New Online Cash Marketplace Platform i-Crop Project Management
Verified
Added on 2023/06/07
|13
|2446
|273
AI Summary
Design, development, and deployment of i-crop system will be done in 86 days to achieve enhancement in profits/revenues, and exchange of goods by 35% and 45% respectively. Check out the project management plan, scope, resources, work breakdown structure, schedule, risk register, quality management plan, and annotated bibliography.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
New Online Cash Marketplace Platform i-Crop Table of Contents Part I......................................................................................................................................................2 Area of Impact...................................................................................................................................2 Values................................................................................................................................................2 MOV Metrics....................................................................................................................................2 Timeframe.........................................................................................................................................2 Summary...........................................................................................................................................2 Part II.....................................................................................................................................................3 Project Scope.....................................................................................................................................3 Scope Management Plan....................................................................................................................3 List of Resources...............................................................................................................................3 Details of Resources..........................................................................................................................4 Part III...................................................................................................................................................5 Project Work Breakdown Structure...................................................................................................5 Project Schedule – Milestones, Resources, Tasks, Budget, and Duration..........................................6 PART IV...............................................................................................................................................7 Assumptions......................................................................................................................................7 Risk Register – Identification, Analysis, Treatment..........................................................................7 Part V....................................................................................................................................................8 Quality Management Plan.................................................................................................................8 Quality Statement..........................................................................................................................8 Verification and Validation Activities...........................................................................................8 Part VI...................................................................................................................................................9 Annotated Bibliography....................................................................................................................9 Closure Checklist...............................................................................................................................9 Project Evaluation Outline.................................................................................................................9 References...........................................................................................................................................10 Appendix.............................................................................................................................................11 Annotated Bibliography...................................................................................................................11 1
New Online Cash Marketplace Platform i-Crop Part I Area of Impact AreaRank Strategy3 Customer1 Financial4 Operational5 Social2 Values Two types of values that will be generated from the project are: Better: Buying and selling of warehoused grain, quality of service Faster: Operational and processing speed, response time MOV Metrics StakeholdersTargetExpectations – Value Project Team (Virtucon)GoodFeedbackfromthe Client Rating on 9+ one a scale on 10 Globex CorpIncreasedprofitsand revenues Increase by at least 35% End-UsersIncreased buying and selling of warehoused grain Increase by at least 45% Timeframe 86 Days Summary Design, development, and deployment of i-crop system will be done in 86 days to achieve enhancement in profits/revenues, and exchange of goods by 35% and 45% respectively. 2
New Online Cash Marketplace Platform i-Crop Part II Project Scope The scope of the project will include the feasibility study, requirements analysis, project planning,systemdesigning,systemdevelopment,integration,changemanagement, implementation, deployment, and closure activities. The members in the project team will not negotiate on the terms of services and agreement. This will be entirely done by the senior management of the organization (Fageha & Aibinu, 2013). Scope Management Plan The scope of the project will be managed using PMBOK approach for project management. The Project Board and management committee will carry out reviews at regular intervals to keep the project scope on track. The changes in the scope will be confirmed by Globex and additional timeframe and budget will be provided to make the changes. List of Resources Resource NameTypeInitialsMax. UnitsStd. RateOvt. Rate Ansar Ali SiddiquiWorkPM100%$90.00/hr$0.00/hr Kush DesaiWorkBA100%$85.00/hr$0.00/hr Renu DeshwalWorkDev100%$80.00/hr$0.00/hr Abhishek ChauhanWorkDes100%$78.00/hr$0.00/hr Akash WaghrayWorkCod100%$76.00/hr$0.00/hr Tools & EquipmentMaterialT$15,650.00 3
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
New Online Cash Marketplace Platform i-Crop Details of Resources 4
New Online Cash Marketplace Platform i-Crop Part III Project Work Breakdown Structure The Work Breakdown Structure for i-Crop project has been shown below. It is a hierarchical structure that comprises of packages and sub-packages that will be involved in the project. The diagram below is a 3-level diagram and there is a milestone that has also been included for each of the five major packages in the project. 5
New Online Cash Marketplace Platform i-Crop Project Schedule – Milestones, Resources, Tasks, Budget, and Duration The total timeframe estimated for the project is 86 days. The project will be completed in five phases and the resources engaged with the project will perform the roles of Project Manager, Business Analyst, Web Developer, Web Designer, and Web Coder. There are costs that will be needed to complete the project activities. Some of the tools and equipment that will be required will include the computer systems for carrying out the design, development, and deployment activities along with development tools, design tools, and testing tools (Zwikael, 2009). A database will also be needed to store the information and integrate it with the system. The total cost that is estimated is $107,722. 6 New Online Cash Marketplace Platform - i-Crop Project Initiation Feasibility Analysis - Technical Features and Aspects Feasibility Analysis - Operational Features and Aspects Feasibility Analysis - Financial Features and Aspects Chartering Processes Submission of the Results Milestone 1: Project Charter Document Requirements Analysis & Project Planning Information collection and analysis Project requirements analysis Identification of the scope Estimations Management & Planning of communications and risks Allocation of Roles & Responsibilities Milestone 2: Project Plan Project Execution Procurement of tools and equipment Design of the system Development of the system Database set up Network Integration Unit Testing Milestone 3: Source Code Project Control Supervisor review Management and planning of the changes Final Review Submission of the Results Milestone 4: Supervisor Report Closure Phase Ethical analysis Documentation activities Sign offs and acceptance Lessons acquired Submission of the closure report Milestone 5: Closure Report
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
New Online Cash Marketplace Platform i-Crop PART IV Assumptions The project business case will be provided to Virtucon by Globex listing out the highlights of the requirements. The Globex representative will be available at the time of communications. The project will be done in 86 days. The project will be completed within the budget allocated. Risk Register – Identification, Analysis, Treatment Risk NamePhaseDescriptionMember AssignedManagement Strategy Security RisksInitiationAttacks on the security of the information associated with the project to hamper theconfidentialityofthe data Renu Deshwal, Ansar Ali Siddiqui Riskavoidance and mitigation Communication Risks PlanningUnavailabilityofthe stakeholders at the time of requirement gathering and Ansar Ali SiddiquiRisk avoidance 7
New Online Cash Marketplace Platform i-Crop planningleadingto incorrectestimations (Peixoto,Tereso, Fernandes&Almeida, 2014) Technical FaultsExecutionFailure of a technical tool or equipment AbhishekChauhan and Akash Waghray Risk transfer Scope InflationControlIntroductionoftoomany changes in the scope at the time of implementation Ansar Ali SiddiquiRisk mitigation Quality RisksClosureInabilitytomaintainthe qualitystatusuptothe mark(Sanchez,Robert, Bourgault&Pellerin, 2009) Kush DesaiRiskavoidance and mitigation Part V Quality Management Plan Quality Statement Management of project quality using PMBoK guidelines to attain maximum user satisfaction and experience by offering them i-Crop system without any bugs and with the inclusion of functional and non-functional requirements Verification and Validation Activities The verification and validation activities that will be carried out will include the conduction of testing processes as functional testing, usability testing, performance testing, security testing, and regression testing (Milunovic & Filipovic, 2013). Reviews, walkthroughs, and inspections will also be conducted to make sure that there are no deviations from scope, ethical codes, quality standards, and legal policies. 8
New Online Cash Marketplace Platform i-Crop Part VI Annotated Bibliography Closure Checklist Schedule Variance: Variance/gaps between the actual and estimated values of project schedule shall be nil and must be calculated using Earned Value Analysis (EVA) method (Kamau, 2015). Cost Variance: Variance/gaps between the actual and estimated values of project costs shall be nil and must be calculated using Earned Value Analysis (EVA) method. Open Defects: None of the defects must be in the open status. Requirements Backlog: The backlog should be empty at the time of the release (Zohrehvandi, Khalilzadeh, Hajizadeh & Cheraghi, 2017). Sing-offs on deliverables: Globex must provide sign offs on the entire project deliverables before it may be considered as closed (Zidane, Johansen & Ekambaram, 2015). Project Evaluation Outline StakeholdersTargetExpectations – ValueEvaluation Method ProjectTeam (Virtucon) Good Feedback from the Client Ratingon9+onea scale on 10 360-degree feedback Globex CorpIncreasedprofitsand revenues Increasebyatleast 35% Cost-benefit analysis,Internal Rate of Return End-UsersIncreased buying and selling of warehoused grain Increasebyatleast 45% Sales Reports 9
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
New Online Cash Marketplace Platform i-Crop References Fageha,M.,&Aibinu,A.(2013).ManagingProjectScopeDefinitiontoImprove Stakeholders’ Participation and Enhance Project Outcome.Procedia - Social And Behavioral Sciences,74, 154-164. doi: 10.1016/j.sbspro.2013.03.038 Kamau, C. (2015). Efficacy of Monitoring and Evaluation Function in Achieving Project Success in Kenya: A Conceptual Framework.Science Journal Of Business And Management,3(3), 82. doi: 10.11648/j.sjbm.20150303.14 Milunovic, S., & Filipovic, J. (2013). Methodology for quality management of projects in manufacturing industries.Total Quality Management & Business Excellence,24(1-2), 91-107. doi: 10.1080/14783363.2012.728851 Peixoto, J., Tereso, A., Fernandes, G., & Almeida, R. (2014). Project Risk Management Methodology:ACaseStudyofanElectricEnergyOrganization.Procedia Technology,16, 1096-1105. doi: 10.1016/j.protcy.2014.10.124 Sanchez, H., Robert, B., Bourgault, M., & Pellerin, R. (2009). Risk management applied to projects, programs, and portfolios.International Journal Of Managing Projects In Business,2(1), 14-35. doi: 10.1108/17538370910930491 Zidane, Y., Johansen, A., & Ekambaram, A. (2015). Project Evaluation Holistic Framework – Application on Megaproject Case.Procedia Computer Science,64, 409-416. doi: 10.1016/j.procs.2015.08.532 Zohrehvandi, S., Khalilzadeh, M., Hajizadeh, M., & Cheraghi, E. (2017). Planning project closure phase in combined cycle power plant projects.Procedia Computer Science, 121, 274-281. doi: 10.1016/j.procs.2017.11.038 Zwikael, O. (2009). The Relative Importance of the PMBOK® Guide's Nine Knowledge Areas during Project Planning.Project Management Journal,40(4), 94-103. doi: 10.1002/pmj.20116 10
New Online Cash Marketplace Platform i-Crop Appendix Annotated Bibliography Kamau, C. (2015). Efficacy of Monitoring and Evaluation Function in Achieving Project Success in Kenya: A Conceptual Framework.Science Journal Of Business And Management,3(3), 82. doi: 10.11648/j.sjbm.20150303.14 There are various critical success factors (CSFs) associated with a project which are used to evaluate and measure the project success. Monitoring & Evaluation function is one such factor that is measured to understand the project success and gaps. The author in the research workhasmadeuseofqualitativeapproachandliteraturereviewtounderstandthe significance of monitoring and evaluation function in project closure and evaluation of project success. There are four stages that have been defined and described in association with the function, such as strength of the resources that are involved, monitoring strategy that is adopted, political influence, and lifecycle of the project that is being monitored and evaluated. The support from the management committee and resources is one of the essential and required factors that play an important role in determining the overall project success. The monitoring and evaluation function that does not have a good management support is likely to fail. There are only two figures used in the research which is one area that could have been improved upon. Zidane, Y., Johansen, A., & Ekambaram, A. (2015). Project Evaluation Holistic Framework – Application on Megaproject Case.Procedia Computer Science,64, 409-416. doi: 10.1016/j.procs.2015.08.532 Project closure is a mandatory phase in a project and shall be carried out to make sure that the project has a positive impact, it is sustainable, and has enhanced effectiveness. The authors have used these three parameters as the primary points for measuring the closure and evaluation of the project. The authors have carried out a research on project closure in large- scale projects that may have higher number of complexities and have selected Algerian highway project case study that has been selected to describe the scientific procedure that may be used for closing such projects. The creators have recommended that a staged approach will be taken after including primer and progress arranging stages alongside the end of the undertaking on the angles as legitimate, monetary, physical, and legally binding. The creators have utilized quantitative strategy as the approach for doing the examination work 11
New Online Cash Marketplace Platform i-Crop and have incorporated the required graphical components to improve the outcomes included. Zohrehvandi, S., Khalilzadeh, M., Hajizadeh, M., & Cheraghi, E. (2017). Planning project closure phase in combined cycle power plant projects.Procedia Computer Science, 121, 274-281. doi: 10.1016/j.procs.2017.11.038 There are several processes and phases that are involved in a project. One of the essential phases in the project is the closure phase. In large-scale projects, there are several issues that come up in terms of budget issues, disputes, claims, and many more. The authors have carried out a research on project closure in mega-projects and have presented their results in the research work. Combined Cycle Power Plant (CCPP) is the mega-project case study that has been selected to describe the scientific procedure that may be used for closing such projects. The authors have suggested that a phased approach shall be followed comprising of preliminary and transition planning phases along with the closing of the project on the aspects as legal, financial, physical, and contractual. The authors have used quantitative methodology as the approach for carrying out the research work and have included the required graphical elements to enhance the results included. 12