Objectives and the Priorities of FTL Project (1) •Themain objective of this project is to launch the Food Test lab on 1 July 2019 to coincide with the Asia Food Safety Convention’s Opening day. •Another objective of the project is to incorporate Fipronil Testing in the project. Both the objectives of the project were fulfilled.
Objectives and the Priorities of FTL Project (2) TimeScopeCost Constrai nt X EnhanceX AcceptX •Fipronil Testing is one of the major project priorities •Apart from that, the launch of the Food Test Lab on 1 July 2019 is another priority of the project. •Both the priorities of the Project is met.
Changes in Schedule and Contributing Event •The Food Test Lab project has seen certain changes in the schedule of the project •This is mainly because of the change in duration of one particular activity in the project. •The contributing event for the same is Fipronil Testing.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Cost Overrun and its contributors •The project has observed certain cost overrun in the project. •The variance in the cost is enforced by the addition of Fipronil Testing in the FTL project. •The major contributing event of cost overrun is therefore the Fipronil Testing.
Lesson Learnt and Suggestions Lesson Learnt •Lesson learnt is considered to be an ongoing effort of a project lifecycle. •The lesson learnt process in FTL project includes the technique of project planning and effective cost estimation Suggestions The suggestions in this project are as follows- The Project Manager should have considered the problem of resource conflict. The cost estimation of the project should be more accurate.