logo

Financial Strategy and Governance

   

Added on  2023-04-17

6 Pages1132 Words227 Views
FINANCIAL STRATEGY AND GOVERNANCE
STUDENT ID:
[Pick the date]

Introduction
Prudent capital allocation is one of the key requisite for generation of shareholders’ value.
This is enabled through the application of appropriate capital budgeting techniques which
allow the management to decide whether a project is financially viable or not. However, the
focus should not be limited to only the quantitative aspects as qualitative aspects must also be
considered before taking capital allocation decisions. In this background, the objective of this
report is to carry out an NPV analysis of the project coupled with highlighting the sensitivity
of the project to changes in discount rate. This would allow the management to decide
whether incremental capital should be allocated to the given project or not.
Analysis of the project
NPV Analysis
A key requisite in order to apply the capital budgeting techniques is to estimate the
incremental cash flows from the project. The following key observations can be made with
regards to the given project.
1) The $10 million expense on factory building is a sunk cost for the purposes of this project.
This is because it has already been incurred three years ago and would not be recovered or
incurred owing to the decision taken with regards to project (Damodaran, 2015).
2) The depreciation related to the factory would not be considered as this is not incremental
and any tax shield on account of the same would not be considered. Similar treatment
would be givne to the cost of dismantling the factory. This is because the factory would
otherwise also have to be dismantled once the project is over and is not contingent to the
given project. Also, the cost of dismantling remains the same and hence no incremental
dismantling costs have to be incurred by the company (Parrino and Kidwell, 2014).
3) The expected fixed cost that would need to be incurred for production to commence is $ 8
million.
4) Incremental depreciation is available with regards to the above fixed cost which would be
equal to 10% of $ 8 million = $ 0.8 million per year
5) Also, the incremental sales revenue to the extent of $ 2.5 million annually would arise for
10 years starting from today. The variable cost per annum is expected to be $ 0.5 million
per annum.
2

Based on the above information and interpretation, the post tax incremental cash flows
expected from the project is indicated as follows.
The NPV needs to be estimated using the discount rate of 10%. The following assumptions
have been made (Brealey, Myers and Allen, 2014).
1) All the relevant cash flows tend to occur at the end of the year only.
2) Further, it has been assumed that the salvage value for the fixed costs which would be
incurred for starting production would be zero at the end of 10 years.
3) Further, the discount rate for the project would remain the same throughout the useful life
of the project.
Taking the above assumptions, the computation of NPV for the given project is shown below.
From the above computation, it is evident that the NPV for the given project is $ 2.08 million.
Considering that the NPV comes out to be greater than zero, hence the given project would
be regarded as financially feasible. Also, this would lead to increase in the wealth of the
shareholders by $ 2.08 million (Beck et. al., 2013).
Sensitivity Analysis
The objective of this analysis is to highlight the sensitivity of thee project to the changes in
discount rate. This is imperative as it highlights the robustness of the project feasibility in
wake of higher financing costs. In order to conduct this analysis, the NPV for various
discount rates need to be determined which is captured in the tabular manner highlighted as
follows (Christensen et. al., 2016).
3

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Financial Analysis of Dell's Laptop Manufacturing Plant
|8
|1222
|92

Capital Budgeting Assignment Sample
|7
|1180
|308

Project Evaluation for a Manufacturing Firm in Brisbane
|5
|771
|101

Assignment on Capital Budgeting Analysis
|4
|874
|68

Financial Decision Making for Richside Industries
|5
|655
|429

Incremental Cash Flows and Capital Budgeting Techniques for Kline Pharmaceuticals
|7
|1439
|131