Take off quantities of materials from the plans detailing the cottage in Project 1

11 Pages1517 Words17 Views
   

Added on  2022-10-08

Estimating Materials Quantities for Building and Construction

Take off quantities of materials from the plans detailing the cottage in Project 1

   Added on 2022-10-08

ShareRelated Documents
Estimating Materials Quantities for Building and Construction Projects 1
IDENTIFY AND PRODUCE ESTIMATED COSTS FOR BUILDING AND CONSTRUCTION
PROJECTS
Name
Course
Professor
University
City/state
Date
Estimating Materials Quantities for Building and Construction_1
Estimating Materials Quantities for Building and Construction Projects 2
Identify and Produce Estimated Costs for Building and Construction Projects
This task involves describing, measuring and recording quantities of different trades for the
cottage project, including 10% wastage.
1. Bored excavation
Let spacing of piers be 1.8m (maximum allowable spacing between piers).
Total number of piers (considering that there is a pier at each corner of the building) = 53
Diameter of pier = 0.3m, depth of pier = 2.5m
Volume of pier = πr2 x h
Item Particulars Unit Qnty Rate ($) Cost ($)
1 Bored excavation for piers m3 9
π/0.152/2.5/53 9.37
2. Bulk excavation
Bulk excavation is done 1m beyond the external house walls and it does not include detailed
excavation. This is done by determining the bulk excavation for each ground floor room. Depth
of bulk excavation is 0.25m.
Item Particulars Unit Qnty Rate ($) Cost ($)
2 Bulk excavation m3 67
Family room
5.08/7.51/0.25 9.54
Kitchen, meals room, laundry, foyer, study,
living, dining, hallway and garage
13.87/14.83/0.25 51.42
Patio
2.67/8.35/0.25 5.57
66.53
The contours and elevations shown on the project drawings have revealed that the site is not
level. This means that some of the excavated material will be used as fill material. Since the
contours on the site are in the range of 0.05 and 0.3, the percentage of materials from bulk
excavation that will be used as fill material is 50%. Thus the volume of fill material is equal to:
50
100 x 67 m3=33.5m3
Estimating Materials Quantities for Building and Construction_2
Estimating Materials Quantities for Building and Construction Projects 3
3. Ground slab N25 concrete
The concrete calculated here is that for ground slab, beams, patio slab, and pad footings.
Ground floor slab
Thickness of ground floor slab = 0.1m
Volume of ground floor slab concrete = length x width x depth
Beams
There are edge beams and internal beams.
Depth of edge beams = 0.42m
Depth of internal beams = 0.35m
Volume of beams concrete = width x depth x length x no. of beams
Patio slab
Thickness of patio slab = 0.1m
Volume of patio slab concrete = length x width x depth
Pad footings
Depth of pad footings = 0.45m
No. of pad footings = 2
Volume of patio footings concrete = length x width x depth x no.
Item Particulars Unit Qnty Rate ($) Cost ($)
3 N25 concrete m3 35
Ground slab m3 19
Family room
4.08/5.51/0.1 2.25
Kitchen, meals room, laundry, foyer, study, living,
dining, hallway and garage
11.87/12.83/0.1 15.23
17.48
Allow 10% wastage
0.1/17.48 1.75
19.23
Beams m3 14
Edge beams
0.45/0.42/10.82/1 2.04
Estimating Materials Quantities for Building and Construction_3
Estimating Materials Quantities for Building and Construction Projects 4
0.45/0.42//12.83/2 4.85
0.45/0.42/10.97/1 2.07
8.96
Internal beams
0.45/0.35/10.97/1 1.73
0.35/0.35/11.48/1 1.41
0.45/0.35/4.61/1 0.73
3.87
12.83
Allow 10% wastage
0.1/12.83 1.28
14.11
Patio slab m3 1
1.32/0.59/0.1 0.08
5.17/1.67/0.1 0.86
1.32/0.24/0.1 0.03
1.08/0.35/0.1 0.04
1.01
Allow 10% wastage
0.1/1.01 0.10
1.11
Pad footings m3 1
1.2/0.9/0.45/2 0.97
Allow 10% wastage
0.1/0.97 0.10
1.07
4. Ground slabs SL72 reinforcing mesh
The first step is to determine the net ground area of family, kitchen, meals room, laundry, foyer,
study, living, dining, hallway, garage and patio.
Effective cover area per SL72 reinforcing mesh sheet = 5.8m x 2.2m = 12.76m2
Item Particulars Unit Qnty Rate ($) Cost ($)
4 SL72 reinforcing mesh
4.1 Net measure of ground floor slab
reinforcing mesh
m2 204
Family
4.08/5.51 22.48
Kitchen, meals room, laundry, foyer, study,
Estimating Materials Quantities for Building and Construction_4

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
CPCCBC4004 Estimated Costs for Building Projects
|13
|2079
|254

Calculation of Quantities of Materials for Building Project 1
|13
|1806
|173

Estimated Costs for Building and Construction Projects
|25
|3387
|369

Calculating Quantities for Bored Excavation and Bulk Excavation
|13
|2597
|151