1 PROJECT MANAGEMENT Table of Contents Part I.................................................................................................................................................2 Part II...............................................................................................................................................2 a) Explanation of the 1st option that is 4-week strike................................................................2 b) Explanation of the 2ndoption that is cold and wet weather.....................................................3 Part III..............................................................................................................................................4 a) SPI calculation and its impact on the schedule........................................................................4 b) CPI calculation and its impact on schedule.............................................................................5 c) Executive summary by using statistics...................................................................................6 d) EAC calculation and remaining critical path..........................................................................7 Bibliography....................................................................................................................................9
2 PROJECT MANAGEMENT Part I The Gantt chart that is provided below helps in reflecting that Stadium construction project will get completed within 62 wks. of time and as per this plan if the project proceed then it is assumed that the project will get finished by 22ndMarch 2005 which is earlier than the deadline date of the project. In addition to this, critical activities of the project are also shown with the help of below figure. Figure 1: Gantt chart (Source: Created by Author) Part II a) Explanation of the 1st option that is 4-week strike As per the above Gantt chart that is planned at the initial state, the construction project gets completed by 22ndMarch 2005 that is earlier than the completion date that is 31stMarch 2015. However, it is analyzed that the union tradesman can support a strike against the city and
3 PROJECT MANAGEMENT as this project is a public project there is 50% chance that they would strike the project for gaining national media attention. It is analyzed that 4 weeks of strike is common and due to this strike; the completion date of the project can get extended which further can create financial loss for the Ace builders. As per the initial planning as the project gets complete by 22ndMarch but due to 4 weeks of strike, the entire completion date of the project can get extended by 4 weeks that is 20 working days excluding Saturday and Sunday. The new completion date of the project will be after 20 days excluding Saturday and Sunday. Completion date-22ndMarch Four weeks strike-20 days (excluding Saturday and Sunday) After excluding the Saturdays and Sundays, completion datewill be on 19thApril 2005 which is reflected with the help of below figure. Figure 2: Gantt chart after strike (Source: Created by Author)
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4 PROJECT MANAGEMENT It is found that as the project gets delayed by 20 days and for each day of delay, the organization need to pay an amount of $250,000. As the project gets extended till 19thApril therefore the amount that the company will lose will be around (19*250,000) = 4,750,000 Therefore, it is found that within profit of $20,000,000, the organization will lose $4,750,000 b) Explanation of the 2ndoption that is cold and wet weather It is found that after planning of the project, Vice President for operations also bring an issue that is related with extreme cold and wet weather condition and this factor have not taken into consideration during the planning phase. It is found that if the workers are unable to work in cold and dry weather then the project can get delayed by 1 month which can be quite challenging for the project team. This can be considered as one of the planning issues for construction and due to this issue, the completion date can get extended and the organization will loss an amount of around $5, 000,000 due to delay of 1 month (20working days) in the project. In order to avoid suchissues,itistheresponsibilityoftheprojectmanagertotakeimportantfactsinto consideration before starting the project for avoiding challenges during the project progress. Part III a) SPI calculation and its impact on the schedule From the table that is given below, it is found that the SPI is around 0.4861 and if SPI remains less than 1 then it means that less work has been completed as compared to the work that planned and therefore the project is behind the schedule.
5 PROJECT MANAGEMENT Tasks%CompleteBid Price ($)Actual expenseEarned value Duration (Weeks)Actual Staging area, mobilization, demolition10065,00,00075,00,00065,00,00088.5 Exacavation-field10075,00075,00075,00088 Subsurface drainage1003,70,0002,70,0003,70,0001410 Fill material for field10050,00050,00050,00042 Instalaltion of turf01,00,0000060 Excavation-façade, roof supports, boxes10010,00,00010,00,00010,00,00045 Pouring concrete footings1001,85,00,0001,85,00,0001,85,00,00066 Pouring box, roof and fascade supports1005,95,00,0005,35,00,0005,95,00,0001011 Erecting pre-cast concrete façade and boxes757,50,00,0005,72,50,0005,62,50,0001613 Finishing of boxes and new façade03,00,00,0000050 Painting1050,00,0005,00,0005,00,00040.5 Dressing rooms, offices and concession101,20,00,00012,00,00012,00,00081 Prefabricated the retractable roof901,00,00,00095,00,00090,00,00044 Erecting the roof1052,50,0005,50,0005,25,00040.5 Scoreboard751,00,00,00072,50,00075,00,00053 New seats103,20,00,00032,00,00032,00,00030.5 Lights and other facilities54,00,00,00020,00,00020,00,00070.1 Wiring, HVAC152,00,00,00030,00,00030,00,00041 Exterior infrastructurre improvements51,96,55,0009,82,7509,82,75060.1 Punch list and demolization050,00,0000030 TOTAL35000000016,63,27,75017,01,52,750 Figure 2: SPI calculation (Source: Created by Author) b) CPI calculation and its impact on schedule As per the table that is provided below, it is analyzed that CPI of the project will be around 1.022 which reflects that the project is under budget and therefore it can be assumed that the project can get completed within the budget that is assumed. The calculation is reflected in the below table.
6 PROJECT MANAGEMENT Tasks%CompleteBid Price ($)Actual expenseEarned value Duration (Weeks)Actual Staging area, mobilization, demolition10065,00,00075,00,00065,00,00088.5 Exacavation-field10075,00075,00075,00088 Subsurface drainage1003,70,0002,70,0003,70,0001410 Fill material for field10050,00050,00050,00042 Instalaltion of turf01,00,0000060 Excavation-façade, roof supports, boxes10010,00,00010,00,00010,00,00045 Pouring concrete footings1001,85,00,0001,85,00,0001,85,00,00066 Pouring box, roof and fascade supports1005,95,00,0005,35,00,0005,95,00,0001011 Erecting pre-cast concrete façade and boxes757,50,00,0005,72,50,0005,62,50,0001613 Finishing of boxes and new façade03,00,00,0000050 Painting1050,00,0005,00,0005,00,00040.5 Dressing rooms, offices and concession101,20,00,00012,00,00012,00,00081 Prefabricated the retractable roof901,00,00,00095,00,00090,00,00044 Erecting the roof1052,50,0005,50,0005,25,00040.5 Scoreboard751,00,00,00072,50,00075,00,00053 New seats103,20,00,00032,00,00032,00,00030.5 Lights and other facilities54,00,00,00020,00,00020,00,00070.1 Wiring, HVAC152,00,00,00030,00,00030,00,00041 Exterior infrastructurre improvements51,96,55,0009,82,7509,82,75060.1 Punch list and demolization050,00,0000030 TOTAL35000000016,63,27,75017,01,52,750 SPI0.48615071 CPI1.02299676 Figure 3: CPI calculation (Source: Created by Author) c) Executive summary by using statistics The paper mainly reflects on renovation of Shea stadium project which was undertaken by Ace Builders for housing the New York Mets. The construction of the project generally stated on 1stJanuary 2004 and it assumed to be completed by 31stMarch 2005. If the project gets delayed after 31stMarch then $250,000 will be paid as per calendar day as penalty whereas $100,000 will be gained each working day, if the work completed before the completion date. It
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7 PROJECT MANAGEMENT is found that that in order to achieve an incentive of around $20million, the project manager creates a plan as peer which the project will get completed by 22ndMarch. On 10thDecember 2004, the status report of the project was released. The values for planned value, earned value as well as actual value is shown in the below figure. Tasks%CompleteBid Price ($)Actual expenseEarned value Duration (Weeks)Actual Staging area, mobilization, demolition10065,00,00075,00,00065,00,00088.5 Exacavation-field10075,00075,00075,00088 Subsurface drainage1003,70,0002,70,0003,70,0001410 Fill material for field10050,00050,00050,00042 Instalaltion of turf01,00,0000060 Excavation-façade, roof supports, boxes10010,00,00010,00,00010,00,00045 Pouring concrete footings1001,85,00,0001,85,00,0001,85,00,00066 Pouring box, roof and fascade supports1005,95,00,0005,35,00,0005,95,00,0001011 Erecting pre-cast concrete façade and boxes757,50,00,0005,72,50,0005,62,50,0001613 Finishing of boxes and new façade03,00,00,0000050 Painting1050,00,0005,00,0005,00,00040.5 Dressing rooms, offices and concession101,20,00,00012,00,00012,00,00081 Prefabricated the retractable roof901,00,00,00095,00,00090,00,00044 Erecting the roof1052,50,0005,50,0005,25,00040.5 Scoreboard751,00,00,00072,50,00075,00,00053 New seats103,20,00,00032,00,00032,00,00030.5 Lights and other facilities54,00,00,00020,00,00020,00,00070.1 Wiring, HVAC152,00,00,00030,00,00030,00,00041 Exterior infrastructurre improvements51,96,55,0009,82,7509,82,75060.1 Punch list and demolization050,00,0000030 TOTAL35000000016,63,27,75017,01,52,750 SPI0.48615071 CPI1.02299676 EAC342132070 Figure 4: CPI, SPI and EAC calculation (Source: Created by Author) From the above figure, it is analyzed that SPI is around 0.461 which reflects that the project does not completes work as per the initial planning and therefore the project is behind schedule. Whereas it is found that CPI of the project will be around 1.022 that means that the project is underbudget and therefore it is assumed that the entire project will get finished with the amount that is identified in the initial phase. Further fore, EAC of the project is around
8 PROJECT MANAGEMENT $342,132,070 as per the calculation. Furthermore, the paper also reflects the remaining critical path of the project within this section. d) EAC calculation and remaining critical path EAC calculation The EAC will be around $342,132,070 as per the calculation that is reflected with the help of the below figure: Tasks%CompleteBid Price ($)Actual expenseEarned value Duration (Weeks)Actual Staging area, mobilization, demolition10065,00,00075,00,00065,00,00088.5 Exacavation-field10075,00075,00075,00088 Subsurface drainage1003,70,0002,70,0003,70,0001410 Fill material for field10050,00050,00050,00042 Instalaltion of turf01,00,0000060 Excavation-façade, roof supports, boxes10010,00,00010,00,00010,00,00045 Pouring concrete footings1001,85,00,0001,85,00,0001,85,00,00066 Pouring box, roof and fascade supports1005,95,00,0005,35,00,0005,95,00,0001011 Erecting pre-cast concrete façade and boxes757,50,00,0005,72,50,0005,62,50,0001613 Finishing of boxes and new façade03,00,00,0000050 Painting1050,00,0005,00,0005,00,00040.5 Dressing rooms, offices and concession101,20,00,00012,00,00012,00,00081 Prefabricated the retractable roof901,00,00,00095,00,00090,00,00044 Erecting the roof1052,50,0005,50,0005,25,00040.5 Scoreboard751,00,00,00072,50,00075,00,00053 New seats103,20,00,00032,00,00032,00,00030.5 Lights and other facilities54,00,00,00020,00,00020,00,00070.1 Wiring, HVAC152,00,00,00030,00,00030,00,00041 Exterior infrastructurre improvements51,96,55,0009,82,7509,82,75060.1 Punch list and demolization050,00,0000030 TOTAL35000000016,63,27,75017,01,52,750 SPI0.48615071 CPI1.02299676 EAC342132070 Figure 5: EAC calculation (Source: Created by Author)
9 PROJECT MANAGEMENT Remaining critical path The remaining critical path for the stadium project after 10 December 2004, is reflected in the below figure. Figure 6: Remaining critical path (Source: Created by Author)
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10 PROJECT MANAGEMENT Bibliography Anantatmula, V. S., & Rad, P. F. (2018). Role of organizational project management maturity factors on project success.Engineering Management Journal,30(3), 165-178. Andersen,E.S.(2016).Doprojectmanagershavedifferentperspectivesonproject management?.International Journal of Project Management,34(1), 58-65. Bjorvatn, T., & Wald, A. (2018). Project complexity and team-level absorptive capacity as driversofprojectmanagementperformance.InternationalJournalofProject Management,36(6), 876-888. Keil, M., Culnan, M., Dinev, T., & Xu, H. (2019). Data governance, consumer privacy, and projectstatusreporting:RememberingH.Jeffsmith.InformationSystems Frontiers,21(6), 1207-1212. Kerzner, H., 2017.Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons. Kerzner, H. (2019).Using the project management maturity model: strategic planning for project management. John Wiley & Sons. Kerzner, H. (2017).Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John Wiley & Sons. Muriana, C., & Vizzini, G. (2017). Project risk management: A deterministic quantitative techniqueforassessmentandmitigation.InternationalJournalofProject Management,35(3), 320-340.