gathered by the project managers and project developers. It is the responsibility of the project
manager to implement the Water in such as a way so that it could meet the criteria of the tower
that is followed all over. After the development of a full scaled prototype by testing the materials
the final construction of the Warka water tower will be prepared.
WBS Task Name Duration Start Finish Cost
0 Warka water tower
project planning 138 days Tue 4/10/18 Thu 10/18/18 $174,880.00
1 Project kickoff 14 days Tue 4/10/18 Fri 4/27/18 $23,520.00
1.1
Selection of location
where the Warka water
tower will be developed
2 days Tue 4/10/18 Wed 4/11/18 $2,240.00
1.2 Site investigation 4 days Thu 4/12/18 Tue 4/17/18 $7,040.00
1.3
Identification of
water issues in that
location
3 days Wed 4/18/18 Fri 4/20/18 $4,800.00
1.4 Development of
project concept 5 days Mon 4/23/18 Fri 4/27/18 $5,600.00
1.5 Preparing ½ scaled
prototype 4 days Mon 4/23/18 Thu 4/26/18 $3,840.00
1.6
Milestone 1:
Completion of project
kickoff
0 days Fri 4/27/18 Fri 4/27/18 $0.00
2 Requirement
gathering and analysis 28 days Mon 4/30/18 Wed 6/6/18 $34,880.00
2.1 Full scale prototype
development 2 days Mon 4/30/18 Tue 5/1/18 $1,920.00
2.2 Testing materials (PE 4 days Wed 5/2/18 Mon 5/7/18 $3,840.00
on the water supply issues in that particular location, the Warka water tower should be installed.
Primarily, just after developing the idea of the concept a prototype will be prepared in this phase.
Obviously that particular prototype should be approved by the project manager and project
sponsors.
Milestone 2: Completion of requirement gathering phase
Before the development of the Warka tower design, all necessary requirements are to be
gathered by the project managers and project developers. It is the responsibility of the project
manager to implement the Water in such as a way so that it could meet the criteria of the tower
that is followed all over. After the development of a full scaled prototype by testing the materials
the final construction of the Warka water tower will be prepared.
WBS Task Name Duration Start Finish Cost
0 Warka water tower
project planning 138 days Tue 4/10/18 Thu 10/18/18 $174,880.00
1 Project kickoff 14 days Tue 4/10/18 Fri 4/27/18 $23,520.00
1.1
Selection of location
where the Warka water
tower will be developed
2 days Tue 4/10/18 Wed 4/11/18 $2,240.00
1.2 Site investigation 4 days Thu 4/12/18 Tue 4/17/18 $7,040.00
1.3
Identification of
water issues in that
location
3 days Wed 4/18/18 Fri 4/20/18 $4,800.00
1.4 Development of
project concept 5 days Mon 4/23/18 Fri 4/27/18 $5,600.00
1.5 Preparing ½ scaled
prototype 4 days Mon 4/23/18 Thu 4/26/18 $3,840.00
1.6
Milestone 1:
Completion of project
kickoff
0 days Fri 4/27/18 Fri 4/27/18 $0.00
2 Requirement
gathering and analysis 28 days Mon 4/30/18 Wed 6/6/18 $34,880.00
2.1 Full scale prototype
development 2 days Mon 4/30/18 Tue 5/1/18 $1,920.00
2.2 Testing materials (PE 4 days Wed 5/2/18 Mon 5/7/18 $3,840.00
3ENGINEERING MANAGEMENT
meshes and Juncus)
2.3 Development of
parametric design 5 days Tue 5/8/18 Mon 5/14/18 $5,600.00
2.4 Concept development
phase 3 days Tue 5/15/18 Thu 5/17/18 $6,240.00
2.5 Optimization of
material 5 days Fri 5/18/18 Thu 5/24/18 $3,200.00
2.6 Transport and
modularity development 3 days Fri 5/25/18 Tue 5/29/18 $6,720.00
2.7 Lightening material
optimization 4 days Fri 5/25/18 Wed 5/30/18 $2,560.00
2.8
Prototype
construction and contract
sign agreement
5 days Thu 5/31/18 Wed 6/6/18 $4,800.00
2.9
Milestone 2:
Completion of milestone
gatherimg and analysis
phase
0 days Wed 6/6/18 Wed 6/6/18 $0.00
3
Research and
development of the
implementation
34 days Thu 6/7/18 Tue 7/24/18 $42,400.00
3.1 Development of
design 2 days Thu 6/7/18 Fri 6/8/18 $1,920.00
3.2 Developing collector 3 days Mon 6/11/18 Wed 6/13/18 $6,240.00
3.3 Material upgradation
to bamboo 7 days Thu 6/14/18 Fri 6/22/18 $4,480.00
3.4 Design and
development of workino 6 days Mon 6/25/18 Mon 7/2/18 $5,760.00
3.5 Wind testing and
rope network designing 5 days Tue 7/3/18 Mon 7/9/18 $8,800.00
3.6 Launching
crowdfunding 5 days Tue 7/10/18 Mon 7/16/18 $5,600.00
3.7 Crowdfunding
campaign 4 days Tue 7/10/18 Fri 7/13/18 $3,840.00
3.8
Workino
development and rain
water collection
6 days Tue 7/17/18 Tue 7/24/18 $5,760.00
3.9
Milestone 3:
Completion of research
and development phase
0 days Tue 7/24/18 Tue 7/24/18 $0.00
4 Design testing 41 days Wed 7/25/18 Wed 9/19/18 $47,840.00
4.1 Testing phase 1 24 days Wed 7/25/18 Mon 8/27/18 $28,320.00
4.1.1 Fog harvesting for 5 days Wed 7/25/18 Tue 7/31/18 $8,000.00
meshes and Juncus)
2.3 Development of
parametric design 5 days Tue 5/8/18 Mon 5/14/18 $5,600.00
2.4 Concept development
phase 3 days Tue 5/15/18 Thu 5/17/18 $6,240.00
2.5 Optimization of
material 5 days Fri 5/18/18 Thu 5/24/18 $3,200.00
2.6 Transport and
modularity development 3 days Fri 5/25/18 Tue 5/29/18 $6,720.00
2.7 Lightening material
optimization 4 days Fri 5/25/18 Wed 5/30/18 $2,560.00
2.8
Prototype
construction and contract
sign agreement
5 days Thu 5/31/18 Wed 6/6/18 $4,800.00
2.9
Milestone 2:
Completion of milestone
gatherimg and analysis
phase
0 days Wed 6/6/18 Wed 6/6/18 $0.00
3
Research and
development of the
implementation
34 days Thu 6/7/18 Tue 7/24/18 $42,400.00
3.1 Development of
design 2 days Thu 6/7/18 Fri 6/8/18 $1,920.00
3.2 Developing collector 3 days Mon 6/11/18 Wed 6/13/18 $6,240.00
3.3 Material upgradation
to bamboo 7 days Thu 6/14/18 Fri 6/22/18 $4,480.00
3.4 Design and
development of workino 6 days Mon 6/25/18 Mon 7/2/18 $5,760.00
3.5 Wind testing and
rope network designing 5 days Tue 7/3/18 Mon 7/9/18 $8,800.00
3.6 Launching
crowdfunding 5 days Tue 7/10/18 Mon 7/16/18 $5,600.00
3.7 Crowdfunding
campaign 4 days Tue 7/10/18 Fri 7/13/18 $3,840.00
3.8
Workino
development and rain
water collection
6 days Tue 7/17/18 Tue 7/24/18 $5,760.00
3.9
Milestone 3:
Completion of research
and development phase
0 days Tue 7/24/18 Tue 7/24/18 $0.00
4 Design testing 41 days Wed 7/25/18 Wed 9/19/18 $47,840.00
4.1 Testing phase 1 24 days Wed 7/25/18 Mon 8/27/18 $28,320.00
4.1.1 Fog harvesting for 5 days Wed 7/25/18 Tue 7/31/18 $8,000.00
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
4ENGINEERING MANAGEMENT
mesh development
4.1.2 Water filter testing 4 days Wed 8/1/18 Mon 8/6/18 $4,480.00
4.1.3 Fog harvesting test 6 days Tue 8/7/18 Tue 8/14/18 $5,760.00
4.1.4 Development of
canopy 4 days Wed 8/15/18 Mon 8/20/18 $4,480.00
4.1.5 Gathered data
analysis 5 days Tue 8/21/18 Mon 8/27/18 $5,600.00
4.2 Testing phase 2 17 days Tue 8/28/18 Wed 9/19/18 $19,520.00
4.2.1 Water storage
distribution 3 days Tue 8/28/18 Thu 8/30/18 $2,880.00
4.2.2 Dew collection 4 days Fri 8/31/18 Wed 9/5/18 $3,840.00
4.2.3 Construction and
maintenance manual 5 days Thu 9/6/18 Wed 9/12/18 $4,800.00
4.2.4 Evaluation and
design finalization 5 days Thu 9/13/18 Wed 9/19/18 $8,000.00
4.2.5
Milestone 4:
Completion of project
testing phase
0 days Wed 9/19/18 Wed 9/19/18 $0.00
5 Pilot installation 12 days Thu 9/20/18 Fri 10/5/18 $18,080.00
5.1 3 pilot installation for
various location 5 days Thu 9/20/18 Wed 9/26/18 $8,800.00
5.2 Monitoring trial 4 days Thu 9/27/18 Tue 10/2/18 $4,480.00
5.3 Material testing 3 days Wed 10/3/18 Fri 10/5/18 $4,800.00
5.4
Milestone 5:
Completion of pilot
installation phase
0 days Fri 10/5/18 Fri 10/5/18 $0.00
6 Project closure 9 days Mon 10/8/18 Thu 10/18/18 $8,160.00
6.1 Stakeholders signoff 5 days Mon 10/8/18 Fri 10/12/18 $5,600.00
6.2 Final submission of
document 4 days Mon
10/15/18 Thu 10/18/18 $2,560.00
6.3
Milestone 6:
Completion of project
closure phase
0 days Thu 10/18/18 Thu 10/18/18 $0.00
Milestone 3: Completion of research and development phase
Research and development is the third milestone of project development phase. It is the
responsibility of the project head to test the data after gathering it from different resources.
Warka water tower is a natural water tower which is comprises of bamboo, rope etc. Even, the
mesh development
4.1.2 Water filter testing 4 days Wed 8/1/18 Mon 8/6/18 $4,480.00
4.1.3 Fog harvesting test 6 days Tue 8/7/18 Tue 8/14/18 $5,760.00
4.1.4 Development of
canopy 4 days Wed 8/15/18 Mon 8/20/18 $4,480.00
4.1.5 Gathered data
analysis 5 days Tue 8/21/18 Mon 8/27/18 $5,600.00
4.2 Testing phase 2 17 days Tue 8/28/18 Wed 9/19/18 $19,520.00
4.2.1 Water storage
distribution 3 days Tue 8/28/18 Thu 8/30/18 $2,880.00
4.2.2 Dew collection 4 days Fri 8/31/18 Wed 9/5/18 $3,840.00
4.2.3 Construction and
maintenance manual 5 days Thu 9/6/18 Wed 9/12/18 $4,800.00
4.2.4 Evaluation and
design finalization 5 days Thu 9/13/18 Wed 9/19/18 $8,000.00
4.2.5
Milestone 4:
Completion of project
testing phase
0 days Wed 9/19/18 Wed 9/19/18 $0.00
5 Pilot installation 12 days Thu 9/20/18 Fri 10/5/18 $18,080.00
5.1 3 pilot installation for
various location 5 days Thu 9/20/18 Wed 9/26/18 $8,800.00
5.2 Monitoring trial 4 days Thu 9/27/18 Tue 10/2/18 $4,480.00
5.3 Material testing 3 days Wed 10/3/18 Fri 10/5/18 $4,800.00
5.4
Milestone 5:
Completion of pilot
installation phase
0 days Fri 10/5/18 Fri 10/5/18 $0.00
6 Project closure 9 days Mon 10/8/18 Thu 10/18/18 $8,160.00
6.1 Stakeholders signoff 5 days Mon 10/8/18 Fri 10/12/18 $5,600.00
6.2 Final submission of
document 4 days Mon
10/15/18 Thu 10/18/18 $2,560.00
6.3
Milestone 6:
Completion of project
closure phase
0 days Thu 10/18/18 Thu 10/18/18 $0.00
Milestone 3: Completion of research and development phase
Research and development is the third milestone of project development phase. It is the
responsibility of the project head to test the data after gathering it from different resources.
Warka water tower is a natural water tower which is comprises of bamboo, rope etc. Even, the
5ENGINEERING MANAGEMENT
water stored in the water collector is also collected from environment such like rain water, dew
fog etc.
Milestone 4: Completion of testing phase
After collecting data from different sources, proper testing of the application is needed to
be done. In order to harvest the fog a mesh has to be developed which is also tested in this phase.
Apart from this, the water filter was tested and also a canopy is developed and tested in this
phase. A water storage distribution application system was also added and tested including dew
collector testing and its evaluation and development.
Milestone 5: Completion of pilot installation phase
This is the fifth phase of Warka water tower development project. The pilot installation
phase is again consists of two activities such as monitoring trial, material testing.
Milestone 6: Completion of project closure phase
The project closure phases the last phase of the Warka water tower development which is
consists of stakeholders’ signoff, final submission of the final document and post maintenance of
the tower. The basement of the water tower is though quite strong but still certain maintenance
steps are needed to be undertaken to avoid natural impact. The basement and other material
should be covered with proper materials to protect the Warka water tower.
water stored in the water collector is also collected from environment such like rain water, dew
fog etc.
Milestone 4: Completion of testing phase
After collecting data from different sources, proper testing of the application is needed to
be done. In order to harvest the fog a mesh has to be developed which is also tested in this phase.
Apart from this, the water filter was tested and also a canopy is developed and tested in this
phase. A water storage distribution application system was also added and tested including dew
collector testing and its evaluation and development.
Milestone 5: Completion of pilot installation phase
This is the fifth phase of Warka water tower development project. The pilot installation
phase is again consists of two activities such as monitoring trial, material testing.
Milestone 6: Completion of project closure phase
The project closure phases the last phase of the Warka water tower development which is
consists of stakeholders’ signoff, final submission of the final document and post maintenance of
the tower. The basement of the water tower is though quite strong but still certain maintenance
steps are needed to be undertaken to avoid natural impact. The basement and other material
should be covered with proper materials to protect the Warka water tower.
6ENGINEERING MANAGEMENT
Figure 2: Gantt chart for Warka Water Tower Project
(Source: Created by author)
Figure 2: Gantt chart for Warka Water Tower Project
(Source: Created by author)
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
7ENGINEERING MANAGEMENT
References
[1].Broniarz-Press, L., Rozanski, J., Rozanska, S. and Kmiecik, J.,. Właściwości reologiczne
warstwy powierzchniowej cieczy wybranych piw komercyjnych. Żywność Nauka
Technologia Jakość, 21(4)., 2014
[2].Fenyvesi, K., Park, H.G., Choi, T., Song, K. and Ahn, S. Modelling Environmental Problem-
Solving Through STEAM Activities: 4Dframe's Warka Water Workshop. In Bridges
Conference Proceedings;. Tessellations Publishing., 2016.
[3].Fenyvesi, K., Park, H.G., Choi, T., Song, K. and Ahn, S. Modelling Environmental Problem-
Solving Through STEAM Activities: 4Dframe's Warka Water Workshop. In Bridges
Conference Proceedings;. Tessellations Publishing., 2016.
[4].Havsteen-Mikkelsen, G.E. Symbiosis of human and water in the anthropocene (Doctoral
dissertation)., 2017.
[5].Le Grange, L. Regional Spatial Development Framework for Saldanha Bay Municipality:
pursuing a more ecologically integrated future (Doctoral dissertation, University of Cape
Town)., 2016.
[6].Nadali, D. and Polcaro, A. THE SKY FROM THE HIGH TERRACE: STUDY ON THE
ORIENTATION OF THE ZIQQURAT IN ANCIENT MESOPOTAMIA. Mediterranean
Archaeology & Archaeometry, 16(4).,2016.
References
[1].Broniarz-Press, L., Rozanski, J., Rozanska, S. and Kmiecik, J.,. Właściwości reologiczne
warstwy powierzchniowej cieczy wybranych piw komercyjnych. Żywność Nauka
Technologia Jakość, 21(4)., 2014
[2].Fenyvesi, K., Park, H.G., Choi, T., Song, K. and Ahn, S. Modelling Environmental Problem-
Solving Through STEAM Activities: 4Dframe's Warka Water Workshop. In Bridges
Conference Proceedings;. Tessellations Publishing., 2016.
[3].Fenyvesi, K., Park, H.G., Choi, T., Song, K. and Ahn, S. Modelling Environmental Problem-
Solving Through STEAM Activities: 4Dframe's Warka Water Workshop. In Bridges
Conference Proceedings;. Tessellations Publishing., 2016.
[4].Havsteen-Mikkelsen, G.E. Symbiosis of human and water in the anthropocene (Doctoral
dissertation)., 2017.
[5].Le Grange, L. Regional Spatial Development Framework for Saldanha Bay Municipality:
pursuing a more ecologically integrated future (Doctoral dissertation, University of Cape
Town)., 2016.
[6].Nadali, D. and Polcaro, A. THE SKY FROM THE HIGH TERRACE: STUDY ON THE
ORIENTATION OF THE ZIQQURAT IN ANCIENT MESOPOTAMIA. Mediterranean
Archaeology & Archaeometry, 16(4).,2016.
8ENGINEERING MANAGEMENT
References
References
1 out of 9
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.