ERP Implementation Project Plan for Automatic Data Processing Inc.

   

Added on  2023-06-03

24 Pages5171 Words358 Views
Swinburne University of Technology
Faculty of Information and Communication Technologies
INF30019 Information Systems Project Management

FINAL PROJECT PLAN
1 Introduction and Objectives of the Project Plan
1.1 Overview of the Organization
Automatic Data processing Inc. is a provider of cloud based solutions to the clients along with the
business process outsourcing services. The Company ADP offers a number of services to the clients that
include the human capital management, payroll services along with benefit administration. The
company is a fairly large size company operation across 110 countries.
The top management of the company ensures customer satisfaction with the services it provides. The
goal of the company is to improve its customers’ base by providing valued services to the customer.
1.2 Current Situation and Problem/Opportunity Statement
In order to help the company achieve its goals, development and implementation of an enterprise
resource planning system for the organization is proposed.
With the increase in the client base, it becomes essential to for the organization to enhance its
performance by reducing the service delivery time. Since the company is operating in a number of
locations, it becomes essential to integrate the different processes of business that are running within
the organization. For that, implementation of enterprise resource planning system is recommended for
the organization.
This system will help in better business management by automatic report generation and enhancing the
decision making process. The organization is in need of an ERP system for better management of the
clients’ needs and enhancing the customers’ satisfaction. Although the business has been delivering
premium services to its clients over the years, it becomes mandatory to keep up to the expectations of
the clients. With the implementation of ERP, the decision making ability with the staffs and the
managers of the organization will increase as well.
2 Project Charter
2.1 Project Information
Project Start Date: Thu 04-10-18
Project End Date: Mon 09-03-20

Project Manager: Please Insert
Project Sponsor: Please Insert
2.2 Project objectives
The Project ERP Implementation in ADP has the following objectives-
1. To identify the requirements of ERP in ADP
2. To understand the implementation process of ERP system
3. TO design and implement the ERP
2.3 Project approach
An Agile project methodology approach is chosen for the project. For accurate project implementation,
a project plan is needed to be prepared. The implementation plan will be followed throughout the
project implementation phase for better project management.
2.4 Roles and Responsibilities
The roles and the responsibilities of different stakeholders of the ERP implementation project in ADP is
represented in the following table-
Name Role Position Contact Information
Please Insert Resource manager Resource
manager
resource@gmail.com
Frank White Project Manager Project Manager white@organization.org
Please Insert Functional
Manager
Functional
Manager
functional_manager@gmail.com
2.5 Project Constraints
There are certain project constraints that have been identified in the project planning phase. The
constraints associated with the project are as follows-
1. Schedule Constrains: The project implementation plan estimates the schedule of
implementation of ERP project in ADP. However, it is seen that the project is needed to be
implemented is a constricted schedule which is one significant constraint.
2. Time: The project has a time constraint as well.
3. Scope: The project is needed to be implemented according to the identified project scope,
which is a major project constraint as well.

2.6 Assumptions
The assumptions considered in the planning process of ERP implementation
project in ADP are as follows-
1. One of the assumptions associated with the project is that it can be
completed in the estimated schedule
2. It is assumed that continuous resource availability can be maintained in
the project implementation phase.
2.7 Preliminary Schedule and Budget Estimates
The Preliminary Project schedule for development and implementation of the ERP project is
represented in the table below-
WBS Task Name Duration Start Finish
0 ERP Implementation 373 days Thu 04-10-18 Mon 09-03-20
1 Project Starts 0 days Thu 04-10-18 Thu 04-10-18
2 Project Initiation 29 days Thu 04-10-18 Tue 13-11-18
2.1 Identification of the
Requirements 7 days Thu 04-10-18 Fri 12-10-18
2.2 Requirements Gathering 5 days Mon 15-10-18 Fri 19-10-18
2.3 Development of Project Charter 7 days Mon 22-10-18 Tue 30-10-18
2.4 M1: Approval of Project
Charter 10 days Wed 31-10-18 Tue 13-11-18
3 Project Planning 29 days Wed 14-11-18 Mon 24-12-18
3.1 Project Scheduling 5 days Wed 14-11-18 Tue 20-11-18
3.2 Estimation of the budget of the
Project 7 days Wed 14-11-18 Thu 22-11-18
3.3 Development of Project
Implementation Plan 12 days Fri 23-11-18 Mon 10-12-18
3.4 M2: Approval of Project
Implementation Plan 10 days Tue 11-12-18 Mon 24-12-18
4 Execution Phase 135 days Tue 25-12-18 Mon 01-07-19
4.1 Project Designing 30 days Tue 25-12-18 Mon 04-02-19
4.2 Coding the ERP 60 days Tue 05-02-19 Mon 29-04-19
4.3 Testing each Modules 45 days Tue 30-04-19 Mon 01-07-19
4.4 M3: Completion of ERP
Development 0 days Mon 01-07-19 Mon 01-07-19
5 Testing 95 days Tue 02-07-19 Mon 11-11-19
5.1 Unit testing 15 days Tue 02-07-19 Mon 22-07-19
5.2 System Testing 30 days Tue 23-07-19 Mon 02-09-19
5.3 Integration testing 20 days Tue 03-09-19 Mon 30-09-19

5.4 Bug Fixing 30 days Tue 01-10-19 Mon 11-11-19
5.5 M4: Completion of Testing and
Bug Fixing 0 days Mon 11-11-19 Mon 11-11-19
6 Project Release 47 days Tue 12-11-19 Wed 15-01-20
6.1 ERP software launch 2 days Tue 12-11-19 Wed 13-11-19
6.2 Training 15 days Thu 14-11-19 Wed 04-12-19
6.3 Bug Fixing (if any) 30 days Thu 05-12-19 Wed 15-01-20
6.4 M5: Delivery of Functional
ERP software 0 days Wed 15-01-20 Wed 15-01-20
7 Project Closure 38 days Thu 16-01-20 Mon 09-03-20
7.1 Collection of Users' Feedback 15 days Thu 16-01-20 Wed 05-02-20
7.2 Project Evaluation 30 days Thu 16-01-20 Wed 26-02-20
7.3 Documentation 5 days Thu 27-02-20 Wed 04-03-20
7.4 Payment Completion 1 day Thu 05-03-20 Thu 05-03-20
7.5 Resource Release 1 day Fri 06-03-20 Fri 06-03-20
7.6 Client Sign Off 1 day Mon 09-03-20 Mon 09-03-20
8 M6: Project Ends 0 days Mon 09-03-20 Mon 09-03-20
The Gantt chart of the project is represented in the following picture-
Figure 1: Representing the Gantt Chart of the project
(Source: Generated by Author using MS project)

The work activities marked in red in the Gantt chart above depict the critical path of the project
The estimated budget for the project is as follows-
Task Name Duration Cost
ERP Implementation 373 days $403,600.00
Project Starts 0 days $0.00
Project Initiation 29 days $12,000.00
Identification of the Requirements 7 days $6,440.00
Requirements Gathering 5 days $2,200.00
Development of Project Charter 7 days $3,360.00
M1: Approval of Project Charter 10 days $0.00
Project Planning 29 days $15,680.00
Project Scheduling 5 days $2,400.00
Estimation of the budget of the Project 7 days $2,240.00
Development of Project Implementation
Plan 12 days $11,040.00
M2: Approval of Project
Implementation Plan 10 days $0.00
Execution Phase 135 days $282,400.00
Project Designing 30 days $257,200.00
Coding the ERP 60 days $14,400.00
Testing each Modules 45 days $10,800.00
M3: Completion of ERP Development 0 days $0.00
Testing 95 days $30,000.00
Unit testing 15 days $3,600.00
System Testing 30 days $7,200.00
Integration testing 20 days $4,800.00
Bug Fixing 30 days $14,400.00
M4: Completion of Testing and Bug
Fixing 0 days $0.00
Project Release 47 days $43,480.00
ERP software launch 2 days $880.00
Training 15 days $6,600.00
Bug Fixing (if any) 30 days $36,000.00
M5: Delivery of Functional ERP
software 0 days $0.00
Project Closure 38 days $20,040.00
Collection of Users' Feedback 15 days $10,800.00
Project Evaluation 30 days $7,200.00
Documentation 5 days $600.00
Payment Completion 1 day $480.00
Resource Release 1 day $480.00
Client Sign Off 1 day $480.00

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Strategic Project Management: Proposal
|7
|1450
|149

Implementation of ERP System in XYZ Organization - ISY2004 Information System and Project Management
|17
|3012
|251

Operational Challenges of Yes Chemist Pty Ltd. | Case Study
|12
|2992
|19

IT Project Management Assignment: Implementation of SAP
|12
|2256
|41

Business Case Project 2022
|13
|2607
|38

SAP Implementation Project Plan for Yes Chemist
|16
|3099
|245