logo

Fundamentals of Project Management

   

Added on  2023-01-11

21 Pages5052 Words33 Views
Leadership Management
 | 
 | 
 | 
Fundamentals of Project
Management
Fundamentals of Project Management_1

Contents
EXECUTIVE SUMMARY.............................................................................................................3
INTRODUCTION...........................................................................................................................1
TASK 1............................................................................................................................................1
A. Importance of various parameters of iron triangle in determining the overall Project
objectives and goals.....................................................................................................................1
B. Identification of the risks that are likely to emerge during the course of project
implementation by AF Plc with the help of risk register.............................................................3
TASK 2............................................................................................................................................8
A. Preparation of a network diagram to show the critical path and planned duration of the
project..........................................................................................................................................8
B. Preparation of a Gantt chart for the project.............................................................................9
C. Details of overall projected budget and calculation of the projected net profit of the
contract........................................................................................................................................9
TASK 3..........................................................................................................................................12
A. Comparing the actual progress with the planned progress using Gantt Chart......................12
B. Production of a revised Gantt chart and analysis of the impact on project completion date
and expected costs and profit.....................................................................................................13
TASK 4..........................................................................................................................................15
A. Using EVA determine the overall actual percentage of work completed and compare it with
overall actual planned percentage of work completed..............................................................15
B. Create a project final spend and date using EAC method derived from Earned Value
Analysis.....................................................................................................................................17
C. Recommendation for which of the options should be accepted and which should be
declined......................................................................................................................................17
REFERENCES..............................................................................................................................19
Fundamentals of Project Management_2

EXECUTIVE SUMMARY
Automatic Futures (AF) PLC is a technology contracting and consulting company which
performs software and product development contracts for various clients and organisation for
increasing automation and technology within a company system. In this project report, a case
study of AF PLC is being done which covers four different aspects of project management of the
company. The first aspect deals with defining the project constraints and risk identification for
the company. Second aspect includes the provision of mapping the project schedule with the help
of Gantt charts and network diagram. In the third aspect of the report, at attempt has been made
to analyse the detailed budget to estimate the profitability of the contract. The last part of the
report deals with preparation of a new project timeline after considering the actual progress with
the planned progress and providing recommendations to the company for deciding to choose a
suitable option for acceleration.
Fundamentals of Project Management_3

INTRODUCTION
Project management can be defined as the process of controlling, monitoring, coordinating
and planning the tasks and activities of a team of people for achieving the objectives and task
requirements of a project within a definite time period (Drouin, Besner and Hobbs, 2012). In the
following project report, a case study of Automatic Futures (AF) PLC is being done which is a
technology consulting, contracting and software/product development company. The report
covers various aspects of the project management by the company such as risk identification,
scheduling the project work and estimating the total cost and revenue from the contract for the
company.
TASK 1
A. Importance of various parameters of iron triangle in determining the overall Project objectives
and goals.
Iron Triangle also known as Project Management triangle or Triple Constraints is a model
which helps in defining the constraints related to the management of a project. Successful
implementation of any project usually depends on three main factors or constraints parameters
which are time, scope, cost and quality which depends on all these three factors. Managers of
any project make efforts to balance the factors which might act as constraints in the overall
execution of the project and its delivery (Usui, 2012). All the factors are interconnected and a
change in any factor results into change in other factors as well. Some of the main guidelines for
any project provided by Iron triangle are:
Every project must be completed within the proposed time.
Every project must be completed within the proposed or budgeted cost.
Every project should meet the scope or the requirements.
Quality requirements of the customer should also be taken care of.
1
Fundamentals of Project Management_4

Cost: Cost can be defined as the total expenditure incurred in a project implementation
and execution. A project should be completed within the expenses budgeted during the initial
project planning (Hall, 2012). However, some project have different requirements and don’t
specify the cost budget as the main focus is on time schedules and quality of the project. If cost
incurred on a project is to be decreased, either the scope of the project needs to be increased or
time schedule needs to be pushed back. The cost for the project by AF Plc is increasing as the
company is making arrangements to meet the new deadlines. To counter this, scope of the
project is being reduced to some extent and some features of the project are being accelerated
and pushed into phase 2 to meet the new deadlines. The major constraint for AF Plc with regards
to cost is time schedule of the project. A reduction in the cost of the project also results into
quality degradation.
Time: Every project has a definite time schedule ahead of its delivery which needs to be
met by the managers of the project. Adding timeline to a project is necessary for effective
monitoring and controlling the project deadline (Kivilä, Martinsuo and Vuorinen, 2017). To
reduce the time implemented in the project, either the cost incurred needs to be increases or the
scope of the project needs to be altered. The management of AF plc have the task to meet the
time requirement of the project as a result of which cost incurred is increasing. The major
constraint for managers of AF Plc with regards to time is scope and requirement of the project.
Scope: Scope of the project can be defined as the task and activities or the other
requirements of the project. It is the stage where many project managers fail as the scope of each
and every project which needs to be implemented by the management is not always very clear
and definite and has the element of ambiguity in it (Klein, Biesenthal and Dehlin, 2015).
Reduction in the scope of a project leads to quality degradation and cost reduction and as a result
time required is also pushed back. One of the major constraint for the managers of AF Plc
regarding scope of the project is the cost incurred in the project implementation.
The overall objective of the project must be established by the managers after having a
deliberate discussion with the clients about the impact of these three hurdles on the management
of the project. To ensure a successful project implementation, time, scope and cost constraints
related with the project need to be clearly analysed by the managers and definite qualitative and
quantitative objectives should be set. Although, AF Plc’s one box project management fits the
requirements of the current clients but it can’t be regarded suitable for every client or type of
2
Fundamentals of Project Management_5

project. Project management triangle is a very useful model which determines relative
importance of three major constraints related to project management.
B. Identification of the risks that are likely to emerge during the course of project
implementation by AF Plc with the help of risk register.
A risk register is one of the most important tools used by the managers of any organisation
for risk management. It is very helpful in the process of identification of potential risk for any
project and assist the management in damage control (Seymour and Hussein, 2014). All the
information such as nature of risk, likelihood of risk occurrence, impact of the risk and the
person responsible for mitigation of the risk are covered in the risk register for better analysis of
risk. Risk management helps the project managers to increase the overall efficiency and quality
of project delivery by predetermination of potential risk which could act as hindrance in the
project implementation project.
Some of the major risks which have been identified for the AF Plc project management
includes health and safety of workers, change of orders, natural disasters, contractual
inefficiency, mismanagement etcetera. All these risks have the potential to act as an obstacle in
the whole process and hence it is suggested that the management should take an early
precautionary step by analysing the risks and their impact ratings on the whole project. The
cumulative rating of a risk depends on two major factors which are the likelihood of the risk
occurrence and the impact of risk occurrence on the whole project scenario (Turner, Ledwith and
Kelly, 2012). These factors are combined together to analyse the risk in terms of its severity. The
following risk register helps the management to decide the overall rating of the risk and
determine the mitigation plan to reduce the likelihood of risk occurrence.
RISK
(Various risks
that may arise
during the
course of
project)
LIKELIHOOD
(1-5), 1 being
least chances
and 5 being the
highest chances.
IMPACT
(1-5), 1
being the
least
impact
and 5
being the
highest
impact
RATING
(Increasing
order
where an
increased
number
denotes
higher
overall
OWNER
(Person who
is
responsible
for
mitigating
the risk.)
MITIGATION
PLAN
(A plan prepared
by the
management to
reduce the
likelihood and
the impact of a
3
Fundamentals of Project Management_6

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Fundamentals of Project Management
|21
|4865
|24

Fundamentals of Project Management
|23
|4501
|72

Fundamentals of Project Management
|21
|4081
|66

Fundamentals of Project Management: PM Consultancy Report
|23
|4034
|70

Fundamental of Project Management
|20
|4626
|78

Fundamentals of Project Management
|24
|5174
|37