Engineering Risk Management: Lessons from the Tianjin China Explosion
VerifiedAdded on 2023/06/14
|11
|2520
|379
AI Summary
This article discusses the Tianjin China Explosion and the lessons learned from it in terms of engineering risk management. It covers the causes and effects of the disaster, how it could have been avoided, and the risks involved and their analysis. The article also provides a plan for measuring and monitoring the performance of risk management plan and the process used to analyze strategic issues.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head: ENGINEERING RISK MANAGEMENT
1
ENGINEERING RISK MANAGEMENT
Name
Institutional Affiliation
1
ENGINEERING RISK MANAGEMENT
Name
Institutional Affiliation
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
ENGINEERING RISK MANAGEMENT 2
Tianjin China Explosion
Introduction
The Tianjin China Explosion occurred on the 12th August of 2015.It involved a series of
explosions that killed 173 people and many more were injured in the warehouse at the shipping
port (Huang & Zhang, 2015). The explosion occurred in a range of 30 seconds. The second blast
had more impact and involved the discharge of 800 tons of ammonium nitrate. The first fires
caused added explosions over the weekend till 15th (Fu et al, 2016).
What went wrong?
This warehouse had containers with very dangerous chemicals that were flammable
which included ammonium nitrate, sodium nitrate, calcium carbide and sodium cyanide.
Firefighters sprayed water on certain chemicals when trying to control the blaze which
led to increased blasts (Jing, 2015).
Cause/effect of the disaster
Calcium carbide is a chemical that was in the warehouse reacted with the sprayed water
resulting to acetylene which is highly reactive. This said acetylene ignited other chemicals to
blast (Aitao & Lingpang, 2017).
The disaster in question destroyed many goods in the port located at Binhai New District.
Many large shipping containers were thrown into the air where they were crumpled by the
detonations. Due to this the port remained partially closed since only one side of the port was
destroyed. This still affected the north as a whole because the port is used as a gateway for most
Tianjin China Explosion
Introduction
The Tianjin China Explosion occurred on the 12th August of 2015.It involved a series of
explosions that killed 173 people and many more were injured in the warehouse at the shipping
port (Huang & Zhang, 2015). The explosion occurred in a range of 30 seconds. The second blast
had more impact and involved the discharge of 800 tons of ammonium nitrate. The first fires
caused added explosions over the weekend till 15th (Fu et al, 2016).
What went wrong?
This warehouse had containers with very dangerous chemicals that were flammable
which included ammonium nitrate, sodium nitrate, calcium carbide and sodium cyanide.
Firefighters sprayed water on certain chemicals when trying to control the blaze which
led to increased blasts (Jing, 2015).
Cause/effect of the disaster
Calcium carbide is a chemical that was in the warehouse reacted with the sprayed water
resulting to acetylene which is highly reactive. This said acetylene ignited other chemicals to
blast (Aitao & Lingpang, 2017).
The disaster in question destroyed many goods in the port located at Binhai New District.
Many large shipping containers were thrown into the air where they were crumpled by the
detonations. Due to this the port remained partially closed since only one side of the port was
destroyed. This still affected the north as a whole because the port is used as a gateway for most
ENGINEERING RISK MANAGEMENT 3
imported and exported goods to Northern China. The restricted movement and strict checking
slowed down activities affecting some industries that relied on the port.
Many cars in the ports` logistics park were destroyed by the fireball.1500 of Renault’s
cars and the 4000 of Hyundai cars were on site hence destroyed altogether.
The waves of the blasts moved even to residential areas shattering windows and even tearing
apart door hinges. Residents of the area neighboring the port had to flee their homes into local
schools for refuge. More than 720 people were hospitalized as a result of being critically injured.
How it could have been avoided
The blasts could have been avoided if there were transparency and a time information.
Information about the dangerous chemical should have been conveyed to the respective people
so as to protect human rights or even create awareness about them. Conveying the information
would have mitigated the risk and prevented the disaster as well.
Lesson learned from the explosion
Most people that gave the lessons included the insurers, those involved in loss adjusting
and also reinsurers.
There should be a change in the thinking of accumulation of risk. Many insurers and
reinsurers got exposed to many claims at a go. Claims from policyholders and many
business lines. This is because the blast affected people, property, vehicles, marine and
also infrastructure. Too much risk was accumulated.
imported and exported goods to Northern China. The restricted movement and strict checking
slowed down activities affecting some industries that relied on the port.
Many cars in the ports` logistics park were destroyed by the fireball.1500 of Renault’s
cars and the 4000 of Hyundai cars were on site hence destroyed altogether.
The waves of the blasts moved even to residential areas shattering windows and even tearing
apart door hinges. Residents of the area neighboring the port had to flee their homes into local
schools for refuge. More than 720 people were hospitalized as a result of being critically injured.
How it could have been avoided
The blasts could have been avoided if there were transparency and a time information.
Information about the dangerous chemical should have been conveyed to the respective people
so as to protect human rights or even create awareness about them. Conveying the information
would have mitigated the risk and prevented the disaster as well.
Lesson learned from the explosion
Most people that gave the lessons included the insurers, those involved in loss adjusting
and also reinsurers.
There should be a change in the thinking of accumulation of risk. Many insurers and
reinsurers got exposed to many claims at a go. Claims from policyholders and many
business lines. This is because the blast affected people, property, vehicles, marine and
also infrastructure. Too much risk was accumulated.
ENGINEERING RISK MANAGEMENT 4
Due to this, the need to collect data for how long a ship should remain at a port which
would help a carrier determine its market share at a certain time and place was
highlighted. This would help avoid potential arising from accumulated risk.
The disaster proved that not only losses from natural calamities have a great impact.
People also learned that it is good to have various supply chains so that a calamity
occurring at one chain does not paralyze economic activities of a given market.
Strict measures of storage were to be upheld. This was mainly to prevent storage of
harmful products. This also included the government`s idea to zone chemical
manufacturers. These measures made warehouses owner reluctant to house harmful
goods.
The need for education was highlighted. If the firefighters had information on how to
deal with the blaze from the chemicals, they wouldn`t have lost their lives.
RISK MANAGEMENT
This involves identifying and evaluation of risks and how to avoid, prevent or minimize
their impact.
Risks involved and their analysis
Financial risk
These are risks resulting from investments, business operations or even assets.
Operational risk - This risk under finance came about when activities at the port were halted due
to the occurrence of the blast. The property was damaged and activities were not as usual. The
zone of the blast being a port, a lot of importation, exportation, loading, offloading and storage
takes place there. For any business that needed goods from there had to halt its operations. All
Due to this, the need to collect data for how long a ship should remain at a port which
would help a carrier determine its market share at a certain time and place was
highlighted. This would help avoid potential arising from accumulated risk.
The disaster proved that not only losses from natural calamities have a great impact.
People also learned that it is good to have various supply chains so that a calamity
occurring at one chain does not paralyze economic activities of a given market.
Strict measures of storage were to be upheld. This was mainly to prevent storage of
harmful products. This also included the government`s idea to zone chemical
manufacturers. These measures made warehouses owner reluctant to house harmful
goods.
The need for education was highlighted. If the firefighters had information on how to
deal with the blaze from the chemicals, they wouldn`t have lost their lives.
RISK MANAGEMENT
This involves identifying and evaluation of risks and how to avoid, prevent or minimize
their impact.
Risks involved and their analysis
Financial risk
These are risks resulting from investments, business operations or even assets.
Operational risk - This risk under finance came about when activities at the port were halted due
to the occurrence of the blast. The property was damaged and activities were not as usual. The
zone of the blast being a port, a lot of importation, exportation, loading, offloading and storage
takes place there. For any business that needed goods from there had to halt its operations. All
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
ENGINEERING RISK MANAGEMENT 5
the burnt property led to the loss of assets which is loss of capital hence occurrence of the
financial risk (Chung & Kim,2015).
Legal risk
This is a risk of loss due to legal action
Regulatory risk- The Chinese government had come up with a safety measure that there should
be a 1000-meter gap between the public buildings and the stores with the dangerous chemicals.
The safety measure was not applied in the Tianjin zone. As a result, the explosion affected even
the residential areas bordering the port (Zhao,2016).
Environmental risk
This is a potential threat to animals, plants, and environment by emissions and wastes.
Pollution
After the explosion, the Chinese people got exposed to contaminated water. The animals, plants
and entire ecosystem were exposed to the risk. Toxics were spilled into the waters and fumes
filled the air. The sodium cyanide from the warehouse, being toxic, causes respiratory poisoning
to both humans and animals. Sodium cyanide would have contaminated the air if it was
converted to hydrogen cyanide gas hence a toxic to the humans. For animals living in water, the
cyanide would have been dangerous because it persists in groundwater for long (Tummala &
Schoenherr, 2011).
Human resource risk
the burnt property led to the loss of assets which is loss of capital hence occurrence of the
financial risk (Chung & Kim,2015).
Legal risk
This is a risk of loss due to legal action
Regulatory risk- The Chinese government had come up with a safety measure that there should
be a 1000-meter gap between the public buildings and the stores with the dangerous chemicals.
The safety measure was not applied in the Tianjin zone. As a result, the explosion affected even
the residential areas bordering the port (Zhao,2016).
Environmental risk
This is a potential threat to animals, plants, and environment by emissions and wastes.
Pollution
After the explosion, the Chinese people got exposed to contaminated water. The animals, plants
and entire ecosystem were exposed to the risk. Toxics were spilled into the waters and fumes
filled the air. The sodium cyanide from the warehouse, being toxic, causes respiratory poisoning
to both humans and animals. Sodium cyanide would have contaminated the air if it was
converted to hydrogen cyanide gas hence a toxic to the humans. For animals living in water, the
cyanide would have been dangerous because it persists in groundwater for long (Tummala &
Schoenherr, 2011).
Human resource risk
ENGINEERING RISK MANAGEMENT 6
These are costs that are incurred when a bad thing happens to people.
Loss of life and injury- From the explosion, more than 100 people died and others were seriously
injured.
Abuse- The firefighters who came to help stop the fire didn’t have abundant information about
the harmful chemicals in the warehouse. Technically, important information was not conveyed to
them and that’s why the water they sprayed didn’t stop the fire, instead, it became more (Das &
Teng, 1998).
Plan for measuring and monitoring the performance of risk management plan
Due to the explosion that occurred at the warehouse for shipping containers in the port, it
is good to for the engineers to come up with a good risk management plan that would prevent or
help get out of the impact of the risk that has already occurred. The following are the steps;
Identification of the risk that could have an impact on the warehouse.
The warehouse is used for storage of containers with both imported goods and those that are to
be exported. It is good to know both the layout of the warehouse and what goods exactly are
being stored there. This will help figure out what risks are to be prevented from occurring. For
example, in this, if the gases in the warehouse are flammable then mechanisms to prevent the
sodium cyanide from exploding should have been in place (Hallikas et al,2004)
The risks should be assessed to reveal their impact.
Each risk that had a possibility of occurring should be noted and what their impact is. For
example, in such a warehouse, theft, explosion, deterioration of goods can occur. These are risks
whose impact on the owners of containers and the port should have in mind (Cervone,2006)
These are costs that are incurred when a bad thing happens to people.
Loss of life and injury- From the explosion, more than 100 people died and others were seriously
injured.
Abuse- The firefighters who came to help stop the fire didn’t have abundant information about
the harmful chemicals in the warehouse. Technically, important information was not conveyed to
them and that’s why the water they sprayed didn’t stop the fire, instead, it became more (Das &
Teng, 1998).
Plan for measuring and monitoring the performance of risk management plan
Due to the explosion that occurred at the warehouse for shipping containers in the port, it
is good to for the engineers to come up with a good risk management plan that would prevent or
help get out of the impact of the risk that has already occurred. The following are the steps;
Identification of the risk that could have an impact on the warehouse.
The warehouse is used for storage of containers with both imported goods and those that are to
be exported. It is good to know both the layout of the warehouse and what goods exactly are
being stored there. This will help figure out what risks are to be prevented from occurring. For
example, in this, if the gases in the warehouse are flammable then mechanisms to prevent the
sodium cyanide from exploding should have been in place (Hallikas et al,2004)
The risks should be assessed to reveal their impact.
Each risk that had a possibility of occurring should be noted and what their impact is. For
example, in such a warehouse, theft, explosion, deterioration of goods can occur. These are risks
whose impact on the owners of containers and the port should have in mind (Cervone,2006)
ENGINEERING RISK MANAGEMENT 7
Evaluation of all stated risks in order for the management to prioritize them
This involves looking at what risks one by one and being able to prioritize by the number of
resources you are willing to invest in the risk. This is either to prevent or deal with a risk that has
already occurred.
Minimize the impact of risks by treating them.
This involves dealing with risks that can be avoided. This for example at the warehouse in this
would include not storing hazardous chemical components.
Come up and review the risk management plan.
This plan contains details of how to deal with the risks projected. The plan entails those
identified risks, the impact of risks, the strategies for dealing with risks, time to implement it,
those responsible and the required resources (Saunders & Cornett, 2003)
The process used to analyze strategic issues
Vision clarification.
This is where short and long-term goals are defined as well as the process to achieve the goals.
Each employee is assigned a task according to their skills in order to contribute towards the
achievement of the goals. Each stakeholder or employee should be aware of the objective.
Gathering and gauging of the information.
It involves collecting data that will aid in the achievement of the goals. The strengths and
weaknesses of the company should be analyzed as well as the external factors.
Formulate good a strategy
Evaluation of all stated risks in order for the management to prioritize them
This involves looking at what risks one by one and being able to prioritize by the number of
resources you are willing to invest in the risk. This is either to prevent or deal with a risk that has
already occurred.
Minimize the impact of risks by treating them.
This involves dealing with risks that can be avoided. This for example at the warehouse in this
would include not storing hazardous chemical components.
Come up and review the risk management plan.
This plan contains details of how to deal with the risks projected. The plan entails those
identified risks, the impact of risks, the strategies for dealing with risks, time to implement it,
those responsible and the required resources (Saunders & Cornett, 2003)
The process used to analyze strategic issues
Vision clarification.
This is where short and long-term goals are defined as well as the process to achieve the goals.
Each employee is assigned a task according to their skills in order to contribute towards the
achievement of the goals. Each stakeholder or employee should be aware of the objective.
Gathering and gauging of the information.
It involves collecting data that will aid in the achievement of the goals. The strengths and
weaknesses of the company should be analyzed as well as the external factors.
Formulate good a strategy
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
ENGINEERING RISK MANAGEMENT 8
This will involves first identifying both internal and external resources that will help achieve the
given goals. Challenges that may hinder success should also be identified then once done, a
strategy is formulated.
Strategy implementation.
If the structure in use does not favor the formulated strategy, then a new structure should be
formulated before the plan kicks off. All employees should know their tasks and roles they play.
Adequate funding should be secured then the plan is executed.
Evaluation of control
This involves measuring performance, reviewing both internal and external issues for any
corrective measures to be taken. Before a strategy is put in place, parameters should which
performance should be measured against should be put in place (Settele et al,2005)
High level of personal autonomy and accountability
Autonomy is how a person governs their own actions while accountability is being answerable.
These both define how a person does tasks better willingly and are accountable for the same.
This is by motivating himself or herself. The highest level of a person`s desire, moves them to
act on certain things. The desire is a motivating factor. Also, a person` s desire to act is also
determined by their level plans and what actions are worth performing. Caring also motivates
one to act and be accountable. The power of her motivation is dependent on her level of
authority.
This will involves first identifying both internal and external resources that will help achieve the
given goals. Challenges that may hinder success should also be identified then once done, a
strategy is formulated.
Strategy implementation.
If the structure in use does not favor the formulated strategy, then a new structure should be
formulated before the plan kicks off. All employees should know their tasks and roles they play.
Adequate funding should be secured then the plan is executed.
Evaluation of control
This involves measuring performance, reviewing both internal and external issues for any
corrective measures to be taken. Before a strategy is put in place, parameters should which
performance should be measured against should be put in place (Settele et al,2005)
High level of personal autonomy and accountability
Autonomy is how a person governs their own actions while accountability is being answerable.
These both define how a person does tasks better willingly and are accountable for the same.
This is by motivating himself or herself. The highest level of a person`s desire, moves them to
act on certain things. The desire is a motivating factor. Also, a person` s desire to act is also
determined by their level plans and what actions are worth performing. Caring also motivates
one to act and be accountable. The power of her motivation is dependent on her level of
authority.
ENGINEERING RISK MANAGEMENT 9
Autonomous people are motivated by desires they cannot resist. For example, drug addicts
cannot stop taking drugs because they have the urge to take the drugs. Being accountable is
attributed from one`s ability to appreciate their reasons for why they do what they do.
Executive summary/Conclusion
The explosion had a great impact on Northern China. It paralyzed activities at the port and even
led to the loss of lives and property as well. Poor risk management in the warehouse caused the
overall blasting of the stored chemicals. This, however, could have been prevented if proper
information was conveyed and if the government had stringed laws governing the storage of the
chemicals in question. The necessary risk management plan should be outlaid to prevent loss
from risk impact.
REFERENCES
Autonomous people are motivated by desires they cannot resist. For example, drug addicts
cannot stop taking drugs because they have the urge to take the drugs. Being accountable is
attributed from one`s ability to appreciate their reasons for why they do what they do.
Executive summary/Conclusion
The explosion had a great impact on Northern China. It paralyzed activities at the port and even
led to the loss of lives and property as well. Poor risk management in the warehouse caused the
overall blasting of the stored chemicals. This, however, could have been prevented if proper
information was conveyed and if the government had stringed laws governing the storage of the
chemicals in question. The necessary risk management plan should be outlaid to prevent loss
from risk impact.
REFERENCES
ENGINEERING RISK MANAGEMENT 10
Aitao, Z., & Lingpeng, F. (2017).A new insight into the accident investigation:A case study of
Tianjin Port fire and explosion in China. Process Safety Progress , 36(4), 362-367.
Cervone, H. F. (2006). Project risk management. OCLC Systems & Services: International
digital library perspectives, 22(4), 256-262.
Chung, Y. S., & Kim, H. S. (2015). On August 12, 2015, the occurrence of explosions and fires
in Tianjin, China, and the atmospheric impact observed in central Korea. Air Quality,
Atmosphere & Health, 8(6), 521-532.
Das, T. K., & Teng, B. S. (1998). Resource and risk management in the strategic alliance making
process. Journal of management, 24(1), 21-42.
Fu, G., Wang, J., & Yan, M. (2016). Anatomy of Tianjin Port fire and explosion: Process and
causes. Process Safety Progress, 35(3)216-220.
Hallikas, J., Karvonen, I., Pulkkinen, U., Virolainen, V. M., & Tuominen, M. (2004). Risk
management processes in supplier networks. International Journal of Production
Economics, 90(1), 47-58.
Huang, P.,& Zhang, J. (2015).Facts related to August 12,2015 explosion accident in
Tianjin ,China. Process Safety Progress,34(4), 313-314.
Jing, Zhao. “Framing the 2015 Tianjin Explosions Crisis: A Content Analysis of People`s Daily
WeChat Official Account.
Saunders, A., & Cornett, M. M. (2003). Financial institutions management: A risk management
approach. Irwin/McGraw-Hill.
Settele, J., Hammen, V., Hulme, P., Karlson, U., Klotz, S., Kotarac, M., ... & Peterson, K.
(2005). ALARM: Assessing LArge-scale environmental Risks for biodiversity with
tested Methods. Gaia-Ecological Perspectives for Science and Society, 14(1), 69-72.
Aitao, Z., & Lingpeng, F. (2017).A new insight into the accident investigation:A case study of
Tianjin Port fire and explosion in China. Process Safety Progress , 36(4), 362-367.
Cervone, H. F. (2006). Project risk management. OCLC Systems & Services: International
digital library perspectives, 22(4), 256-262.
Chung, Y. S., & Kim, H. S. (2015). On August 12, 2015, the occurrence of explosions and fires
in Tianjin, China, and the atmospheric impact observed in central Korea. Air Quality,
Atmosphere & Health, 8(6), 521-532.
Das, T. K., & Teng, B. S. (1998). Resource and risk management in the strategic alliance making
process. Journal of management, 24(1), 21-42.
Fu, G., Wang, J., & Yan, M. (2016). Anatomy of Tianjin Port fire and explosion: Process and
causes. Process Safety Progress, 35(3)216-220.
Hallikas, J., Karvonen, I., Pulkkinen, U., Virolainen, V. M., & Tuominen, M. (2004). Risk
management processes in supplier networks. International Journal of Production
Economics, 90(1), 47-58.
Huang, P.,& Zhang, J. (2015).Facts related to August 12,2015 explosion accident in
Tianjin ,China. Process Safety Progress,34(4), 313-314.
Jing, Zhao. “Framing the 2015 Tianjin Explosions Crisis: A Content Analysis of People`s Daily
WeChat Official Account.
Saunders, A., & Cornett, M. M. (2003). Financial institutions management: A risk management
approach. Irwin/McGraw-Hill.
Settele, J., Hammen, V., Hulme, P., Karlson, U., Klotz, S., Kotarac, M., ... & Peterson, K.
(2005). ALARM: Assessing LArge-scale environmental Risks for biodiversity with
tested Methods. Gaia-Ecological Perspectives for Science and Society, 14(1), 69-72.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
ENGINEERING RISK MANAGEMENT 11
Tummala, R., & Schoenherr, T. (2011). Assessing and managing risks using the supply chain
risk management process (SCRMP). Supply Chain Management: An International Journal,
16(6), 474-483.
Zhao, B. (2016). Facts and lessons related to the explosion accident in Tianjin Port, China.
Natural Hazards, 84(1), 707-713.
Tummala, R., & Schoenherr, T. (2011). Assessing and managing risks using the supply chain
risk management process (SCRMP). Supply Chain Management: An International Journal,
16(6), 474-483.
Zhao, B. (2016). Facts and lessons related to the explosion accident in Tianjin Port, China.
Natural Hazards, 84(1), 707-713.
1 out of 11
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.