Project Management: American Constructors Inc- World Outreach Expansion Project
Verified
Added on 2023/04/23
|7
|1601
|197
AI Summary
This document discusses the project management of American Constructors Inc- World Outreach Expansion Project. It includes a Gantt chart, analysis of main issues and stakeholders, project deliverables, and notorious project challenges.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running Head: PROJECT MANAGEMENT: AMERICAN CONSTRUCTORS INC- WORLD OUTREACH EXPANSION PROJECT1 Project Management: American Constructors Inc- World Outreach Expansion Project Name Course Institution Professor Date
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Running Head: PROJECT MANAGEMENT: AMERICAN CONSTRUCTORS INC- WORLD OUTREACH EXPANSION PROJECT2 Gantt chart screen shots The Gantt chart was developed in a Project Management software, based on the tasks required to complete the World Outreach Church building and the interrelationships between the tasks as shown below; Figure1
Running Head: PROJECT MANAGEMENT: AMERICAN CONSTRUCTORS INC- WORLD OUTREACH EXPANSION PROJECT3 Analysis Q1. Main Issues The main issues in the project are a tight schedule within which to complete the work earlier than had previously been planned for. Initially, the WOC project was to be completed on 10thMarch 2010; however, the WOC (the client) wants the project to be ready for use by December. Grott, knowing this would be too much to ask, has added two weeks so that the project is now scheduled to be completed on 14thDecember 2009. Still, this still remains a challenge because it implies the project has been pushed forward by three months which Grott and his team must find a way to compensate for. To complete the project on time; Grott and his team must compress tasks, either by hiring additional staff and/ or contractors (resources) and by working overtime(Billows, 2015). This will ensure tasks are crashed by taking advantage of lag times to do extra work and shortening the Critical Path so the tasks are completed by the new set deadline. Undertaking tasks concurrently will also help compress the Critical path and ensure Grott and his team finishes on time. Another technique is fast tracking where tasks that are dependent on the preceding task to be completed are done in parallel, at least for a portion of their duration. Q2. Main stakeholders The main stakeholders in the project include the Church itself (the church management, who are the project sponsors/ clients) and who need to accept the project in order for it to be considered finished. Another important stakeholder is Grott, who is responsible for ensuring the overall project is completed within the given time schedule and budget. Grott must plan the project effectively, working with Bordbeck and Hawker, as well as the client, to ensure the objectives are met. Grott, for instance, must decide which tasks can be combined, what resources are needed, and where to use extra resources and over time to ensure the project schedule is maintained. Bordbeck is another stakeholder who is responsible for ensuring the work tasks (the work breakdown structure) flows smoothly, and that everything is done as required. Hawker is another stakeholder, responsible for determining the required time to complete tasks such as installation of concrete stairs on the deck, installation of hardware and doors within the sanctuary, and painting as well as works on the stairs RACI\The RACI was developed in a spreadsheet as shown in the figure below by listing all tasks in a single column and then listing the persons involved. The roles are the assigned based on who is accountable, who is responsible, who needs to be consulted, and who must be informed.
Running Head: PROJECT MANAGEMENT: AMERICAN CONSTRUCTORS INC- WORLD OUTREACH EXPANSION PROJECT4 Project DeliverableGrottBordbeckHawkerWOC Framing/ hanging/ dry wall finishingCRII Installing hard tile – F2RAII finishing stone columnsRAII MillingRRII Casework (installing cabinetry)CRRI Installing flooring- F 6CRRI Glass installation-F 3&4RRII Painting -F 8RRII Installing doors and associated h/ware- F 9/7CRRI MEPARII Cleanup and Punch list- F 2CIII Fire Marshall inspection -F 12ARRI Architect Punch List – F 13CRAI reception area- millworkRAAI hard ceilingRAAI lobby drywallRAAI Painting -F 18RARI Hard tile -F 18CARI Wood flooring treatment – F 21CARI Carpeting 1st floor, stairwell & lobby 2nd floor-F 21&22CARI Finish public restrooms- F17&18CARI Glass installation/ hanging chandeliers- S 25CARI Ceiling tiles -F 19RRII Doors and handles – F 27RRII Complete MEP work- F 27RRII Cleaning and ACI punch list -F 29RRII Sanctuary work-Auditorium seatingRRII bowlRAII terraceRAII Core drill railsRAII Install rails,CAII seats,CAII wood paneling, stage work, trimCAII staining concrete floorRAII stage steps carpeted -F 35RAII carpet at seats completedRAII Carpeting seating area-F 41RAII staining concrete in stage BOWL- F 38RACI SEAT Installation- F 33, 38, 40, 43RACI stage steps, lats, isles carpet – P 43RACI Doors and hardware installation in sanctuary- F 45IARI window surrounds sept 24- F 31IARI terrace waterproofing-F 47IARI
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Running Head: PROJECT MANAGEMENT: AMERICAN CONSTRUCTORS INC- WORLD OUTREACH EXPANSION PROJECT5 Insulation- F 48RIII concrete deck and stairs on terrace-F 49IARI pour concrete for deck-F 50IARI Stairs – FIRAI Aluminum rails installationARII complete stair masonry-F 53CRAI Figure2 Q 3 By using project management techniques such as compressing and fast tracking, the project should be completed on time. For instance, work on the lobby can be undertaken at the same time as tasks are done in the sanctuary and in the kitchen/ cafe/ bookstore. However, some tasks must be done after others; for example, the walls must be finished before they can be painted; similar to the floors being stained before carpeting can be done(Kerzner, 2009). Q4. Notorious Project Challenges The most notorious project implementation challenges, especially in a construction project like the WOC project include not having well defined goals, frequent or undue changes to the project scope, lack of accountability where all goals assigned to specific persons are undertaken as required. Other challenges include lack of/or a poor risk management strategy, poor stakeholder management, poor or ineffective communication, having expectations that are not realistic, and indifference by stakeholders(Wright, 2016). These challenges can be overcome by effective project planning, employing suitable project management techniques and methodologies, such as using PRINCE 2, effective risk management, and putting in place effective scope and change management plans. Further, sticking to the project schedule and baseline will ensure these challenges are overcome(Kerzner, 2016) Conclusion The WOC project undertaken by ACI can be best managed and tracked using the project management tool of a Gantt Chart (Fig I) which has been developed based on the tasks required. The main issues in the project include having to complete the project earlier by three months and ensuring the highest quality standards are maintained without too much additional costs. To achieve the new deadline of December 14th2009 and not march 10th2010; Grott and his team should use the tools of crashing and fast tracking. The main stakeholders in the project include Grott, Bordbeck, Hawker, and WOC (the client) as illustrated in Fig II. Notorious project issues in similar projects include poor goal definition, changes to scope, poor accountability,poor risk management strategy,
Running Head: PROJECT MANAGEMENT: AMERICAN CONSTRUCTORS INC- WORLD OUTREACH EXPANSION PROJECT6 poor stakeholder management, poor or ineffective communication, having expectations that are not realistic, and indifference by stakeholders
Running Head: PROJECT MANAGEMENT: AMERICAN CONSTRUCTORS INC- WORLD OUTREACH EXPANSION PROJECT7 References Billows, D. (2015). Project Trade-offs - Project Alternatives-4PM.com. Retrieved from https://4pm.com/2015/10/12/project-trade-offs-4pm-com/ Kerzner, H. (2009).Project Management: A Systems Approach To Planning, Scheduling, And Controlling 10E With Case Studies 3E Set(2nd ed.). Hoboken, NJ: John Wiley & Sons. Kerzner, H. (2016).Project Management Metrics, KPIs, and Dashboards: A Guide to Measuring and Monitoring Project Performance, Third Edition(3rd ed.). Hoboken, NJ: John Wiley & Sons, Inc. Wright, S. (2016). Project Management Challenges in the Construction Industry. Retrieved from https://project-management.com/project-management-challenges-in-the-construction- industry/