This report focuses on the fundamentals of project management, including the importance of iron triangle parameters in setting project objectives. It covers topics such as risk management, planning, and costs. The report also includes a network diagram and Gantt chart for project planning.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Fundamentals of Project Management
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
EXECUTIVE SUMMARY The project analysis focuses on different facets of successful issues of project management. The whole report is based on a business that is an enterprise named as automation future (AF). In addition, this report provides a detailed summary of the concerns and needs for the overall evaluation of the project. Further part of report summarizes thata project manager needs to have all the characteristics which can contribute to achieve overall goals of a project in an effective manner. In the absence of contribution of a project manager, a project cannot be successful.
Table of Contents EXECUTIVE SUMMARY.............................................................................................................2 INTRODUCTION...........................................................................................................................4 MAIN BODY...................................................................................................................................4 Part A - Project Management Consultancy Report..........................................................................4 Project Definition/Parameters and Risks (Question 1)....................................................................4 Importance of the iron triangle parameters in setting the Overall Project objectives and inter relations between these parameters.............................................................................................4 Risk register with ten risks..........................................................................................................6 Planning and costs (Question 2)......................................................................................................9 Preparing a network diagram showing the critical path and planned duration of the project along with computing the float on the non-critical tasks............................................................9 Preparing a Gantt chart and determining the planned completion date....................................10 Developing overall Project Budget and calculating projected Net profit for the contract........12 Managing progress and spending (Question 3).............................................................................14 Comparison between the planned progresses against the actual progress using a Gantt chart.14 Producing a revised Gantt chart and identifying the new completion date...............................14 Earned Value Analysis and Acceleration (Question 4).................................................................18 Creating an Earned Value Analysis table..................................................................................18 Creating a projected completion date........................................................................................19 Recommendations..........................................................................................................................20 Part B - Reflective Essay..............................................................................................................21 CONCLUSION..............................................................................................................................23 REFERENCES..............................................................................................................................24
INTRODUCTION The word project management may be regarded as a formalized mechanism for tracking the various forms of project tasks. The principal aim of theproject management is to attaina present target for available resources. In case of absence of proper and effectivemanagement of the varying tasks of project, there may be different types of obstructions, like the malfunction of aproject.Theprimarypurposeoftheprojectreportistopayattentionondetailedand comprehensiveprocessofprojectmanagementandalsoonissuesthatariseduringthe completion of a specific project (Sipes, 2019). The study-reportis aligned withcompany's study case named"Automation Futures". Thecompany doesn't really exist in true life; this is a corporation premised on assumptions that operates in the development anddesigningof various types of software as well as advanced computingtechnologies. According to thiscase study data, the corporation's project concerns manufacturing of trains. The project study-report isfocusedon 2 majortasks namedA and B. Multiple formsof tasksarecontainedhereintaskA,liketheplannedmethodofdevelopmentand production,fiscalplan and the estimation ofvalue of entireproject earned. While onother hand, Task Bis entirely focused on a reflective review wherein information is given onproblems facingproject manager and also onlearning outcomes. MAIN BODY Part A - Project Management Consultancy Report Project Definition/Parameters and Risks (Question 1) Importance of the iron triangle parameters in setting the Overall Project objectives and inter relations between these parameters. AF plc mentioned in case study is a multinational corporation that performs a wide varietyofoperations,includingtechnologyoutsourcing,consultancy,software development/designandmuchmore.Irontrianglecriteria/parameterorvariablesarequite important when it comes to determining overall project goals. That's because, with the aid of these guidelines, it is simpler forproject'smanagers to evaluate the results ofproject in a much
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
more successful and productive manner. Each variable is connected to one another. Below isdiscussionaboutsignificance of these variables,as follows: Cost- It is perceived to be one main criteria to developa better project. It'sthe duty ofproject managersto understand how more can be done to accomplish a project goals. A thorough estimate of potential costs needs to be made for this reason (Poston and Richardson, 2019). As for the above-mentioned organization project, this is required for executives to create an estimate of the total costs that might arise and to also concentrate on certain activities whose costs are high orrising. In case ofeffectiveabsence of a reasonable cost forecast, it will be impossible formanager ofrespectiveorganization to maintain project costs lower thanprojected cost. Time- Almost every project does have a target date to accomplish and it is essential for the project leader to undertake all tasks within a prescribed period (Belack, Di Filippo and Di Filippo, 2019). If aproject is not finished within a specific deadline, it may contribute to a variety of hurdles. As with the contextofAF plc'sproject case, thisis necessary for their executives to monitor the progression of every task in aspects of timing. This can be achieved by splitting all duties or operations ofproject in simple tasks and giving time with each activity. This makes it convenient for management to have an additional focus on the progression of each task in attempt to assess whetherit will have done within a specified time span. Scope-Theparticularscopeofaprojectrequirestobetranslucent,preciseand sustainable. That's because each person in the team will be informed of the overall aim of the project with the aid of this. Like ifscope and nature of aproject is transparent, it would be simpler for project leaders to convey important knowledge easily to others. As withAF plc project mentioned above, it's also essential forproject managersto convey the general scope of thisproject with all those involved with suchproject. Quality- This one islast considerationrelevant to controlling the overall output ofproject (Stamatis,2019).That'scriticalthatifprojectwillbecompleted/accomplished withquality standardsand in an efficient way, it is regarded an excellent project. As with the aforementioned organization project, it's also crucial forproject leader to preserve the quality standardsofproject so that they'll get more project back again from client.
Interrelation: All variables or criteria are interconnected. That's because overlooking one variable will result to a failing of the project (Shirley, 2020). Manager could not rely heavily on a single aspect, like costs and time, which are interconnected. It's because a lag in finishing the project will turn to higher costs. Range and consistency variables are both connected to one another. Because whenproject team people are informed of actualscope ofproject, it'll be fairly easy to preservequality ofproject. Which means that all variables are related to one another. Risk register with ten risks A risk registry is a database that is utilized as a risk control device which satisfies regulatory requirements and serves as a record for all known threats that provides detailed details on and risk, such as risk intent, guide and controller, mitigating steps. Users may display it as a scatter plot or as a chart (Zachko, Golovatyi and Kobylkin, 2019). A risk register has the primary purpose of serving as the dataset for specific risks. Such threats may be health hazards, business risks, financial risks, environmental risks and more-so anyone could have different records for each form of danger-or combine more than one practical danger into a common project management risk registry (Dotsenko, Chumachenko, 2019). The risk registry requires a project manager or organization to mention all actual or future threats in rows, and then define and describe critical components of such threats in the columns linked. Through a project, the intent of a risk registry often changes slightly. The aim at the beginning of a project is to include a thought process where project leaders and other relevant stakeholders may come together and discuss risks. RiskCategory of the risk Likelihood of occurrence oftherisk (Out of 5; 5 beinghigh likely occurrence) Impact ofthe risk (Outof 5;5 being high impact) CausesMitigation strategies IncreasedFinancial44ThetriggerofThis risk could
expensesof labours suchriskisthe transitionsinUn itedKingdom's labour/worker union. be managed by recruiting labourona fixedwages policyforthe overall project. Increased expensesfor raw material Financial44This form of risk may emerge as a resultof increased demandaswell asalowered supply ofnecessarymat erialsrequired inmarket. Riskmaybe loweredby enforcingthe pre-availability of any and all formsof materialand resources required. Ineffective utilizationof resources Financial24Theabsenceof monitoring functionby workers,and alsoany structural failure inmachines, mayalso contributeto suchrisk. Itcouldbe eliminatedor regulatedby careful oversight of all activitiesand keyresources utilized. Adversecost variance Financial35Itmayincrease asaresultof increasedusage ofwater, electricityor Itcanbe managedby planningemer gencyfinancia lbudgetfor
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
someother essentialresourc es. these concerns. Labour strikeOperational25Thisriskmay emerge owing to the strength and influentialpower of union leaders (Betta and Iwko, 2019). Thiscanbe managedby recruiting employees based oncontract policies. LayoffsOperational25Alterationsor variationsin political circumstances andeventscan be keyreason for such a risk. Thiscanbe regulatedby the authorisation ofregulatory authoritiesto operatethe project. Accidenton site Human resource 15Thisriskmay usuallyhappen as a result of any mechanical malfunctionof equipmentor duetounskilled workers. This risk could alsobe decreasedby havinghealth coveragefor workers,and alsocareful supervision. Higher employee turnover Human resource 25Thiscan increasedueto adverse,unfavou rable,unsatisfact oryworking Thiscanbe regulatedby upgrading workplace practicesand
conditions.alsoproviding comfortable and motivating workingenvir onment. Improper communication Technical3.52.5Divergent workforceor lowskilled workers may be thecausefor such a risk. Thiscanbe resolvedby recruiting local insteadof immigrant workers. Issuesin automation Technical42Thismaybe increasedby recruitingless knowledgeable workingpersonn el. Itcanbe handledby employing staffmembers intunewith the requirements oftheproject (Ambrose, Harrisand Ball, 2019). Fromallthediscussedrisks,ithasbeennotedthatthemostoftheserisksarelinkedto communications. Nevertheless, their effect on the ultimate objective ofproject is negligible. Along with problems relevant to the division of human resources, they have a huge influence on the project. Therefore, above all, the project managersof the organization require to concentrate on such risks whose impact is stronger on the success of the project.
Planning and costs (Question 2) Preparing a network diagram showing the critical path and planned duration of the project along with computing the float on the non-critical tasks A network diagram/structureis a form of analysisthat relates to the estimation of the length ofproject (the line-up). A network diagram enables to determine which tasks are necessary and how longproject will take (Petroutsatou, 2019). With assistance of this diagram, it is easier for leaders to identify objectives in multiple ways in activities and duties. This is likely that, within this system, the important tasks are illustrated in a specific colour to making it easier for project managersto effectively completethe project.Thisdiagram can be developed byproject manager of in respective project as stated below: Tasks that encircleabove graph in red colourare crucial indicators which together establish project'scritical path. The prolonged distance among starting stage and ending phase iscritical direction of thisproject. Estimation ofcritical path is significant for a company as it determines the overall timeline which will be needed to complete the project.Tasks 1 to 18coversthe critical path/routeof this project of companyAF Plc.It will take around92 weeks for carry out almost all the tasks they 're planning to bring on. Phase 2 with3-week float, phase 4 hasa 1- week glide, cycle with8-week float, shift ninewith9-week float then phase tenwith an 8-week flowsare severalnon-critical activities. Such float amount is determined by subtracting the approximate length of the entireproject fromstart time frame. Preparing a Gantt chart and determining the planned completion date. A Gantt chart implies tomethod through which projects or activities are tracked over time. Each type of graph contains the date of begin and the date of finish (Mozhei and Lukianov,
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
2019). The graph shows the basic beginning and the end date information for each specified feature or service. With this support, it is easier for managers to find out which activities can be difficult and the activities can be completed in much less time-duration. The very first phase of suchproject, as is shown inGantt chart following, iscompletion of entireproject, which is expected to begin on the8thJuly 2019 and therefore will require oneweek to complete. Before this phase, numerous activities are required to take place one after the other. as demonstrated inproject'sGantt chart below,TTF project wouldbe completed by 6thJuly 2020.
Developing overall Project Budget and calculating projected Net profit for the contract. The project spending plan or fiscalbudget is an overview of allexpenditures which the corporation wants to spend on the execution of aproject (Становськаs and Колеснікова, 2019). AF Plc does have at minimum GBP58.5 millionto completeTTF Automation Factory. The net costing as shown in the estimate below is around48.7 million. Whenproject is finished on 25thSeptember, the corporation will receive around 13.85 revenue, alsoaccording toprojected schedule, employing Gantt's regular schedule, thisproject will be finished 81-days earlier, leading in an additional revenue of 4.05 million.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Managing progress and spending (Question 3) Comparison between the planned progresses against the actual progress using a Gantt chart. A progress plan has been conducted in AF Plc after 17 weeks of the process to manage the inconsistency between the scheduled aspects and the finished one. Considering actual progress in a project prior to the 17th week, a table is constructed to calculate the current project percent status and expected percentage change. TasksPlanned progress (%)Actual progress (%) PI100100 A100100 B100100 C100100 D10080 E100100 F6035 G6035 H55.5550 From above table this can be assed that, tasks PI, A, B, C, D and E were performed as expected. Nevertheless, the following aspects are under performed: F, G, and H. During the 17th week, Project F was expected to be carried out progress by 60%, but in actual this was of just 35%, almost half of the forecasts were achieved. This repeated the same situation with the task of G with 55.55 % of success. The "H" tasks’ actual progress was of 50 percent by week 17. The reason of this poor performance may be because of any external cause or due to lack of internal power. Producing a revised Gantt chart and identifying the new completion date. The actual project layout is used to create a modified model of the Gantt. A description of the updated running period together with the Gantt map and network diagram below is:
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
The Gantt chart mentioned above states that project will fully over in 144 weeks. This divided tasks will impact the AF Ltd team members, because they are not prepared to gain higher rate of success.
Earned Value Analysis and Acceleration (Question 4) Creating an Earned Value Analysis table EVA is a project planning methodology and essentially for an evaluation of the current and planned features of scheduled operations (Chandra, 2020). Estimates of both BCWP and ACWP activities have already been provided for AF Plc. For the estimation of both these variables, the consolidated amount and the estimated working / work cost shall be determined. The AF Plc has paid charges on the operating expenses and the estimated costs of the work / work scheduled to occur. Tasks Work completion (percentage) Budgeted/plannedCosts ofWork-Performed (BCWP) [Earned value] Actualincurred CostsofWork- Performedi.e. ACWP BudgetedCostsof Work-Scheduled (BCWS) PI100200.20.2 A1002802.912.8 B1001601.721.6 C1001501.531.5 D803044.083.8 E1005405.975.4 F351191.323.4 G35227.52.766.5 H502002.754 Tota l2000.523.2429.2 (BAC) Costs Variance (CV = EV - AC)-$32,35,000.00 Costs Performance Index (CPI = EV/AC)0.86 Schedule Variance (SV = EV - PV)$1,95,05,000.00 Schedule-Performance Index (SPI = EV/PV)40.01
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
SchedulePerformance Index (SPI = EV/PV)1.001.001.001.000.920.950.840.710.69 The variability of such a project's cost is calculated by the value received and the actual costs projected at 32, 35,000. In relation to uncertainty the SP and CP numbers are also determined. The cost-efficiency ratio here is calculated at about 0.86, which is the actual relative cost profit. Thus the schedule index of the Plan is around 40.01. This is determined by valuing the whole enterprise, including the one scheduled. Creating a projected completion date. During completion of the project, the process or method for estimating a project's completion date and cost is determined (Cakmakci, 2019). The completion deadline for such a project has been revised to 14 August 2020, as a consequence of the 17th weekly project analysis. As a result, this ambiguity will impact the Project 's earnings as AF Plc. Their early attempts did not give them an expected opportunity. The real expense estimates for the project are calculated by the estimate of execution. For the previous budget the spending was projected at 48.7 million. Estimate at completion (EAC) = Actual cost (AC) + ((Budget at completion (BAC) – Earned value (EV)) / (Cost performance index (CPI) * Schedule performance index (SPI))) Estimate at completion (EAC) = $2,32,40,000 + ($2,92,00,000 - $2,00,05,000) / 0.86 * 40.01 $2,32,40,000 + $9195000/ 0.86 * 40.01 $32435000 / 0.86 * 40.01 $32435000 / 34.4086 = $942642.24 Costs for operations PI to H will be worked out using the estimation form of $942642.24. According to real costs, it was found that the projected / anticipated costs are 25.2 million for PI's H operations, while the current expense here is around $942642.24 more than the costs previously reported. Reduce the risk of higher expenditures. AF Ltd will maintain resources in this scenario to avoid risk turning the expected profits of this company into losses.
Recommendations There are various approaches accessible to reducing the penalty costs. There are multiple challengesanddrawbacksacrossstylesofchoices.Basedonthisanalysisitmaybe recommended that the alternative carrier be selected. That is because saving 75,000 pounds on cost will be beneficial. They will also depend on the alternative set out above. If this alternative is rendered by the above company, the productivity would have a beneficial effect: Lower cost- This alternative has lower production costs which will make it easier to reduce the extra costs for the above project. And if the rates will lower than the production, that would be easier. However, other options are also acceptable, but none are highly productive and can reduce higher prices. Suitable- In addition to the above-mentioned importance of the preferred alternative, having this choice in the sense of the business project will be suitable as it is linked to reducing cost. Since these results indicate that if they follow this approach, they inevitably lead to success in the sector. Examination of possible options and core projects indicated that the whole project processremainedviablefortheorganizationuntiltheapproacheswereaddressed.The completion date is set for 14 Aug 2020, starting from 6 July 2020, with the introduction of the choices. This is evident because the policy system includes a component of expense control. By the completion of the year, i.e. 25/09/2020, the AF PLC had to reimburse the TTF and had to return 100 K pounds per day for the remainder of the day. The consumer gets a £ 50 K bonus early on the day of delivery. The customer is unable to complete the product before the supplementary option is offered and if the organization follows the original solution the customer will complete this project soon. And these are the main guidelines which the project manager of the above-mentioned company will follow. By doing so, higher profits and better work results will be good for them. AF plc would find it easy to handle the project efficiently, owing to the availability of integration of the necessary elements.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Part B - Reflective Essay Difficulties experienced during the Unit- as the AF PLC's Project Director, I met several difficulties throughout the design phase that posed significant issues at the project's completion. Since the plan was carried out by a small team, I have faced many problems and none is very involvedintheprojectmanagementprocess.Suchchangesinconfigurationalsoledto substantial confusion within the community, since no team member has clear location criteria. The reason for this is that such concerns have become the main goals in my position as project leader. Because AF PLC is a well-known company, the staff are more responsible than ever under every situation. Difficulties producing the assessment- I identified several problems in the evaluation which culminated in mental illness. I primarily discussed the problem of defining tasks and obligations to the different team members. That's why I couldn't even know my workers' potential. Another problem for me was the planned assembly of workers, as I could not carry out the work within a defined date and expense due to an uncertain implementation of the position. Here are some of the main preoccupations across the study. Nonetheless, it is my responsibility to delegate tasks to all colleagues correctly and to determine the success of each team member. However, I also managed to learn some additional insight from those topics on how to cope with a difficult situation. Such hurdles will surely encourage me to handle the different aspects of project management in next few years. Clear personal development goals- I described certain key personal priorities at the end of AF Plc 's project centred on my knowledge as project manager. Technical development goals are as follows: I'm starting to operate on time management. It is mainly that a group leader wants to be courteous and gracious enough to encourage all of the team leaders. I was ignorant of the time of administration during the project which led to a variety of issues. I will also concentrate on building up my personal skills. Since I don't know how to better interact with fresher men. Due to that, I faced complications during the later process. Characteristics of a Good Project Manager- A good project manager must have sufficient expertise and qualifications to enable effective implementation of projects. Underneath is part of a good manager's main features: Better communication skills- Consistent coordination at the start of the project is essential for the group to make the correct decision. The distinct types of project operations will
become easier to understand because of strong teamwork. Therefore, possessing good interpersonal capabilities is important for a project manager. Good collaboration abilities between team leaders can help recognize problems at AF PLC. In fact, as project manager, I would work frankly and effectively with other team leaders to accomplish the end objective with less time and money. Good decision maker- As project manager, I need to proactively follow certain measures and make choices at the AF PLC project. The question is regarded as successful, and whether an action is performed on schedule is treated accordingly. Technical role as a project manager would reinforce my capacity to take reasonable action and make advancement towards to the ultimate objective. Technical Expertise- As AF PLC is a consulting firm, a qualified project manager must be accessible to the organisation. Business activities will be easily achieved if managers are facilitated with the right information and the path to achieve an objective is advanced technologies-how. I should prepare myself fully trained for a project manager as to the technical expertise. Leadership skills- An executive leader of a project is accountable for the task and aims to accomplish the goals. Proactive procedures of this aspect must be improved so that projectteammemberscan functiontogetherasstakeholdersof myguidanceand responsibilities. It is one of the important step to take the lead to create credibility for the company in the competitive environment. CONCLUSION The above study showsthat projectmanagementishighly criticalas it meansthat appropriate competitive assessment goals are completed in motion. It helps administrators to maintain efficient leverage of different tasks by incorporating detailed standardized task detail such as study summary, working time and quantities and the date by which each assignment is accomplished. The report concludes that timetables and plans for finalisation, overly ambitious or over-regarding related activities unless the programs are well prepared, cannot be specified completely. The second part of report is related to reflective statement of project manager as well as key features of a good manager are also concluded in this part.
REFERENCES Books and journal: Sipes, C., 2019.Project Management for the Advanced Practice Nurse Second Edition. Springer Publishing Company. Poston, R.S. and Richardson, S.M., 2019. Designing an academic project management program: A collaboration between a university and a PMI chapter.Journal of Information Systems Education,22(1), p.6. Shirley, D., 2020.Project management for healthcare. CRC Press. Dotsenko, N., Chumachenko, D. and Chumachenko, I., 2019, September. Modeling of the process of critical competencies management in the multi-project environment. In2019 IEEE14thInternationalConferenceonComputerSciencesandInformation Technologies (CSIT)(Vol. 3, pp. 89-93). IEEE. Petroutsatou, K., 2019. A proposal of project management practices in public institutions through a comparative analyses of critical path method and critical chain.International Journal of Construction Management, pp.1-10. Mozhei, К.A. and Lukianov, D.V., 2019. Contemporary approaches in project management education in Belarus. Chandra, P., 2020.Fundamentals of Financial Management|. McGraw-Hill Education. Cakmakci,M.,2019.Interactioninprojectmanagementapproachwithinindustry4.0. InAdvances in Manufacturing II(pp. 176-189). Springer, Cham. Belack, C., Di Filippo, D. and Di Filippo, I., 2019.Cognitive Readiness in Project Teams: Reducing Project Complexity and Increasing Success in Project Management. CRC Press. Stamatis, D.H., 2019.Six Sigma fundamentals: A complete introduction to the system, methods, and tools. CRC Press. Zachko, O., Golovatyi, R. and Kobylkin, D., 2019, September. Models of safety management in developmentprojects.In2019IEEE14thInternationalConferenceonComputer Sciences and Information Technologies (CSIT)(Vol. 3, pp. 81-84). IEEE. Betta, J. and Iwko, J., 2019, December. Draft of Project Team Quality Model in Traditional Project Management. InFourth International Conference on Economic and Business Management (FEBM 2019). Atlantis Press. Ambrose, G., Harris, P. and Ball, N., 2019.The fundamentals of graphic design. Bloomsbury Publishing. Становська, І.І. and Колеснікова, К.В., 2019. The individual competences stratification in order to build the dynamic morphological models of project management.Bulletin of NTU"KhPI".Series:StrategicManagement,Portfolio,ProgramandProject Management, (1 (1326)), pp.30-36.