Introduction Almost everyone in the construction industry will be affected by the new changes in the Building and Construction Industry Security of Payment Act (“SOPA”). SOPA was first introduced by the NSW government in 2004 with the aim of improving cash-flow in the NSW building and construction industry (BCI). On 21stNovember 2018, the NSW Parliament passed the SOPA amendments act of 2018. However, the amendments did not come into force since there were incomplete changes within the Security of Payment Regulations. As of now, the new amendments are expected to be enforced on 21 October 2019. This paper sets to provide an overview of the effects of the amendment act in relation to the construction contracts. How the Act Work The entry of SOPA brought regulations for countering unjust practices in the construction industry that involved non-payment among others. The Act aimed to ensure that all persons involved in carrying out construction work under a contract received their rightful payments.1 The Act established statutory provisions that thought not intact with the construction contract, they operate in parallel to give force to any construction contract. That means even without the inclusion of some terms in the contract, there are implied terms that the parties need to comply with as applied by the act. In achieving its objectives, the act introduced new claimant’s statutory rights. Among them is to progressive payments.2Under the provision for progressive payments, the claimant may choose to seek payments through the provisions of the Act or by enforcing the construction contract. Where the claimant chooses to enforce the rights under the construction contract, the Act requires the claim to be processed in accordance with the rights and obligations 1Commonwealth of Australia,Insolvency in the Australian Construction Industry: ‘I Just Want to Be Paid’(2015) <https://www.aph.gov.au/Parliamentary_Business/Committees/Senate/Economics/ Insolvency_construction/Report/>. 2Building and Construction Industry Security of Payment Act19998.
contained in the contract. On the other hand, where the claimant brings the claim by invoking the provisions of the Act, the Act will provide even powers that were not included in the contract. Also, the Act applies without the consideration of whether the contract was made orally, in writing or partly oral.3 In general, the Act enforces payment through a process that involves; a)The claimant makes a payment claim. Under section 13, payment claim refers to a document which identifies the construction work, and the amount due.4 b)The Act stipulates the service for payment claim as per the contract or 12 months after completion of the project.5 c)Section 14 orders the respondent to whom the claim has been served to reply to the claim or pay the claimed amount.6 d)Section 15 and 16 provide consequences for not paying;7 e)Section 17 provides avenues for adjudication.8 In addition to the rights of the progress payment, the Act provides a right to claim interest on the owed payment.9 3Ibid sec 7. 4Ibid Sec 13. 5Ibid sec 13. 6Ibid sec 14. 7Ibid 15 & 16. 8Ibid sec 17. 9Ibid sec 11(2).
Also, the claimants have the right to suspend any work in progress pending the payment.10There is also a right of lien.11Also, the Act prevents inclusion of the ‘payed-when- payed’ clauses and prevents any action meant to contract out or override the provisions of the Act.12The ‘payed-when-payed’ clauses are provisions in the contract which allows the head contractor to withhold subcontractor’s payment until when the owner of the project pays the head contractor. In regard to contracting out, the act renders any attempt to override its provisions invalid, but the court emphasized that some conducts such as those create estoppel can prevent a party from relying on the non-ouster nature of the provision.13 The Act also introduced a rapid adjudication. This is a dispute resolution mechanism where an independent adjudicator will be called tom make interim determinations in relation to the progress payments. The Act also limits the initiation of the adjudication resolution only to claimants. However, both parties can make their submissions to the adjudicator.14By introducing the adjudication process, the intention of the Act was to provide a mechanism for determining payments in the progress claim pending the final resolution of the dispute in the rest of the proceedings. However, courts misunderstood this decision by setting aside adjudication determination until the intervention of the NSW Court of Appeal in Brodyn Pty. Ltd case.15 10Ibid sec 15(2), 16(2), 24(1). 11Ibid 11(3). 12Ibid s. 12(1), s. 34. 13Barclay Mowlem Construction Ltd v Tesrol Walsh Bay Pty Ltd(2004) 2004 NSWSC. 14Building and Construction Industry Security of Payment Act1999s. 17(3)(b). 15Brodyn Pty Ltd t/as Time Cost and Quality v Davenport & Anor(2003) 394 NSWCA.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Why Was It Introduced The term ‘security of payment’ (SOP) refers to the general entitlement of payments to subcontractors, contractors, suppliers or any consultants involved in a construction contractual arrangement to receive payments that are due as per the agreed terms.16The SOPA was first introduced by the NSW government in 2004 with the intention of improving cash-flow in the BCI. In other words, its aim was to ensure that workers and small subcontracting companies in the construction contracts receive their payments as agreed under the contract.17As reported by Brand and Davenport, the Commonwealth of Australia found that there was a consistent failure within the building industry to come up with effective frameworks of ensuring full payment of all participants in a construction project.18 The act intended to eliminate the unfair practices of the main contractors or the clients in arbitrary delaying payment or even withholding the entire payment.19Even if subcontractors are taken as the primary beneficiaries of SOPA, the provisions also include the protection of the rights of suppliers and contractors. The Act excluded only the client who is the owner of the construction project. Generally, issues of SOP related to problems that result from late payments, complete non-payment or arbitrary devaluation of the construction work.20To recover the due payments under a construction contract, suppliers and subcontractors used traditional channels such as face to face consultation, traditional methods of dispute resolution such as 16John Murray,Review of Security of Payment Laws: Building Trust and Harmony(Department of Jobs and Small Business, 2017). 17NSW Fair Trading,Security of Payment Reforms(27 August 2018) Fair Trading NSW <https://www.fairtrading.nsw.gov.au/consultation-tool/security-of-payment-reforms>. 18Michael C Brand and Philip Davenport, ‘Proposal for a “Dual Scheme” Model of Statutory Adjudication for the Australian Building and Construction Industry’ [2011]International Journal of Law in the Built Environment<https://www.emerald.com/insight/content/doi/10.1108/17561451111178452/ full/html>. 19Michael C Brand and Thomas E Uher, ‘Review of the Performance of Security of Payment Legislation in New South Wales’ inRICS Construction and building research conference COBRA(2008). 20Julian Bailey,Construction Law.(Taylor and Francis, 2014).
arbitration or sometimes the disputes escalated to litigation.21While these methods were helpful in securing the subcontractors' payments, the time delays and prohibitive costs involved led the suppliers and subcontractors to forfeit their rights to payment and moved on with other projects to maintain their cash flows. While issues of insolvency, unfair practices such as withholding payments, and delayed payment are common BCI, SOP is a critical issue due to different contributors. Firstly, most of the contractual arrangements on construction projects typically follow a multi-tiered hierarchy that creates cascading payment requirements.22Another problem is that contractual hierarchies rely heavily on cash flows together with a requirement for maximizing liquidity within the entire timeline of the construction project. This is a problem that causes poor financing of to the persons lower in the hierarchy, and when this happens, the people and the organization working with low finances are forced to bear the upfront costs.23As a consequence, the problem of late payments and/or unfair withholding of payments arises due to significant financial strain. The work of Andrew Burr reports that after recognizing these issues, Hon. Morris Iemma, the Minister for Public Works and Services in NSW stated that there were very many cases of unjust practices committed on small subcontractors. The minister stated that the unjust practices were preventing small subcontractors from surviving a financial clash when it occurs thus prompting the NSW Government to intervene.24 Recent Amendments In 2018, the Parliament made a number of amendments that would enhance the operation of SOPA. These amendments will affect both the respondents and the claimant in a construction 21Ibid. 22Commonwealth of Australia, above n 1. 23Brand and Davenport, above n 18. 24Andrew Burr,International Contractual and Statutory Adjudication(Taylor & Francis, 2017).
contract dispute. There are various changes particularly affecting the way the claimants’ will handle their claims as discussed below. Elimination of the concept of "reference date" The original Act under section 8 required payment claims to consider the reference date as stated in the construction contract. The new amendments have removed the importance of a reference date as a precondition to the validity of the payment claim. This change will have an effect on the entitlement to progress payments. Unlike before when the progress claim depended on the inclusion of the reference date on the contract, the amendment simplifies the process even for those construction contracts that have no reference date. In addition, the Amendment Act has introduced subsections 13(1A) to (1C) which provides more flexibility to the claimant in relation to serving the payment claim. These changes provide a future solution for problems like those that were encountered inAudi Construction case.25In the case, the contract stipulated the 20thof day of each month as the day of the serving a claim.26However, a problem arose when the 20th day was a Sunday, and the claimant decided to serve the claim on Friday, the 18th.27In addition, these amendments are in accordance with the reasoning in theSouthern Han Breakfast Point Pty Limited,which allowed claimants to bring their claims even after the termination of the contract.28 Application of the Act a claimant in liquidation The new Amendment Act will introduce section 32B. This section creates provisions that prohibit corporations in insolvency from serving payment claims or enforcing the payment claims. Also, if a corporation that is in liquidation had made an application for the payment 25Audi Construction Pte Ltd v Kian Hiap Construction Pte Ltd(2018) 4 SGCA. 26Ibid. 27Ibid. 28Southern Han Breakfast Point Pty Limited (in liq) v Lewence Construction Pty Limited(2016) 5 HCA.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
claims initiating an adjudication process prior to getting into liquidation, the application will have no effect upon the determination of the liquidation. The reforms follow the recommendation made by Murray in 2017 stating that claimants in liquidation should be prevented from filing payment claims.29It is also consistent with the Victorian Court of Appeal Victorian position which had stated that the Act does not apply to companies in liquidation.30On the other hand, the reforms are inconsistent with the NSW Court of Appeal which termed the Victorian decision as wrong.31 Shortened terms of payment and reforms in the adjudication process Under section 11(1B)(a), the Amendment Act has reduced the previous maximum period given to the head contractor within which they must make progress payments to subcontractors.32 The reforms in this section have significant effects on both subcontractors and head contractors cash flows. While the original act did not have provisions for withdrawing of claims, the Amendment Act will permit claimants to withdraw their adjudication applications any time prior to the appointment of the adjudicator. Further, the new amendments will leave out the wording contained in section 21(3)(a) of the original act. On this section, the amendments extend adjudicators’ the time frame for making their adjudication determination to 10 business days from the date of the application for the adjudication response. The original act instead gave the adjudicators 10 business days after their notification to the respondent and the claimant about the acknowledgment of the application.33The Amendment Act also adds section 32A. This section grants the Supreme Court the powers that are necessary for setting aside a part of the 29Murray, above n 16. 30Façade Treatment Engineering Pty Ltd (In Liq) v Brookfield Multiplex Constructions Pty Ltd (2016) 247 VSCA. 31Seymour Whyte Constructions Pty Ltd v Ostwald Bros Pty Ltd (in liquidation)(2019) 11 NSWCA. 32Building and Construction Industry Security of Payment Act1999. 33Ibid.
adjudicators’ determination or the entire determination. Again, this follows Murray’s recommendations.34 The importance is given to investigations and enforcement The new amendments introduce Part 3A which provides provision for the appointment of the investigator in accordance with the Fair Trading Act.35The new amendments also provide for the establishment of the frameworks for investigation and enforcement decision as well as compliance with the act. The Amendment Act also introduces section 28A which grants the minister the powers of creating and enforceable rules for Authorised Nominating Authorities (ANA). These reforms provide subcontractors with confidence in the recovery of their payments or the head contractors’ compliance with the law. Increasing penalties in certain offenses The new amendments have increase penalties units on some offenses. For instance, unlike in the original act where section 13(7) provides for 200 penalty units on corporations that fail to provide supporting statements when serving payment claims, the new amendments has increased the units to 1,000. Again, these reforms provide confidence to subcontractors, and they also encourage the head contractor to comply with the law. Conclusion The Amendment Act will provide greater benefits as well as offer legal protection to suppliers and subcontractors who could suffer unjust actions in the hands of head contractors under the construction contract. While the effects of these proposed amendments are yet to be realized, the NSW government hopes to provide a solution to the increasing number of cases. Also, even though the amendments seem to favor subcontractors, it will also invariably strike a 34Murray, above n 16. 35Fair Trading Act198718.
balance in the industry especially between the rival interests of the different stakeholders within the industry.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Bibliography (a)Books, Journals/Reports Bailey, Julian,Construction Law.(Taylor and Francis, 2014) Brand, Michael C and Thomas E Uher, ‘Review of the Performance of Security of Payment Legislation in New South Wales’ inRICS Construction and building research conference COBRA(2008) Brand, Michael C and Philip Davenport, ‘Proposal for a “Dual Scheme” Model of Statutory Adjudication for the Australian Building and Construction Industry’ [2011]International Journal of Law in the Built Environment <https://www.emerald.com/insight/content/doi/10.1108/17561451111178452/full/html> Burr, Andrew,International Contractual and Statutory Adjudication(Taylor & Francis, 2017) Commonwealth of Australia,Insolvency in the Australian Construction Industry: ‘I Just Want to Be Paid’(2015) <https://www.aph.gov.au/Parliamentary_Business/Committees/Senate/Economics/ Insolvency_construction/Report/> Murray, John,Review of Security of Payment Laws: Building Trust and Harmony(Department of Jobs and Small Business, 2017) (b) Cases Audi Construction Pte Ltd v Kian Hiap Construction Pte Ltd(2018) 4 SGCA Barclay Mowlem Construction Ltd v Tesrol Walsh Bay Pty Ltd(2004) 2004 NSWSC Brodyn Pty Ltd t/as Time Cost and Quality v Davenport & Anor(2003) 394 NSWCA Façade Treatment Engineering Pty Ltd (In Liq) v Brookfield Multiplex Constructions Pty Ltd (2016) 247 VSCA Seymour Whyte Constructions Pty Ltd v Ostwald Bros Pty Ltd (in liquidation)(2019) 11 NSWCA Southern Han Breakfast Point Pty Limited (in liq) v Lewence Construction Pty Limited(2016) 5 HCA (c) Legislations Building and Construction Industry Security of Payment Act1999 Fair Trading Act1987
NSW Fair Trading,Security of Payment Reforms(27 August 2018) Fair Trading NSW <https://www.fairtrading.nsw.gov.au/consultation-tool/security-of-payment-reforms>